Accelerating New Ways of Working and Investment in New Technologies and Businesses Through the Transfer of Headquarters Assets
First written in FY2024-Q3. 1 of 3 entries say "Advanced", first in FY2024. Latest entry: FY2025.
1 other company's latest entry also says "Achieved".
- FY2025AchievedAnnual report
「In December 2024, the headquarters and Integrated Engineering Center will relocate to 1-1 Nakase, Mihama Ward, Chiba City, Chiba Prefecture, which will also become the registered head office, and the Tokyo head office (registered office) will be renamed the Tokyo Office.」
The relocation of the headquarters and Integrated Engineering Center was completed in December 2024, establishing a base for new ways of working. - FY2024AdvancedAnnual report
「The transfer date for the land is 27 March 2024, and the scheduled transfer date for the buildings and structures is 31 December 2024.」
The transfer of the 35,870 m² headquarters site in Narashino City was completed on 27 March 2024, while the scheduled transfer of the buildings and structures remains 31 December 2024. The headquarters is scheduled to relocate to the Makuhari Technical Center, with the Company pursuing new ways of working and accelerated investment in new technologies and businesses. - FY2024-Q3First statedAnnual report
「1. Reasons for the transfer ・Effective use of owned assets and realization of new ways of working to support further growth ・Acceleration of investment in new technologies and businesses, including carbon neutrality 2. Overview of assets to be transferred Land (35,870 m²)* Buildings and structures 2-8-1 Akanehama, Narashino City, Chiba Prefecture Headquarters office (to be relocated) 3. Transfer schedule Land Scheduled transfer date: 27 March 2024 Buildings and structures Scheduled transfer date: 31 December 2024 4. Impact on profit or loss and consolidated profit or loss In the consolidated and non-consolidated financial results for the fourth quarter of the fiscal year ending March 2024, the transfer of these assets is expected to result in a gain on transfer, calculated by deducting the carrying amount and various transfer-related costs from the transfer price, together with an impairment loss on fixed assets related to the headquarters office currently in use, for an estimated net extraordinary gain of approximately ¥4.9 billion.」
The Company decided to transfer its 35,870 m² headquarters site and its buildings and structures in Narashino City. The land was scheduled for transfer on 27 March 2024 and the buildings and structures on 31 December 2024. The reasons cited were the effective use of assets, the realization of new ways of working, and accelerated investment in new technologies and businesses, including carbon neutrality. An extraordinary gain of approximately ¥4.9 billion is expected.