Decline in Bridge Business Order Intake and Increase in Order Backlog

First written in FY2017-Q1. 5 of 36 entries say "Advanced", first in FY2023. Latest entry: FY2026.

36entries
11years
1from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseOtherFY2017-Q1 – FY2023-Q3OtherFY2024-Q2 – FY20252016: 220162017: 420172018: 420182019: 420192020: 320202021: 420212022: 420222023: 420232024: 320242025: 220252026: 22026
Same theme, other companies
Changes in Order Intake and Order BacklogA theme 156 companies write about · 29 as a headwind · 111 as a tailwind

57 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 156 companies compared. The sentences above are computed from all 156.
Full recordFilings, disclosures and news, newest first
  1. FY2026AdvancedAnnual report

    「Orders received during the fiscal year totaled ¥11,137.679 million, up 1.1% from the previous fiscal year, and the order backlog at fiscal year-end was ¥14,304.340 million, up 3.8%.」

    Both orders received and the order backlog in the bridge business exceeded the previous fiscal year. However, revenue from completed construction work declined 18.5%, resulting in a segment loss of ¥451.146 million.
  2. 2026-05-15AdvancedEarnings

    「Orders received amounted to ¥11,137 million, up 1.1% year on year. As a result, the order backlog at the end of the fiscal year under review stood at ¥14,304 million, up 3.8% year on year.」

    Orders received and the order backlog in the bridge business increased year on year.
  3. FY2026-H1AdvancedAnnual report

    「In the bridge business, revenue for the interim accounting period was ¥5,571.394 million, down 14.9% year on year, and the segment loss was ¥218.689 million, compared with segment profit of ¥94.095 million in the same period of the previous year. Orders received during the interim accounting period totaled ¥7,120.381 million, up 37.3% year on year, while the order backlog at the end of the interim accounting period was ¥15,334.530 million, up 6.3% year on year.」

    In the bridge business, orders received totaled ¥7,120.381 million, up 37.3% year on year, and the order backlog was ¥15,334.530 million, up 6.3%. Orders received turned upward from a decline in the previous fiscal year, while revenue and profitability deteriorated.
  4. FY2025Bridge orders received up, order backlog downAnnual report

    「Orders received during the fiscal year totaled ¥11,021.544 million, up 3.8% from the previous fiscal year, and the order backlog at fiscal year-end was ¥13,785.544 million, down 12.7%.」

    In the bridge business, orders received increased while the order backlog declined. Revenue from completed construction work fell 16.6% from the previous fiscal year, and segment profit declined 92.5%.
  5. FY2025-H1Orders received up, order backlog downAnnual report

    「In the bridge business, revenue for the interim accounting period was ¥6,547.328 million, down 13.0% year on year, and segment profit was ¥94.095 million, down 90.8% year on year. Orders received during the interim accounting period totaled ¥5,184.928 million, up 19.6% year on year, while the order backlog at the end of the interim accounting period was ¥14,427.530 million, down 18.0% year on year.」

    In the bridge business, orders received increased 19.6% year on year, while the order backlog declined 18.0%, revenue declined 13.0% and segment profit declined 90.8%.
  6. FY2024Decline in orders received and order backlogAnnual report

    「Orders received during the fiscal year totaled ¥10,617.515 million, down 40.6% from the previous fiscal year, and the order backlog at fiscal year-end was ¥15,789.931 million, down 24.1%.」

    Both orders received and the order backlog in the bridge business were below the previous year. Orders received totaled ¥10,617.515 million and the order backlog was ¥15,789.931 million.
  7. FY2024-Q3Decline in orders received and order backlogAnnual report

    「Orders received in the bridge business during the cumulative third quarter totaled ¥7,484.149 million, down 46.0% year on year, while the order backlog at the end of the third-quarter accounting period was ¥16,906.951 million, down 18.0% year on year.」

    Orders received in the bridge business declined 46.0% year on year and the order backlog declined 18.0%. The order backlog turned downward after exceeding the same period of the previous year through the preceding quarter.
  8. FY2024-Q2Bridge orders received down, order backlog upAnnual report

