Komori
Takuma (6013) · InitiativeLower order intake; projects ongoing

Expansion of orders for domestic waste treatment facilities and biomass power generation

First written in FY2017-Q1. 16 of 36 entries say "Softened", first in FY2018-Q1. Latest entry: FY2027-H1.

36entries
11years
2from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseSoftenedFY2022-Q1 – FY2023-Q3AdvancedFY2023 – FY2025-H12016: 220162017: 420172018: 420182019: 420192020: 420202021: 320212022: 320222023: 420232024: 320242025: 120252026: 42026
Same theme, other companies
Integrated EPC and O&M Services for the Environmental BusinessA theme 11 companies write about · 1 as a headwind · 12 as a tailwind

The whole theme swung hardest in 2022: 1 of 10 companies on the "Worse" side.

0 other companies' latest entry also says "Other".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2027-H1Lower order intake; projects ongoingAnnual report

    「During the current interim consolidated accounting period, the Company received orders for four core improvement projects at waste treatment plants, among others. However, order intake decreased by ¥54,046 million from the previous interim consolidated accounting period*, to ¥84,519 million, which had included orders for DBO projects (construction and operation projects), among others.」

    While the Company received orders for four core improvement projects at waste treatment plants, among others, order intake in the domestic Environment and Energy business declined following the previous interim consolidated accounting period's orders for large DBO projects and other work.
  2. FY2026AdvancedAnnual report

    「During the fiscal year under review, we continued working to capture solid demand and received orders for 5 new construction projects (replacement projects), mainly DBO projects for waste treatment plants, 2 major refurbishment projects and 4 new energy plant projects, among others. As a result, orders received increased by ¥73,916 million from the previous fiscal year to ¥288,709 million.」

    Orders in the domestic environment and energy businesses totaled ¥288,709 million, an increase of ¥73,916 million from the previous fiscal year.
  3. FY2026-H1Lower orders, but maintained at a high levelAnnual report

    「During the 6-month consolidated period under review, the Company received orders for 2 DBO projects for waste treatment plants and 2 new biomass power generation plant projects, among others. Orders totaled ¥138,566 million, a decrease of ¥6,223 million from the previous interim consolidated period*, but remained at a high level.」

    Although the Company received orders for 2 DBO projects and 2 new biomass power generation plant projects, orders in the domestic environment and energy businesses declined by ¥6,223 million year on year. However, the Company stated that the order level remained high.
  4. FY2025-H1AdvancedAnnual report

    「During the 6-month consolidated period under review, the Company received orders for 2 DBO projects for waste treatment plants, 1 major refurbishment project, 1 new biomass power generation plant project, and 1 sewage sludge incineration power generation plant project, among others. Orders increased by ¥87,606 million from the previous interim consolidated period* to ¥144,789 million.」

    The domestic environment and energy businesses received orders for 2 DBO projects, 1 major refurbishment project, 1 new biomass project, and 1 sewage sludge incineration power generation project, among others, resulting in an ¥87,606 million year-on-year increase in orders.
  5. FY2024AdvancedAnnual report

    「Revenue also increased by ¥3,204 million from the previous fiscal year to ¥119,190 million, mainly due to increases in EPC and after-sales service for waste treatment plants.」

    Increases in waste treatment plant EPC and after-sales service drove revenue growth in the domestic environment and energy businesses.
  6. FY2024-Q3AdvancedAnnual report

    「During the first 9 months of the current consolidated fiscal year, in addition to receiving orders for 1 waste treatment plant DBO project and 7 new energy plants, including biomass power plants, we received orders for a large-scale renewal project for sand filtration equipment at a sewage treatment plant and a sludge-incineration power plant, among others. Orders received increased by ¥49,913 million year on year to ¥115,031 million.」

    The domestic environment and energy businesses received orders for DBO projects, new energy plant construction, sand filtration equipment renewal, and sewage sludge incineration power generation, resulting in a year-on-year increase in orders.
  7. FY2024-Q2AdvancedAnnual report

