Damage to 石川サンケン Caused by the 2024 Noto Peninsula Earthquake
First written in FY2024-Q3. 2 of 4 entries say "Mitigated", first in FY2025. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026MitigatedAnnual report
「In response to the Noto Peninsula Earthquake, which particularly severely damaged the Shika Plant of 石川サンケン株式会社 in January 2024, we completed the relocation of production facilities to other sites by the end of FY2025 while continuing production activities and minimizing the impact on customers.」
As a response to damage to the Shika Plant from the Noto Peninsula Earthquake, the relocation of production facilities to other sites was completed by the end of FY2025. - FY2025MitigatedAnnual report
「Production had fully resumed at all plants by 31 March 2024.」
Full production resumed by the end of March 2024 at the 3 石川サンケン plants damaged by the Noto Peninsula Earthquake. Meanwhile, the Shika Plant is being closed and production restructured because permanent use is considered difficult. - FY2025-H1MaterialisedAnnual report
「To promptly restore capital impaired by damage from the Noto Peninsula Earthquake that occurred on 1 January 2024, and to address shareholder returns, funding needs during the 2024 Medium-Term Management Plan period, and fundamental improvement of the financial position」
Damage from the Noto Peninsula Earthquake became an actual business and financial issue in the form of capital impairment, and measures including the sale of Allegro shares were implemented. - FY2024-Q3First statedAnnual report
「The 2024 Noto Peninsula Earthquake, which occurred on 1 January 2024 with its epicenter in Ishikawa Prefecture, caused damage including breakage to equipment at our consolidated subsidiary 石川サンケン株式会社. The main affected assets were buildings and structures, machinery, equipment and vehicles, and inventories including products. The amount of damage is currently being assessed in detail.」
The Noto Peninsula Earthquake damaged buildings, machinery and equipment, inventories and other assets at 石川サンケン. The amount of damage is still under review, and the company stated that the amount of the impact cannot yet be reasonably estimated.