Scale-up and Commercialization of the ACES21® Urea Process
First written in FY2016. 8 of 10 entries say "Advanced", first in FY2018. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026AdvancedAnnual report
「In fiscal 2025, the company’s technology was adopted for a urea plant planned by a Nigerian fertilizer producer, comprising 4,000 t/day x 2 trains.」
For ACES21™, adoption was demonstrated at a urea plant in Nigeria comprising a total of 4,000 t/day x 2 trains. The first application of ACES21-LP™ to a project in Indonesia is also continuing. - FY2025AdvancedAnnual report
「In fiscal 2024, the company won an order for a urea licensing project for a 4,000 t/day urea plant in the Republic of Angola.」
In relation to ACES21, the company won an order for a licensing project for a 4,000 t/day urea plant in the Republic of Angola. - FY2024AdvancedAnnual report
「In fiscal 2023, the company won an order for a urea licensing project for a fertilizer plant in Indonesia using ACES21®. This facility is scheduled to be the first to apply the ACES21-LP® design.」
ACES21-LP® has progressed from the stage of process improvement and announcement to its first application in a licensing project for a fertilizer plant in Indonesia. - FY2023AdvancedAnnual report
「During the year, the company completed performance testing and began commercial operations at the 3,850 t/day urea production facility in India using the ACES21® process.」
The 3,850 t/day ACES21®-related facility in India completed performance testing and began commercial operations. The company also announced ACES21-LP®, which combines low-pressure synthesis technology, and is pursuing its application to larger-scale, energy-saving facilities. - FY2021AdvancedAnnual report
「Commissioning of Train 2 of the 4,000 t/day Nigerian urea production facility, which has the world’s largest production capacity, began in April 2021 ahead of handover. Construction of the 3,850 t/day urea production facility in India is also progressing, with operations scheduled to begin during fiscal 2021.」
For ACES21®-related projects, commissioning of Train 2 of the 4,000 t/day Nigerian facility began ahead of its April 2021 handover, and construction of the 3,850 t/day Indian facility is under way for start-up during fiscal 2021. - FY2020AdvancedAnnual report
「Construction is under way on the 3,850 t/day urea production facility in India and Train 2 of the 4,000 t/day urea production facility in Nigeria, following Train 1 delivered in fiscal 2017, with both scheduled to begin operations in the second half of fiscal 2020.」
For ACES21®-related facilities, construction of the 3,850 t/day facility in India and Train 2 of the 4,000 t/day facility in Nigeria is under way, with operations scheduled to begin in the second half of fiscal 2020. - FY2019AdvancedAnnual report
「In July 2018, the company handed over to the customer a 1,725 t/day urea production facility in Indonesia, and in February 2019, it handed over a fertilizer production plant in India comprising 2,000 t/day x 2 trains.」
For ACES21®-related facilities, the company handed over the 1,725 t/day facility in Indonesia and the 2,000 t/day, 2-train facility in India. It also won an order for Train 2 of the 4,000 t/day facility in Nigeria. - FY2018AdvancedAnnual report
「The ACES21® urea process is a leading proprietary process developed by the company, which continues to pursue process improvements to increase scale and save energy. Its optimization of energy consumption as a fertilizer complex was highly evaluated, and the company won an order for a fertilizer production facility in India with a urea capacity of 3,850 t/day.」
The company continues to improve ACES21® for greater scale and energy savings, and, following recognition of its optimized energy consumption, won an order for a 3,850 t/day urea facility in India. - FY2017AchievedAnnual report
「The ACES21® urea process and the company’s large-granular urea process, both leading proprietary processes developed by the company, have been adopted for a Nigerian urea production facility with the world’s largest production capacity as of the end of March 2017 (4,000 t/day), and commercial operations began in June 2016. Development of the process for an even larger plant (6,000 t/day) has also been completed.」
The 4,000 t/day Nigerian facility began commercial operations in June 2016, and process development for the large 6,000 t/day plant has also been completed. - FY2016First statedAnnual report
「The ACES21® urea process, a leading proprietary process developed by the company, has been adopted for a Nigerian urea production facility with the world’s largest production capacity (4,000 t/day), where commissioning began in May 2016 ahead of handover. Development of an even larger plant (6,000 t/day) has already been completed, and the start-up of the above urea production facility is expected to make a major contribution to its realization.」
The company states that commissioning began for the 4,000 t/day facility and that development of the large 6,000 t/day plant was also completed.