Construction of a new plant and after-sales service facility at the Harima Plant
First written in FY2020-Q2. 2 of 10 entries say "Advanced", first in FY2020. Latest entry: FY2023.
No other company in this theme has enough history to compare yet.
- FY2023AdvancedAnnual report
「January 2023 The new Harima Plant (Takasago, Hyogo) commenced operations.」
The new Harima Plant and after-sales service facility construction project, costing approximately ¥13 billion, commenced operations in January 2023. - FY2023-Q3Decrease in construction-related costsAnnual report
「Costs related to construction of the new plant 255 185」
¥185 million was recorded as an extraordinary loss for costs related to construction of the Harima Plant new plant and after-sales service facility, down from ¥255 million in the same period of the previous year. - FY2023-Q2Continued recording of construction-related costsAnnual report
「Extraordinary loss Costs related to construction of the new plant 167 112」
¥112 million was recorded as an extraordinary loss for costs related to construction of the new plant and after-sales service facility. - FY2023-Q1Continued recording of construction-related costsAnnual report
「Extraordinary loss Costs related to construction of the new plant 76 51」
¥51 million in costs related to construction of the new plant was recorded as an extraordinary loss in connection with construction of the Harima Plant new plant and after-sales service facility. - FY2022-Q3Increase in construction-related costsAnnual report
「Extraordinary loss Costs related to construction of the new plant - 255」
The amount of costs related to construction of the new plant recorded as an extraordinary loss in connection with the Harima Plant new plant and after-sales service facility construction project was ¥255 million. - FY2022-Q2Continued recording of construction-related costsAnnual report
「Extraordinary losses Costs related to construction of a new plant - 167」
Cumulative costs of ¥167 million related to construction of the new plant were recorded as an extraordinary loss in connection with the Harima Plant new plant and after-sales service facility construction project. - FY2022-Q1Recording of construction-related costsAnnual report
「Extraordinary loss Costs related to construction of the new plant - 76」
¥76 million in costs related to construction of the new plant was recorded as an extraordinary loss in connection with the Harima Plant new plant and after-sales service facility construction project. - FY2020AdvancedAnnual report
「Filing company Harima Plant (Amagasaki, Hyogo) Environment and energy (Japan) New plant and after-sales service facility Approx. 13,000 38 Internal funds August 2019 December 2022」
Progress on the Harima Plant new plant and after-sales service facility project was disclosed, with construction having begun in August 2019, ¥38 million already paid, and completion scheduled for December 2022. - FY2020-Q3RestatedAnnual report
「Harima Plant (Takasago, Hyogo) Environment and energy (Japan) New plant and after-sales service facility Approx. 13,000 1 Internal funds 2019 August 2022 December」
The plan to construct a new plant and after-sales service facility at the Harima Plant at a cost of approximately ¥13 billion continued to be disclosed, with construction scheduled to begin in August 2019 and be completed in December 2022. - FY2020-Q2First statedAnnual report
「Harima Plant (Takasago, Hyogo) Environment and energy (Japan) New plant and after-sales service facility Approx. 13,000 Internal funds August 2019 December 2022」
The Company newly decided to construct a new plant and after-sales service facility at the Harima Plant at a cost of approximately ¥13 billion, to establish a production system capable of meeting diversifying customer needs and an after-sales service system for the reliable and rapid supply of parts. Construction was scheduled to begin in August 2019 and be completed in December 2022.