Improving production capacity and rationalizing and streamlining production through new plant construction
First written in FY2019-Q3. 9 of 15 entries say "Advanced", first in FY2019. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026ReframedAnnual report
「Hyogo Plant, Annex building, Kato, Hyogo; building (office building); ¥535 million; —; internal funds and borrowings; July 2026; August 2027」
The facilities plan has been reorganized from the previous fiscal year’s plan to rebuild the logistics building, with planned investment of ¥1.7 billion and completion scheduled for December 2028, to a plan for an annex building to address aging logistics equipment, with planned investment of ¥535 million, construction scheduled to start in July 2026 and completion scheduled for August 2027. - 2026-05-15ReframedM&A and Subsidiary Changes
「物流棟設備の老朽化に伴い、建て替え計画を進めて参りましたが、建設費の高騰が激しく、当初予算から大きく乖離した見積金額となったことから、計画を改修工事へ変更いたしました。」
物流棟について、従来の建替え計画から屋根・屋内電気設備・駐車場等の改修工事へ計画内容が変更された。投資総額6億35百万円、2026年7月着工・2027年8月竣工予定も具体化されている。 - FY2025AdvancedAnnual report
「Hyogo Plant, logistics equipment, ¥1,700 million, —, internal funds and borrowings, September 2025, December 2028」
Following completion of the new plant building and head office building, the company has newly fleshed out plans to rebuild the logistics building to address aging logistics equipment, with planned investment of ¥1.7 billion, construction scheduled to start in September 2025 and completion scheduled for December 2028. The project aims to improve inventory management and shipping efficiency and upgrade employee welfare facilities. - FY2025-H1AdvancedAnnual report
「(7) Method and recipient of allocation: The shares were allocated to 日電ホールディングス by way of a third-party allotment. (8) Use of proceeds: costs related to rebuilding the logistics building」
Following completion of the new plant building and head office building, the company has progressed to the stage of raising funds to rebuild the logistics building. - FY2024Update on completed projectsAnnual report
「During the fiscal year, the company made capital investments totaling ¥1,070.752 million, including software acquisitions. The primary investments were construction costs for the new plant building and office building.」
Following completion of the new plant building and head office building, the company made total capital investments of ¥1,070.752 million during the fiscal year, showing the execution of the construction plan on a full-year basis. - FY2024-Q3AchievedAnnual report
「Of the major additions to property, plant and equipment that were planned at the end of the previous fiscal year, the following were completed during the cumulative third quarter. New plant building and head office building, Kato, Hyogo; wire business; buildings and other assets; investment: ¥1,086.443 million; internal funds and borrowings; completion: October 2023」
The planned new plant building and head office building were completed in October 2023 at an investment of ¥1,086.443 million, bringing the construction and operations plan to the completion stage. - FY2023-Q3AdvancedAnnual report
「Sale of equipment Hyogo Plant Kato, Hyogo Wire business Production equipment 366,424 502,755 13,860 883,040 September 2022 (22,471) The company continues to lease the land, buildings and other assets described above after the sale and continues to use them as before.」
In connection with the consolidation of production and logistics operations, the company sold the buildings, land and other assets of the Hyogo Plant in September 2022 at a total carrying value of ¥883.040 million, then moved to leasing and continuing to use them as before. - FY2022AdvancedAnnual report
「New plant building and head office building (provisional names), Kato, Hyogo; buildings and other assets; planned investment: ¥900 million; funding: internal funds and borrowings; construction start: October 2022; scheduled completion date: undecided」
Following the new plant’s start of operations in January 2020, the company describes plans for a new plant building and head office building aimed at rationalizing costs, improving operating efficiency and expanding future production capacity, with planned investment of ¥900 million and construction scheduled to start in October 2022. - FY2021RestatedAnnual report
「During the consolidated fiscal year, the group made capital investments totaling ¥42.751 million, including software acquisitions. The primary purpose was to cover construction costs for a new plant in the wire business, along with other capital investments aimed at further increasing production capacity and streamlining and improving production operations.」
Following the start of operations at the new plant, the company has continued making capital investments to increase production capacity and streamline and improve production operations. - FY2020AdvancedAnnual report
「Against this backdrop, the group adopted the following management policies: 1. eliminate waste; 2. keep things simple; and 3. move forward with a sense of urgency. It made investments to streamline and improve production operations and brought the new plant into operation in January 2020.」
The new-plant project progressed through the planning, financing and construction stages to the start of operations in January 2020. - FY2020-Q3AdvancedAnnual report
「The company has also begun construction of a new plant to further increase production capacity.」
The new-plant project progressed from planning and financing to the construction stage. Construction in progress increased from ¥498.730 million at the end of the previous consolidated fiscal year to ¥1,430.469 million. - FY2020-Q2AdvancedAnnual report
「The main factors were an increase of ¥23.125 million in long-term borrowings due within 1 year, an increase of ¥855.625 million in long-term borrowings, a decrease of ¥40.864 million in notes and accounts payable, a decrease of ¥38.689 million in electronically recorded obligations, and a decrease of ¥450 million in short-term borrowings, among others.」
Long-term borrowings for construction of the new plant increased, with the drawn-down balance disclosed in the notes advancing from ¥450 million to ¥900 million. The new-plant project has progressed further in terms of financing and investment execution. - FY2020-Q1AdvancedAnnual report
「The group has entered into long-term loan agreements with 2 of its relationship banks to fund construction of the new plant.」
The new-plant project progressed from planning to financing and investment execution, with ¥450 million of the total ¥1.7 billion contract amount already drawn down. Construction in progress also increased from ¥498.730 million at the end of the previous consolidated fiscal year to ¥948.910 million. - FY2019AdvancedAnnual report
「During the consolidated fiscal year, the group made capital investments totaling ¥498.652 million, including software acquisitions. The primary purpose was to cover construction costs for a new plant in the wire business, along with other capital investments aimed at further increasing production capacity and streamlining and improving production operations.」
During the consolidated fiscal year, the company made total capital investments of ¥498.652 million for the new plant, and construction in progress had reached ¥480.042 million. The project progressed from the planning stage to construction commencement and investment execution. - FY2019-Q3First statedAnnual report
「The company will construct a new plant to further increase production capacity and streamline and improve its production operations, with the existing First Plant designated for mass production and the new plant for all-round production. Total floor area: approximately 8,024.75 m²; total investment: approximately ¥1.7 billion, including buildings and manufacturing equipment; construction start: January 2019 (scheduled); completion: November 2019 (scheduled).」
The company has decided to construct a new plant, distinguishing the existing First Plant and the new plant as mass-production and all-round-production facilities, respectively. The plant will have approximately 8,024.75 m² of total floor area and require total investment of approximately ¥1.7 billion, with construction scheduled to start in January 2019 and finish in November 2019.