ProgressHeldSoftenedWorseAdvancedFY2017AdvancedFY2022 – 2026-07-102016: 120162017: 120172018: 020182019: 020192020: 020202021: 120212022: 120222023: 020232024: 120242025: 120252026: 22026
Same theme, other companies
Expansion and Rationalization of Production FacilitiesA theme 390 companies write about · 0 as a headwind · 430 as a tailwind
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 183 companies compared. The sentences above are computed from all 183.Comparing 200 of the theme's 430 threads.
Full recordFilings, disclosures and news, newest first
  1. 2026-07-10AdvancedOther Disclosures

    「米国ミシガン州にて新工場建設のための土地取得及び工場建設にかかる契約を締結いたしました。」

    北米では約3,300万米ドルの新工場投資、インドでは約3億円のサービス工場建設により、生産・サービス拠点の拡張が具体化された。
  2. FY2026AdvancedAnnual report

    「Additional large processing machinery, rationalization of the Tsukui Kousoku Machine Plant, and building reinforcement work at the Sagami and Tsukui plants」

    A ¥1,738 million capital investment plan was presented, focused on the Sagami and Tsukui plants and including additional large processing machinery, rationalization of the Tsukui Kousoku Machine Plant, and building reinforcement work.
  3. FY2025AdvancedAnnual report

    「Capital expenditures for the fiscal year totaled ¥1,146 million. Major capital expenditures by segment included ¥191 million for acquiring equipment and machinery at the Sagami Plant in the Japan segment and ¥213 million invested in business infrastructure to promote digital transformation.」

    Capital expenditures totaled ¥1,146 million, including ¥191 million for equipment at the Sagami Plant and ¥213 million for business infrastructure to promote digital transformation. Plans were also presented for ¥360 million of additional large processing machinery and ¥201 million for rationalizing the Tsukui Kousoku Machine Plant.
  4. FY2024AdvancedAnnual report

    「Capital expenditures for the fiscal year totaled ¥1,800 million. Major capital expenditures by segment included ¥546 million for expanding business systems in the Japan segment and ¥136 million for upgrading equipment and machinery at the Sagami Plant.」

    The results included total capital expenditures of ¥1,800 million, ¥546 million for expanding business systems, and ¥136 million for equipment and machinery at the Sagami Plant.
  5. FY2022AdvancedAnnual report

    「Capital expenditures for the fiscal year totaled ¥1,839 million. Major capital expenditures by segment included ¥274 million for rebuilding the Osaka Service Plant and ¥241 million for acquiring equipment and machinery at the Tsukui Plant in the Japan segment, and ¥457 million for acquiring processing machinery at the Malaysia plant in the Asia segment.」

    Specific results were presented for strengthening domestic and overseas production and service bases, including total capital expenditures of ¥1,839 million, rebuilding the Osaka Service Plant, acquiring equipment at the Tsukui Plant, and acquiring processing machinery at the Malaysia plant.
  6. FY2021RestatedAnnual report

    「Capital expenditures for the fiscal year totaled ¥597 million. Major capital expenditures by segment included the acquisition of equipment and machinery at the Sagami Plant in the Japan segment, amounting to ¥105 million, and ¥134 million invested in core systems to strengthen the management infrastructure.」

    Capital expenditures decreased to ¥597 million from the previous fiscal year, while investment in equipment and machinery at the Sagami Plant and in core systems continued.
  7. FY2017AdvancedAnnual report

    「The filing company planned to invest ¥1,000 million in plant construction, including land and buildings, from October 2017 through September 2018, and ¥361 million in large processing machinery and other equipment from February 2017 through March 2018.」

    Specific investment plans were presented, including domestic plant construction, large processing machinery, and facility expansions in Malaysia, China, the United States and Italy.
  8. FY2016First statedAnnual report

    「Capital expenditures for the fiscal year totaled ¥4,654 million. By segment, major capital expenditures included production equipment rationalization and additional processing machinery in the Japan segment, plant expansion and strengthening of production capabilities in the U.S. segment, and strengthening of production capabilities at the Malaysia plant in the Asia segment.」

    In addition to capital expenditures made during the year, plans for plant expansions and the introduction of large processing machinery in China, Malaysia, Italy and other locations were described.
Moved together

"Improving Lead-Time and Cost Competitiveness through Joint Production and Local Procurement of Large Custom-Built Equipment" moved the same way as this thread, in the same document, in 6 of its 8 moves.

666555★123456
  1. ★This thread
  2. 1Improving Lead-Time and Cost Competitiveness through Joint Production and Local Procurement of Large Custom-Built Equipment6×
  3. 2Increasing the adoption rate and in-house production of proprietary automated equipment6×
  4. 3Strengthening proposal-based services, including preventive maintenance and retrofits6×
  5. 4Pursuit of New Technologies in Near-Net-Shape Forming5×
  6. 5Development of Forming Systems for Aluminum and Ultra-High-Tensile Steel5×
  7. 6Enhancing Product Competitiveness Through the Evolution of Servo Presses and the Development of New Motors5×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Aida Engineering yet. It last moved in the Other Disclosures of 2026-07-10: "Advanced".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.