    「During the 6-month consolidated period under review, the Company received orders for 4 new biomass power generation plant projects and 1 new biomass plant project for self-consumption, as well as a large-scale renewal project for sand filtration equipment for a sewage treatment plant. Orders increased by ¥12,006 million from the same period of the previous year to ¥57,183 million.」

    The domestic environment and energy businesses received orders for biomass power generation, biomass plants for self-consumption, and equipment for sewage treatment plants, bringing orders to ¥57,183 million, an increase of ¥12,006 million year on year.
  8. FY2024-Q1AdvancedAnnual report

    「During the first quarter of the current consolidated fiscal year, in addition to receiving orders for 2 new biomass power plants, orders received increased by ¥1,873 million year on year to ¥26,166 million, owing to increased orders for after-sales services such as waste treatment plant operations management and maintenance.」

    The domestic environment and energy businesses received orders for 2 new biomass power generation plant projects and after-sales service projects, bringing orders to ¥26,166 million, an increase of ¥1,873 million year on year.
  9. FY2023AdvancedAnnual report

    「Meanwhile, revenue increased by ¥7,328 million from the previous fiscal year to ¥115,985 million, and operating profit increased by ¥3,968 million to ¥14,875 million, due to changes in the project mix in the EPC business and the steady growth of stock-based businesses such as O&M and the new power business.」

    Although domestic orders declined, revenue and operating profit increased due to growth in stock-based businesses and other factors, advancing the earnings power of the domestic businesses.
  10. FY2023-Q3SoftenedAnnual report

    「Although the Company received orders for 1 major refurbishment project at a waste treatment plant, 1 long-term O&M project, 5 new biomass power generation plant projects, including fuel conversion, and 1 new industrial waste treatment plant project, orders decreased by ¥21,678 million from the same period of the previous year* to ¥65,117 million.」

    Although orders continued for waste treatment, biomass, and industrial waste treatment projects, orders in the domestic environment and energy businesses declined by ¥21,678 million year on year.
  11. FY2023-Q2SoftenedAnnual report

    「During the first 6 months of the current consolidated fiscal year, we continued working to capture firm demand and received orders for 1 waste treatment plant core improvement project and 5 new biomass power plants, including fuel-conversion projects. However, orders received decreased by ¥32,376 million from the same period of the previous year※ to ¥45,177 million.」

    Although the Company received specific waste treatment and biomass projects, orders in the domestic environment and energy businesses declined by ¥32,376 million, partly due to the reaction to the large projects received in the same period of the previous year.
  12. FY2023-Q1SoftenedAnnual report

    「During the first quarter of the current consolidated fiscal year, we continued working to capture firm demand and received orders for 1 waste treatment plant core improvement project and 2 new biomass power plants, among others. However, orders received decreased by ¥4,364 million from the same period of the previous year※ to ¥24,293 million.」

    Although specific waste treatment and biomass-related orders continued, orders in the domestic environment and energy businesses declined by ¥4,364 million compared with the same period of the previous year, when long-term O&M and other orders were received.
  13. FY2022-Q3SoftenedAnnual report

    「During the 9-month consolidated period under review, the Company continued efforts to capture firm demand and received orders for 1 DBO project for a waste treatment plant, 1 long-term O&M project, 2 biomass power generation plant construction projects, 1 industrial waste treatment plant construction project, and 1 large-scale renewal project for sand filtration equipment for a sewage treatment plant. However, partly due to the cancellation of a contract for 1 project received in a prior fiscal year following the discontinuation of the plan, orders decreased by ¥49,073 million from the same period of the previous year*, when numerous relatively large projects were received, to ¥86,795 million.」

    Although the Company received multiple domestic projects, domestic orders declined by ¥49,073 million due to the cancellation of a contract for 1 project received in a prior fiscal year following the discontinuation of the plan, as well as the reaction to the large projects received in the same period of the previous year.
  14. FY2022-Q2SoftenedAnnual report

