Strategic clarification and reform of the group's production framework
First written in FY2016. 15 of 24 entries say "Advanced", first in FY2018-Q1. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026Increase in investment and delay in completionAnnual report
「Due to a review of the capital investment plan and other factors, the planned investment amount has changed from ¥1,200 million to ¥1,391 million. Due to delays in the construction schedule and other factors, the scheduled completion month has changed from July 2026 to December 2026.」
For the production equipment in Tono, Iwate, the planned investment amount was increased from ¥1.2 billion to ¥1.391 billion, and the scheduled completion was postponed from July 2026 to December of the same year. - 2026-06-04AdvancedGeneral Meeting of Shareholders
「当連結会計年度における設備投資額は783百万円で、主なものは、岩手東亜DKKの新工場棟建設工事、生産・研究開発設備の更新です。」
岩手東亜DKKの新工場棟建設工事を含む設備投資の実施を記載した。 - FY2025AdvancedAnnual report
「Reporting company | Equipment leased to an affiliated company (Tono, Iwate) | Measurement equipment business | Production equipment | Planned investment amount ¥1,200 million | Funding method: Internal funds | Start of construction: July 2025 | Completion: July 2026」
Following completion and the start of operations at the Sayama Integration Center, a plan was presented to install equipment costing ¥1.2 billion at an affiliated company in Tono, Iwate. - FY2025-H1AdvancedAnnual report
「Construction in progress: ¥2,175 million, due to the commencement of operations at the Sayama Integration Center and other factors」
The completed Sayama Integration Center was reported to have commenced operations, indicating progress from construction to the operational stage. - FY2024AchievedAnnual report
「For the Sayama Integration Center, for which the planned investment amount was ¥3,000 million and the scheduled completion month was June 2024, the scheduled completion month has changed from July 2024 to June 2024. The new facility had been completed as of the date of submission of the annual securities report.」
For the Sayama Integration Center, which had been under construction, completion was brought forward to June 2024, and the new facility had been completed as of the submission date. - FY2024-Q3AdvancedAnnual report
「This was primarily due to increases of ¥1,845 million in construction in progress, ¥965 million in inventories, ¥678 million in investment securities and ¥371 million in electronically recorded monetary claims, and decreases of ¥2,704 million in cash and deposits, ¥608 million in notes and accounts receivable and contract assets, and ¥135 million in deferred tax assets, among other factors.」
Construction in progress increased by ¥1,845 million, indicating further progress from the previous quarter in investment to develop the production framework, including the new production building. - FY2024-Q2AdvancedAnnual report
「This was primarily due to increases of ¥1,105 million in construction in progress and ¥774 million in inventories, and decreases of ¥1,216 million in cash and deposits, ¥791 million in notes and accounts receivable and contract assets, and ¥222 million in electronically recorded monetary claims, among other factors.」
Construction in progress increased by ¥1,105 million, indicating further progress from the previous quarter in investment to develop the production framework, including the new production building. - FY2024-Q1AdvancedAnnual report
「This was primarily due to increases of ¥1,043 million in construction in progress, ¥572 million in inventories, ¥129 million in investment securities and ¥100 million in electronically recorded monetary claims, and decreases of ¥1,546 million in cash and deposits and ¥767 million in notes and accounts receivable and contract assets, among other factors.」
Construction in progress increased by ¥1,043 million, providing financial confirmation that investment in developing the production framework, including the new production building, is progressing. - FY2023Increase in investment and postponement of completionAnnual report
「The planned investment amount has changed from ¥2,700 million to ¥3,000 million. Due to delays in the construction schedule and other factors, the scheduled completion month has changed from February 2024 to July 2024.」
For the new production building, the planned investment amount was increased from ¥2.7 billion to ¥3.0 billion against a backdrop of soaring material prices and other factors, while the scheduled completion was postponed from February 2024 to July of the same year. - FY2023-Q3RestatedAnnual report
「We also began construction of the new production building included in the medium-term management plan and initiated business process reforms through digital transformation.」
It was again stated that construction of the new production building had begun, together with business process reforms through digital transformation. - FY2023-Q2RestatedAnnual report
「We also began construction of the new production building included in the medium-term management plan and initiated business process reforms through digital transformation.」
It was stated that construction of the new production building had begun as an initiative under the medium-term management plan, continuing from the previous quarter. - FY2023-Q1AdvancedAnnual report
