Damage Sustained by Our Group and Resumption of Operations Following the 2026 Kumamoto Earthquake (Second Report)

The Kumamoto-area facility of the subsidiary affected by the Kumamoto earthquake repaired equipment and machinery that had shifted out of position, among other damage, and resumed operations on 5 August 2026.

Worth reading
63In focus
Scored from 3 of 5 sections
Direction
Mixed performance
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Definitive
How definitive the wording is.

Damage Sustained by Our Group and Resumption of Operations Following the 2026 Kumamoto Earthquake (Second Report)

Subject Entity

フェローテックテクノロジーデベロップメントジャパン株式会社

Target Locations / Products

Kumamoto-area facility (precision parts reconditioning and cleaning services for equipment used at semiconductor manufacturing plants)

OccurrenceAround 16:27 on 28 July 2026
This disclosure08/05/2026
Cause

An earthquake estimated at magnitude 7.1, with a maximum seismic intensity of 7, centered in the Kumamoto region of Kumamoto Prefecture

Company response

Scheduled resumption date

5 August 2026 (operations have resumed)

Outlook

If any material event requiring disclosure is identified, a further announcement will be made.

Planned follow-up disclosure

A further announcement will be made if any material event is identified.

Event that occurred
ItemDetails
Event nameDamage Sustained by Our Group and Resumption of Operations Following the 2026 Kumamoto Earthquake (Second Report)
Date of occurrenceAround 16:27 on 28 July 2026
Subject Entityフェローテックテクノロジーデベロップメントジャパン株式会社
Target Locations / ProductsKumamoto-area facility (precision parts reconditioning and cleaning services for equipment used at semiconductor manufacturing plants)
CauseAn earthquake estimated at magnitude 7.1, with a maximum seismic intensity of 7, centered in the Kumamoto region of Kumamoto Prefecture
Scheduled resumption date5 August 2026 (operations have resumed)
OutlookIf any material event requiring disclosure is identified, a further announcement will be made.
Planned follow-up disclosureA further announcement will be made if any material event is identified.
Items this document does not state (17)
Date recognized / date notice receivedAmount of Impact on Business PerformanceAccounting period in which recognizedImpact on Earnings ForecastType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionSuspended operationsInvestigation structureMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the change

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The earthquake that occurred on 28 July 2026 caused physical damage, but operations resumed because repairs had been underway since immediately after the earthquake.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Damage Sustained by Our Group and Resumption of Operations Following the 2026 Kumamoto Earthquake (Second Report) | Ferrotec Corporation (6890) timely disclosure | Komori