    「During the 6-month consolidated period under review, the Company continued efforts to capture firm demand and received orders for 1 DBO project for a waste treatment plant (construction and operation), 1 long-term O&M project, and 2 biomass power generation plant construction projects. However, compared with the same period of the previous year, when it received numerous relatively large projects, including 3 new waste treatment plant construction projects, including DBO projects, and 2 major refurbishment projects, orders decreased by ¥25,968 million to ¥77,554 million.」

    Although the Company received orders for a waste treatment DBO project, long-term O&M, and biomass power generation construction, orders in the domestic environment and energy businesses declined by ¥25,968 million as a reaction to the large projects received in the same period of the previous year.
  15. FY2022-Q1SoftenedAnnual report

    「Although the Company received orders for 1 long-term O&M project for a waste treatment plant and 1 biomass power generation plant construction project, orders totaled ¥28,658 million, a decrease of ¥41,042 million from the same period of the previous year, when it received numerous relatively large projects, including 2 new waste treatment plant construction projects, including a DBO project, and 1 major refurbishment project.」

    Although specific orders continued, orders in the domestic environment and energy businesses declined by ¥41,042 million as a reaction to the large projects received in the same period of the previous year.
  16. FY2021-Q3AdvancedAnnual report

    「During the 9-month consolidated period under review, the Company continued efforts to capture firm demand and received orders for 3 new construction projects, including a DBO project for a waste treatment plant (construction and operation), 2 major refurbishment projects, 1 O&M project, and 1 biomass power generation plant construction project, as well as 1 sewage sludge incineration power generation plant construction project. Orders increased by ¥60,439 million from the same period of the previous year to ¥135,869 million. Revenue increased by ¥14,958 million to ¥87,133 million, mainly due to progress on the construction of plants for which orders had already been received, while operating profit increased by ¥1,936 million to ¥8,947 million.」

    The domestic environment and energy businesses received multiple waste treatment and power generation-related projects, resulting in year-on-year increases in orders, revenue, and operating profit.
  17. FY2021-Q2AdvancedAnnual report

    「During the 6-month consolidated period under review, the Company continued efforts to capture firm demand and received orders for 3 new construction projects, including a DBO project for a waste treatment plant (construction and operation), and 2 major refurbishment projects. Orders increased by ¥47,124 million from the same period of the previous year to ¥103,522 million.」

    The domestic environment and energy businesses received orders for 3 new construction projects and 2 major refurbishment projects, bringing orders to ¥103,522 million, an increase of ¥47,124 million year on year.
  18. FY2021-Q1AdvancedAnnual report

    「During the first quarter of the current consolidated fiscal year, we continued working to capture firm demand and received orders for 2 new construction projects, including a waste treatment plant DBO project, and 1 core improvement project. Orders received increased by ¥49,407 million year on year to ¥69,700 million.」

    The Company received specific waste treatment-related projects in the domestic environment and energy businesses, resulting in a substantial year-on-year increase in orders.
  19. FY2020SoftenedAnnual report

    「However, compared with the previous fiscal year, when the Company received multiple large-scale biomass power generation plant orders with output of approximately 50–75 MW, orders decreased by ¥30,473 million to ¥123,154 million.」

    Although the Company received specific orders, orders in the domestic environment and energy businesses declined by ¥30,473 million as a reaction to the large-scale biomass projects received in the previous fiscal year.
  20. FY2020-Q3SoftenedAnnual report

    「During the first 9 months of the current consolidated fiscal year, we received orders for 1 waste treatment plant equipment renewal project, 4 biomass power plant construction projects and 1 O&M project. However, orders received decreased by ¥17,968 million year on year to ¥75,430 million, compared with the same period of the previous year, when we received orders including waste treatment plant DBO projects.」

    Although the Company received specific orders, orders in the domestic environment and energy businesses declined by ¥17,968 million compared with the same period of the previous year, when it received orders including a DBO project.
  21. FY2020-Q2SoftenedAnnual report