「We also began construction of the new production building included in the medium-term management plan and initiated business process reforms through digital transformation.」
Construction of the new production building included in the new medium-term management plan progressed from the planning and resolution stage to the actual start of construction. - FY2022AdvancedAnnual report
「At an extraordinary meeting of the Board of Directors held on 8 December 2021, the company resolved to demolish the aging building at the Sayama Technical Center and construct a new production building. As a result, the carrying amount of the above assets was reduced to their recoverable amount, and the reduction of ¥52 million was recognized as an impairment loss under extraordinary losses.」
The company resolved to demolish the aging building and construct a new production building, and recognized an impairment loss of ¥52 million. The equipment plan for the new production building totals ¥2.7 billion, with completion scheduled for February 2024. - FY2022-Q3AdvancedAnnual report
「Sayama Technical Center (Sayama, Saitama) | Measurement equipment business | Production equipment | 2,700 | — | Internal funds | March 2022 | February 2024」
The company plans to install production equipment totaling ¥2.7 billion at the Sayama Technical Center, with work starting in March 2022 and completion scheduled for February 2024. It also stated that a resolution was adopted to demolish the aging building and construct a new production building, and that an impairment loss of ¥52 million was recognized. - FY2020-Q3RestatedAnnual report
「In addition, we obtained China's national performance certification for a new model of an automatic analyzer for total nitrogen and total phosphorus used in environmental water quality monitoring, while local production in China is also getting on track, and we are promoting business expansion.」
It was stated that the company continues to strengthen its production and business framework through certification of the new model for China and local production. - FY2020-Q2AdvancedAnnual report
「We obtained China's national performance certification for a new model of an automatic analyzer for total nitrogen and total phosphorus used in environmental water quality monitoring, and began local production in China to promote business expansion.」
The start of local production in China and the new model's certification indicated concrete progress in the production and business framework. - FY2019-Q3AdvancedAnnual report
「For China, we improved production capacity and production efficiency to respond to increased demand for water-effluent monitoring.」
It was stated that production capacity expansion and production efficiency improvements had been achieved in response to demand from China, indicating progress in developing the production framework. - FY2019-Q2RestatedAnnual report
「Improving production efficiency and expanding production capacity to respond to increased demand in China」
We continue to pursue production efficiency improvements and production capacity expansion in response to increased demand in China. - FY2019-Q1RestatedAnnual report
「We also focused on improving production efficiency and expanding production capacity to respond to increased demand in China, among other initiatives.」
We continue to pursue production efficiency improvements and production capacity expansion in response to increased demand in China. - FY2018AdvancedAnnual report
「As part of our production framework, we worked to improve production efficiency through process reviews and expand production capacity in response to increased demand in China.」
In response to increased demand in China, we advanced production efficiency improvements through process reviews and expanded production capacity. - FY2018-Q3AdvancedAnnual report
「Sales increased 14.9% year on year as a new production building dedicated to medical equipment began operations and full-scale mass production of the powder-type dialysate dissolving machine, a key product, commenced.」
For the medical equipment production building that was under construction through the previous quarter, concrete progress was indicated through the start of operations and the full-scale start of increased production of key products. - FY2018-Q2AdvancedAnnual report
「This was primarily due to increases of ¥560 million in construction in progress for the medical equipment production building and ¥256 million in inventories.」
For construction of the medical equipment production building, construction in progress amounted to ¥560 million. This increased from the ¥285 million previously reported, indicating progress in developing the production framework. - FY2018-Q1AdvancedAnnual report
「Construction in progress for the new medical equipment plant: ¥285 million」
Construction in progress for the new medical equipment plant increased by ¥285 million, indicating concrete progress in developing the production framework. This does not indicate completion. - FY2016First statedAnnual report
「Strategically clarify the group's production framework and carry out reforms.」
As an issue for FY2016, the company adopted a policy of clarifying the roles within the production framework and advancing reforms.