Komori
Toho Zinc (5707) · InitiativeDropped

Extending Mine Life through Exploration and Deep Development at Existing Mines

First written in FY2019. 11 of 13 entries say "Worsened", first in FY2020. Latest entry: FY2025-H1.

13entries
6years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2019WorsenedFY2020 – FY20242019: 120192020: 220202021: 220212022: 120222023: 420232024: 32024
Same theme, other companies
Continued and Expanded Investment in Resource Exploration and DevelopmentA theme 7 companies write about · 0 as a headwind · 14 as a tailwind

Toho Zinc moved to the "Worse" side of this theme in 2020.

The whole theme swung hardest in 2020: 1 of 6 companies on the "Worse" side.

1 other company's latest entry also says "Dropped".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2025-H1DroppedAnnual report

    「From the perspective of our financial capacity, it is difficult to continue the resources business, and we will exit the business early through measures such as closing or selling our owned mines.」

    The policy shifted from extending the life of existing mines through exploration and deep development to an early exit through the sale of owned mines.
  2. FY2024WorsenedAnnual report

    「The current main medium-grade orebody will be exhausted over the next 3 years, while development of the deep orebody that is to become the next main production area would require substantial investment and increase operating costs. We therefore concluded that continued medium- to long-term operations at the Rasp mine, premised on developing that orebody, would not be sufficiently economically viable, and in November 2023 decided to close the mine in 2024.」

    The Rasp mine reached the decision to close in 2024 rather than extend its mine life and continue operations over the medium to long term.
  3. FY2024-Q3WorsenedAnnual report

    「We concluded that the economics of developing the orebody that was to become the next main production area were poor and that the medium- to long-term business plan for the mine, premised on developing that orebody, was not economically viable. We therefore decided to close the Rasp mine by the end of 2024.」

    The development economics of the next main orebody were judged to be poor, and the Rasp mine moved toward closure at the end of 2024 rather than mine-life extension and continued operations.
  4. FY2024-Q2WorsenedAnnual report

    「We concluded that the economics of developing the orebody that was to become the next main production area were poor and that the medium- to long-term business plan for the mine, premised on developing that orebody, was not economically viable. We therefore decided to close the Rasp mine by the end of 2024.」

    We determined that development of the next main orebody at the Rasp mine was not economically viable and decided to close the mine by the end of 2024. Conditions relating to mine-life extension and continued operations at existing mines deteriorated further.
  5. FY2024-Q1WorsenedAnnual report

    「At the Rasp mine, actual mining of the high-grade orebody was postponed until the beginning of fiscal 2024, resulting in lower run-of-mine ore grades and reduced production.」

    At the Rasp mine, mining of the high-grade orebody was postponed until the beginning of fiscal 2024, resulting in lower run-of-mine ore grades and reduced production.
  6. FY2023WorsenedAnnual report

    「At CBH's Rasp mine in Australia, concentrate production declined from the previous fiscal year, mainly due to lower ore grades resulting from reduced mining volumes of high-grade orebodies, compounded by slower operation of the processing plant due to operator shortages during the COVID-19 pandemic.」

    At the Rasp mine, mining volumes of high-grade orebodies, ore grades and concentrate production declined, further worsening conditions relating to operations at existing mines and mine-life extension.
  7. FY2023-Q3WorsenedAnnual report

    「In addition, operating income turned into a loss due to lower production resulting from declining ore grades and the associated deterioration in productivity.」

    The resources business experienced production cuts and deteriorating productivity due to lower run-of-mine ore grades. Conditions relating to operations at existing mines and mine-life extension did not improve, and the business shifted to an operating loss.
  8. FY2023-Q2WorsenedAnnual report

    「Operating profit declined due to lower production resulting from declining ore grades and less favorable ore sales terms.」

    Production cuts occurred in the resources business due to lower ore grades, conditions relating to productivity and mine-life extension at existing mines did not improve, and earnings deteriorated.
  9. FY2021WorsenedAnnual report

    「At CBH's Rasp Mine, operations shifted in July 2020 to an optimal production configuration involving an approximately 30% production cut aimed at improving economic performance. As a result, concentrate production declined, and, together with lower metal prices compared with the previous period, comparing January–December, and the suspension of operations at the Endeavour Mine, revenue fell to ¥7,557 million, a decrease of ¥3,888 million, or 34%, from the previous period.」

    In addition to the suspension of operations at the Endeavor mine, the Rasp mine also moved to a production reduction of approximately 30%. Conditions relating to production levels and mine-life extension at existing mines did not improve, and revenue declined by 34%.
  10. FY2021-Q3WorsenedAnnual report

    「Although there were developments such as the suspension of operations at CBH's Endeavor mine,」

    The Endeavor mine remains on care and maintenance, conditions relating to operations at existing mines and mine-life extension have not improved, and the deterioration in the effectiveness of mine-life extension measures has continued.
  11. FY2021-Q2WorsenedAnnual report

    「The Resources business also reported lower consolidated revenue year on year, partly because CBH Co.'s Endeavor mine had remained shut since the end of the previous year.」

    The Endeavor mine remains on care and maintenance, and conditions relating to operations at existing mines and mine-life extension have deteriorated.
  12. FY2020WorsenedAnnual report

    「Deep exploration aimed at extending the mine life produced insufficient results from an economic evaluation standpoint, and the mine was placed on care and maintenance at the end of 2019.」

    Deep exploration failed to produce sufficient results for extending the life of the Endeavor mine, and the mine moved to suspended operations at the end of 2019.
  13. FY2019First statedAnnual report

    「It is necessary to increase recoverable ore reserves through peripheral exploration and deep development at existing mines and thereby extend mine life.」

    New measures were explicitly outlined to increase recoverable ore reserves at the Endeavor, Rasp and other mines through peripheral exploration and deep development.
Moved together

"Securing Stable Earnings Through Businesses Less Affected by Market Conditions" moved the same way as this thread, in the same document, in 11 of its 13 moves.

111111988★123456
  1. ★This thread
  2. 1Securing Stable Earnings Through Businesses Less Affected by Market Conditions11×
  3. 2Achievement of the resource business's production plan and cost reductions11×
  4. 3Strengthening CBH’s management foundation and improving mining operation efficiency11×
  5. 4Decline in the profitability and asset value of CBH's mines9×
  6. 5Efficient Operations in the Smelting Business8×
  7. 6Consolidated results turn profitable from losses in the same period of the previous year8×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Toho Zinc yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Extending Mine Life through Exploration and Deep Development at Existing Mines | Toho Zinc Co.,Ltd. (5707) | Komori