    「During the 6-month consolidated period under review, the Company received orders for 1 equipment renewal project at a waste treatment plant and 2 construction projects for biomass power generation plants. However, orders totaled ¥56,398 million, a decrease of ¥20,652 million from the same period of the previous year, when the Company received orders for a DBO project for a waste treatment plant and other projects.」

    Although the Company received specific orders, orders in the domestic environment and energy businesses declined by ¥20,652 million compared with the same period of the previous year, when it received large orders including a DBO project.
  22. FY2020-Q1SoftenedAnnual report

    「During the 3-month consolidated period under review, orders totaled ¥20,293 million, a decrease of ¥2,731 million from the same period of the previous year, when the Company received orders for major refurbishment work at waste treatment plants and biomass power generation plants.」

    Although the Company received orders for major refurbishment work at waste treatment plants and biomass power generation plants, orders in the domestic environment and energy businesses declined by ¥2,731 million year on year.
  23. FY2019AdvancedAnnual report

    「During the current consolidated fiscal year, we received orders for 2 new construction projects, including a waste treatment plant DBO project, 3 core improvement projects, 1 equipment renewal project, and 8 construction projects and 1 O&M project for private-sector customers, including biomass power plants. Orders received increased by ¥4,735 million year on year to ¥153,628 million.」

    Orders in the domestic environment and energy businesses totaled ¥153,628 million, up 3.2% from the previous fiscal year, with multiple waste treatment and biomass-related projects secured.
  24. FY2019-Q3SoftenedAnnual report

    「During the 9-month consolidated period under review, the Company received orders for 2 new construction projects, including a DBO project for a waste treatment plant (construction and operation), 2 major refurbishment projects, and 1 equipment renewal project. For private-sector projects such as biomass power generation plants, it also received orders for 2 construction projects and 1 O&M project. However, orders totaled ¥93,399 million, a decrease of ¥34,842 million from the same period of the previous year, when the Company received orders for multiple large-scale biomass power generation plant construction projects.」

    Although the Company received specific orders, orders in the domestic environment and energy businesses declined by ¥34,842 million compared with the same period of the previous year, when it received orders for a large-scale biomass project.
  25. FY2019-Q2SoftenedAnnual report

    「During the first 6 months of the current consolidated fiscal year, we received orders for 2 new construction projects, including a waste treatment plant DBO project, 2 core improvement projects, and 1 construction project and 1 O&M project for biomass power plants. However, orders received decreased by ¥34,462 million year on year to ¥77,050 million, compared with the same period of the previous year, when we received orders for multiple large-scale biomass power plant construction projects.」

    Although the Company received specific orders, orders in the domestic environment and energy businesses declined by ¥34,462 million compared with the same period of the previous year, when it received an order for a large-scale biomass project.
  26. FY2019-Q1SoftenedAnnual report

    「During the first quarter of the current consolidated fiscal year, we received orders for 2 core improvement projects at waste treatment plants and 1 biomass power plant. However, orders received decreased by ¥41,731 million year on year to ¥23,024 million, compared with the same period of the previous year, when we received orders for a waste treatment plant DBO project and a large-scale biomass power plant.」

    Although the Company received orders for major refurbishment work and biomass power generation, orders in the domestic environment and energy businesses declined substantially compared with the same period of the previous year, when it received orders for a DBO project and a large-scale biomass project.
  27. FY2018Lower orders, but maintained at a high levelAnnual report

    「Orders for waste treatment plant construction, major refurbishment work, operation and maintenance, biomass power generation facilities, and sewage sludge incineration power generation facilities brought orders to ¥148,892 million. Although this was a decrease of ¥14,613 million, or 8.9%, from the previous consolidated fiscal year, orders remained at a high level.」

    Orders in the domestic environment and energy businesses declined 8.9% year on year but remained at a high level.
  28. FY2018-Q3SoftenedAnnual report