    「In the bridge business, revenue for the cumulative second quarter was ¥7,524.305 million, up 21.4% year on year, and segment profit was ¥1,018.614 million, up 276.9% year on year. Orders received during the cumulative second quarter totaled ¥4,334.219 million, down 39.1% year on year, while the order backlog at the end of the second-quarter accounting period was ¥17,601.780 million, up 2.7% year on year.」

    In the bridge business, revenue, segment profit and the order backlog exceeded the previous year, while orders received declined 39.1%. The order backlog was ¥17,601.780 million, up 2.7% year on year.
  9. FY2024-Q1AdvancedAnnual report

    「In the bridge business, revenue for the cumulative first quarter was ¥3,497.706 million, up 12.9% year on year, and segment profit was ¥427.563 million, compared with a segment loss of ¥162.247 million in the same quarter of the previous year. Orders received during the cumulative first quarter totaled ¥3,240.710 million, up 85.5% year on year, while the order backlog at the end of the first-quarter accounting period was ¥20,534.870 million, up 38.2% year on year.」

    Orders received in the bridge business totaled ¥3,240.710 million and the order backlog was ¥20,534.870 million, both exceeding the same quarter of the previous year. Segment results also turned from a loss to a profit.
  10. FY2023AdvancedAnnual report

    「As a result, full-year orders were ¥17,889.565 million in the bridge business and ¥4,279.165 million in the steel structures business, for a total of ¥22,168.730 million, an increase of 57.7% from the previous fiscal year.」

    Orders in the bridge business were ¥17,889.565 million and the order backlog was ¥20,791.867 million, with orders up 61.5% year on year and the order backlog up 28.2%.
  11. FY2023-Q3Higher orders; deterioration in profitabilityAnnual report

    「Revenue in the bridge business for the cumulative third-quarter period was ¥9,443.493 million, up 6.4% year on year, and segment profit was ¥364.663 million, down 43.8% year on year. Cumulative orders for the third-quarter period were ¥13,855.217 million, up 32.3% year on year, while the order backlog at the end of the third-quarter accounting period was ¥20,624.194 million, up 9.1% year on year.」

    Orders, the order backlog and revenue in the bridge business all exceeded the year-earlier levels, while segment profit declined 43.8% due to costs being incurred ahead of revenue.
  12. FY2023-Q2Higher orders and order backlog, but lower revenue and profitAnnual report

    「Revenue in the bridge business for the cumulative second-quarter period was ¥6,200.091 million, down 3.5% year on year, and segment profit was ¥270.238 million, down 60.9% year on year. Cumulative orders for the second-quarter period were ¥7,118.764 million, up 130.3% year on year, while the order backlog at the end of the second-quarter accounting period was ¥17,131.144 million, up 22.6% year on year.」

    Orders and the order backlog in the bridge business increased, while revenue fell 3.5% and segment profit fell 60.9%.
  13. FY2023-Q1First-quarter increase in orders; flat order backlogAnnual report

    「Revenue in the bridge business for the cumulative first-quarter period was ¥3,098.729 million, down 11.6% year on year, and segment loss was ¥162.247 million, compared with segment profit of ¥530.214 million in the year-earlier quarter. Cumulative orders for the first-quarter period were ¥1,747.002 million, up 78.7% year on year, while the order backlog at the end of the first-quarter accounting period was ¥14,860.744 million, up 0.6% year on year.」

    Orders in the bridge business increased 78.7% year on year and the order backlog increased 0.6%, while revenue fell 11.6% and the business posted a segment loss of ¥162.247 million.
  14. FY2022Decline in Full-Year Orders and BacklogAnnual report

    「As a result, the order backlog at the end of the fiscal year was ¥16,212.471 million, down 6.7% from the previous fiscal year, and the company was unable to maintain the balance at the end of the previous fiscal year.」

    Full-year orders in the bridge business were ¥11,079.011 million, down 29.6% year on year, and the order backlog was ¥16,212.471 million, down 6.7%.
  15. FY2022-Q3Third-quarter increase in orders and order backlogAnnual report

    「Revenue in the bridge business for the cumulative third-quarter period was ¥8,875.844 million, down 0.6% year on year, and segment profit was ¥649.209 million, up 58.7% year on year. Cumulative orders for the third-quarter period were ¥10,474.887 million, up 4.5% year on year, while the order backlog at the end of the third-quarter accounting period was ¥18,902.110 million, up 15.3% year on year.」

