DMWインド社: New Plant in India and Expansion of Small Pump Production Capacity
First written in FY2017. 6 of 9 entries say "Advanced", first in FY2018. Latest entry: FY2026.
0 other companies' latest entry also says "Other".
- FY2026Update to annual capital expenditure resultsAnnual report
「Total capital expenditure was ¥874 million, mainly for the construction and refurbishment of production equipment at the Mishima facility.」
Capital expenditure was updated from ¥654 million in the previous fiscal year to ¥874 million. Investment was carried out mainly for the construction and refurbishment of production equipment at the Mishima facility. - FY2024AdvancedAnnual report
「Total capital expenditure was ¥631 million, mainly for the construction and refurbishment of production equipment at the Mishima facility and the expansion of equipment at DMW India’s plant.」
The report states that capital expenditure, including the expansion of equipment at DMW India’s plant, was carried out during the year. - FY2023AdvancedAnnual report
「DMW India Indian plant India (Pune) Manufacturing equipment for pumps and other products, etc. 400 201 Internal funds April 2022 June 2023 Strengthening the production system for overseas markets」
Regarding the expansion of equipment at the Pune plant, the report describes a plan for total planned investment of ¥400 million, ¥201 million already paid, completion scheduled for June 2023, and strengthening the production system for overseas markets. - FY2020AdvancedAnnual report
「July 2019: DMW India (now a consolidated subsidiary) carried out a capital increase to expand equipment at its Pune plant」
Following the establishment of the Pune plant in July 2017, the report states that a capital increase was carried out in July 2019 to expand its equipment. - FY2019RestatedAnnual report
「DMW India India Plant (Pune) Manufacturing equipment for pumps and other products, etc.」
The manufacturing equipment at DMW India’s Pune plant, established in July 2017, continues to be listed as major equipment. - FY2018AdvancedAnnual report
「July 2017: DMW India (now a consolidated subsidiary) established a new plant in Pune」
Regarding the previously planned Pune plant of DMW India, the report states that it was newly established in July 2017 and records ¥162 million for the building and ¥127 million for machinery and equipment. - FY2017First statedAnnual report
「Manufacturing equipment for pumps and other products, etc. Total planned investment: ¥345.003 million. Start: March 2016. Completion: August 2017. Small-pump production capacity is expected to increase.」
The report describes a plan to invest ¥345.003 million in the Pune, India plant and increase small-pump production capacity, with completion scheduled for August 2017.