Resumption of manufacturing at other sites and early recovery after the fire at the Kofu Plant
First written in FY2024-Q2. 1 of 3 entries say "Restated". Latest entry: FY2025-H1.
No other company in this theme has enough history to compare yet.
- FY2025-H1AchievedAnnual report
「The restoration work following the September 2023 fire at the Techno Center of the Kofu Plant of group company 三工社 was completed in June 2024, and the Group's production system returned to its pre-fire state in July of the same year.」
The restoration work following the fire at the Techno Center of the Kofu Plant was completed in June 2024, and the production system returned to its pre-fire state from July of the same year. - FY2024-Q3RestatedAnnual report
「While continuing efforts toward the early recovery of operations from the fire at the Techno Center of the Kofu Plant of group company 三工社 in September 2023 and the recovery of business performance」
The Company continues efforts toward the early recovery of operations and business performance after the fire at the Kofu Plant. Even after operations resumed as of the filing date, it continues to aim to return to the pre-fire level. - FY2024-Q2First statedAnnual report
「As of the filing date, operations have resumed using buildings that escaped damage and facilities of the Group, and efforts are under way to return to the operating level before the fire as soon as possible.」
After the fire at the Kofu Plant, manufacturing and operations resumed using buildings that escaped damage and Group facilities, and efforts are under way to return to the pre-fire operating level as soon as possible.