    Revenue in the bridge business fell 0.6% year on year, while orders increased 4.5% and the order backlog increased 15.3%. Orders and the order backlog turned higher after declining in the previous quarter.
  16. FY2022-Q2Second-quarter decline in orders and order backlogAnnual report

    「Revenue in the bridge business for the cumulative second-quarter period was ¥6,424.032 million, up 7.9% year on year, and segment profit was ¥691.537 million, up 153.3% year on year. Cumulative orders for the second-quarter period were ¥3,091.518 million, down 52.3% year on year, while the order backlog at the end of the second-quarter accounting period was ¥13,970.554 million, down 11.7% year on year.」

    The bridge business cumulative second-quarter results were updated. Revenue and segment profit increased, while orders fell 52.3% year on year and the order backlog fell 11.7%.
  17. FY2022-Q1First-Quarter Results UpdateAnnual report

    「Revenue in the bridge business for the cumulative first-quarter period was ¥3,505.581 million, up 19.3% year on year, and segment profit was ¥530.214 million, compared with a segment loss of ¥108.020 million in the year-earlier quarter. Cumulative orders for the first-quarter period were ¥977.726 million, up 248.3% year on year, while the order backlog at the end of the first-quarter accounting period was ¥14,775.211 million, up 16.9% year on year.」

    The bridge business first-quarter results were updated. Orders increased 248.3% year on year and the order backlog increased 16.9%, while segment earnings turned from a year-earlier loss into profit of ¥530.214 million.
  18. FY2021Full-Year Results UpdatedAnnual report

    「Orders for the fiscal year were ¥15,747.143 million, up 13.2% year on year, exceeding the solid results of the previous fiscal year. As a result, the order backlog at the end of the fiscal year was ¥17,382.992 million, up 13.7% year on year and above the balance at the end of the previous fiscal year.」

    The bridge business full-year orders and order backlog were updated. Orders increased 13.2% and the order backlog increased 13.7%.
  19. FY2021-Q3Orders and order backlog results updatedAnnual report

    「Revenue in the bridge business for the cumulative third-quarter period was ¥8,933.069 million, down 19.5% year on year, and segment profit was ¥409.020 million, down 38.7% year on year. Cumulative orders for the third-quarter period were ¥10,024.831 million, down 8.5% year on year, while the order backlog at the end of the third-quarter accounting period was ¥16,386.848 million, down 1.5% year on year.」

    The bridge business results were updated through the cumulative third-quarter period. Orders fell 8.5% year on year and the order backlog fell 1.5%, while revenue and segment profit also declined.
  20. FY2021-Q2Increase in order intake and order backlogAnnual report

    「Revenue in the bridge business for the cumulative second-quarter period was ¥5,956.117 million, down 19.6% year on year, and segment profit was ¥272.964 million, down 28.8% year on year. Cumulative orders for the second-quarter period were ¥6,475.352 million, up 21.2% year on year, while the order backlog at the end of the second-quarter accounting period was ¥15,814.321 million, up 7.4% year on year.」

    The bridge business reported lower revenue and profit, while orders increased 21.2% year on year and the order backlog increased 7.4%.
  21. FY2021-Q1Continued decline in orders received and order backlogAnnual report

    「Cumulative orders in the bridge business for the first-quarter period were ¥280.713 million, down 50.6% year on year, while the order backlog at the end of the first-quarter accounting period was ¥12,637.662 million, down 8.7% year on year.」

    First-quarter orders in the bridge business fell 50.6% year on year and the order backlog fell 8.7%, as the contraction in order volumes that began in the previous fiscal year continued.
  22. FY2020-Q3Accelerating growth in orders; continued decline in order backlogAnnual report

    「Revenue in the bridge business for the cumulative third-quarter period was ¥11,102.634 million, up 3.2% year on year, and segment profit was ¥666.880 million, up 21.7% year on year. Cumulative orders for the third-quarter period were ¥10,954.040 million, up 72.6% year on year, while the order backlog at the end of the third-quarter accounting period was ¥16,636.928 million, down 6.2% year on year.」