    「Orders for waste treatment plant construction, major refurbishment work, operation and maintenance, biomass power generation facilities, and sewage sludge incineration power generation facilities brought orders to ¥128,241 million. Although this was a decrease of ¥19,141 million, or 13.0%, from the same period of the previous year, orders remained at a high level.」

    Order activity continued in the domestic environment and energy businesses, including sewage sludge incineration power generation facilities, but orders declined 13.0% year on year. Meanwhile, orders remained at a high level.
  29. FY2018-Q2AdvancedAnnual report

    「In addition to orders for waste treatment plant construction, major refurbishment work, and operation and maintenance, the Company also received orders for biomass power generation facilities and sewage sludge incineration power generation facilities, resulting in orders of ¥111,513 million, an increase of ¥26,233 million, or 30.8%, from the same period of the previous year.」

    Orders progressed in the domestic environment and energy businesses, including sewage sludge incineration power generation facilities, bringing orders to ¥111,513 million, up 30.8% year on year.
  30. FY2018-Q1SoftenedAnnual report

    「Although the Company steadily secured orders for waste treatment plant construction, major refurbishment work, operation and maintenance, and biomass power generation facility construction, orders totaled ¥64,755 million, a slight decrease of ¥1,276 million, or 1.9%, from the same period of the previous year.」

    Although order activity continued, orders in the domestic environment and energy businesses declined 1.9% year on year, weakening the track record of domestic order expansion.
  31. FY2017AdvancedAnnual report

    「In addition to orders for waste treatment plant construction, major refurbishment work, and operation and maintenance, the Company also received orders for biomass power generation facilities and sewage sludge incineration power generation facilities, resulting in orders of ¥191,026 million, a substantial increase of ¥91,106 million, or 91.2%, from the previous consolidated fiscal year.」

    Orders expanded in Japan's environment and energy businesses, including sewage sludge incineration power generation facilities, bringing consolidated orders to ¥191,026 million, up 91.2% year on year.
  32. FY2017-Q3AdvancedAnnual report

    「In addition to steadily securing orders for waste treatment plant construction, major refurbishment work, and operation and maintenance, the Company also received orders for biomass power generation facility construction, resulting in orders of ¥168,731 million, a substantial increase of ¥88,819 million, or 111.1%, from the same period of the previous year.」

    Cumulative domestic orders in the environment and energy businesses for the first 3 quarters totaled ¥168,731 million, up 111.1% year on year.
  33. FY2017-Q2AdvancedAnnual report

    「In addition to steadily securing orders for waste treatment plant construction, major refurbishment work, and operation and maintenance, the Company also received orders for biomass power generation facility construction, resulting in orders of ¥100,341 million, a substantial increase of ¥37,978 million, or 60.9%, from the same period of the previous year.」

    Orders in Japan for waste treatment facilities and biomass power generation projects progressed, bringing cumulative orders for the first half to ¥100,341 million, up 60.9% year on year.
  34. FY2017-Q1First statedAnnual report

    「In addition to steadily receiving orders for the construction, core improvement, operation and maintenance of waste treatment facilities, the company received orders for the construction of biomass power generation facilities. Orders received increased substantially to ¥72,282 million, up ¥42,625 million, or 143.7%, from the same period of the previous year.」

    The domestic environment and energy business has received orders for construction, core improvements, operation and maintenance, and biomass power generation facilities.
Moved together

"Widening operating loss in the Overseas Environmental and Energy Business" moved the same way as this thread, in the same document, in 19 of its 36 moves.

191616151414★123456
  1. ★This thread
  2. 1Widening operating loss in the Overseas Environmental and Energy Business19×
  3. 2Overseas Plant Maintenance and Biomass Power Generation Boilers16×
  4. 3Profit decline due to lower revenue and higher selling, general and administrative expenses16×
  5. 4Substantial increase in orders received and high order backlog15×
  6. 5Further strengthening the financial position14×
  7. 6Decline in operating profit in the Consumer Thermal Energy Business14×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Takuma yet. It last moved in the Earnings presentation of 2026-08-05: "Softened".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.