    Orders in the bridge business increased substantially, up 72.6% year on year, while the order backlog fell 6.2%. Revenue and segment profit exceeded the year-earlier levels.
  23. FY2020-Q2Higher order intake, lower order backlogAnnual report

    「Cumulative orders in the bridge business for the second-quarter period were ¥5,342.212 million, up 11.5% year on year, while the order backlog at the end of the second-quarter accounting period was ¥14,722.930 million, down 26.2% year on year.」

    Orders in the bridge business exceeded the year-earlier level, but the order backlog fell 26.2% year on year, and the contraction in order volumes continued.
  24. FY2020-Q1Continued decline in orders received and order backlogAnnual report

    「Cumulative orders in the bridge business for the first-quarter period were ¥567.791 million, down 56.9% year on year, while the order backlog at the end of the first-quarter accounting period was ¥13,839.953 million, down 31.6% year on year.」

    In the bridge business, orders fell 56.9% year on year and the order backlog fell 31.6%, as the contraction in order volumes that began in the previous fiscal year continued into the first quarter.
  25. FY2019Decline in Full-Year Orders and BacklogAnnual report

    「As a result, the order backlog at the end of the fiscal year was ¥16,785.523 million, down 24.2% year on year.」

    Full-year orders in the bridge business were ¥9,825.496 million, down 46.1% year on year, and the order backlog was ¥16,785.523 million, down 24.2%.
  26. FY2019-Q3Decline in orders received and order backlogAnnual report

    「Cumulative orders in the bridge business for the third-quarter period were ¥6,346.663 million, down 48.7% year on year, while the order backlog at the end of the third-quarter accounting period was ¥17,742.897 million, down 10.8% year on year.」

    The bridge business results were updated through the cumulative third-quarter period. Orders fell 48.7% year on year and the order backlog fell 10.8%, with both below the year-earlier levels.
  27. FY2019-Q2Decline in Orders Received and Order BacklogAnnual report

    「Revenue in the bridge business for the cumulative second-quarter period was ¥7,003.434 million, up 15.2% year on year, and segment profit was ¥374.546 million, up 44.6% year on year. Cumulative orders for the second-quarter period were ¥4,792.481 million, down 51.8% year on year, while the order backlog at the end of the second-quarter accounting period was ¥19,942.732 million, down 4.5% year on year.」

    The bridge business half-year results were updated. Revenue and segment profit increased, while orders fell 51.8% year on year and the order backlog fell 4.5%.
  28. FY2019-Q1Updated actual resultsAnnual report

    「Revenue in the bridge business for the cumulative first-quarter period was ¥3,226.119 million, up 23.6% year on year, and segment profit was ¥191.567 million, up 203.1% year on year. Cumulative orders for the first-quarter period were ¥1,316.754 million, down 75.0% year on year, while the order backlog at the end of the first-quarter accounting period was ¥20,244.321 million, up 3.0% year on year.」

    The bridge business first-quarter results were updated. Revenue and segment profit increased, and the order backlog rose 3.0% year on year, while orders fell 75.0%.
  29. FY2018Full-Year Results UpdatedAnnual report

    「By rigorously narrowing the projects bid on, strengthening technical proposals and improving the accuracy of bid prices, the company steadily accumulated orders. Orders totaled ¥18,215.494 million, up 42.2% year on year, marking solid results for the fourth consecutive fiscal year. As a result, the order backlog at the end of the fiscal year was ¥22,153.686 million, up 30.3% year on year, exceeding ¥20 billion in the bridge business alone.」

    The bridge business full-year results were updated. Orders increased 42.2% year on year and the order backlog increased 30.3%, exceeding ¥20 billion in the bridge business alone.
  30. FY2018-Q3Updated actual resultsAnnual report

    「Net sales in the Bridge business for the third-quarter cumulative period were ¥9,502.177 million, up 2.3% year on year, and segment profit was ¥813.138 million, up 239.9%. Orders received were ¥12,380.799 million, up 159.0%, and the order backlog at the end of the third quarter was ¥19,883.106 million, up 62.5%.」

    The bridge business results were updated through the cumulative third-quarter period. Revenue, segment profit, orders and the order backlog all exceeded the year-earlier levels, with orders up 159.0% and the order backlog up 62.5%.
  31. FY2018-Q2Updated actual resultsAnnual report

    「Revenue in the bridge business for the cumulative second-quarter period was ¥6,080.095 million, down 0.5% year on year, and segment profit was ¥258.986 million, up 21.5% year on year. Cumulative orders for the second-quarter period were ¥9,951.875 million, up 113.9% year on year, while the order backlog at the end of the second-quarter accounting period was ¥20,876.264 million, up 36.6% year on year.」

    The bridge business half-year results were updated. Revenue fell 0.5% year on year, while segment profit increased 21.5%, orders increased 113.9% and the order backlog increased 36.6%.
  32. FY2018-Q1Updated actual resultsAnnual report

    「Net sales in the Bridge business for the first-quarter cumulative period were ¥2,610.716 million, up 9.3% year on year, while segment profit was ¥63.194 million, compared with a segment loss of ¥24.293 million in the same period of the previous year. Orders received during the first-quarter cumulative period were ¥5,266.722 million, compared with ¥176.574 million in the same period of the previous year, and the order backlog at the end of the first quarter was ¥19,660.490 million, up 35.3% year on year.」

    The bridge business results were updated through the first quarter. Revenue, segment profit, orders and the order backlog all exceeded the year-earlier quarter, and segment earnings turned from a loss to a profit.
  33. FY2017Updated actual resultsAnnual report

    「Revenue in the bridge business for the fiscal year was ¥12,542.154 million, up 28.2% year on year, and segment profit was ¥380.956 million, compared with a segment loss of ¥241.574 million in the previous year. Orders were ¥12,806.707 million, down 10.6% year on year, while the order backlog at the end of the fiscal year was ¥17,004.484 million, up 1.6% year on year.」

    The bridge business full-year results were updated. Revenue increased and segment profit turned positive, while orders declined and the order backlog edged up.
  34. FY2017-Q3Updated actual resultsAnnual report

    「① Bridge business Revenue in the bridge business for the cumulative third-quarter period was ¥9,285.512 million, up 39.5% year on year, and segment profit was ¥239.224 million, compared with a segment loss of ¥200.455 million in the same period of the previous year. Cumulative orders for the third-quarter period were ¥4,780.236 million, down 45.8% year on year, while the order backlog at the end of the third-quarter accounting period was ¥12,234.656 million, down 14.8% year on year.」

    The bridge business results were updated through the cumulative third-quarter period. Revenue increased and segment profit turned positive, while orders and the order backlog were below the year-earlier levels.
  35. FY2017-Q2Updated actual resultsAnnual report

    「Cumulative orders for the second quarter were ¥4,653.214 million, down 30.3% year on year, while the order backlog at the end of the second-quarter accounting period was ¥15,283.580 million, up 4.9% year on year.」

    Orders in the bridge business fell 30.3% year on year, while the order backlog increased 4.9%, updating the latest half-year results.
  36. FY2017-Q1First statedAnnual report

    「Cumulative orders in the bridge business for the first quarter were ¥176.574 million, down 91.5% year on year, while the order backlog at the end of the first-quarter accounting period was ¥14,526.875 million, up 17.6% year on year.」

    In the bridge business, new orders during the quarter fell substantially year on year, while the order backlog exceeded the year-earlier level.
Moved together

"Securing a Stable Order Pipeline" moved the same way as this thread, in the same document, in 4 of its 36 moves.

443333★123456
  1. ★This thread
  2. 1Securing a Stable Order Pipeline4×
  3. 2Funding-related liquidity risk4×
  4. 3Interest-rate risk3×
  5. 4Capital Investment to Ensure Consistent Quality and Use of Retained Earnings for Business Expansion3×
  6. 5Significant increase in order intake in the steel structures business3×
  7. 6Core Systems Update3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for TAKADAKIKO(Steel Construction) yet. It last moved in the Earnings of 2026-05-15: "Advanced".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Decline in Bridge Business Order Intake and Increase in Order Backlog | TAKADAKIKO(Steel Construction)CO.,LTD. (5923) | Komori