Expanding production capacity, centered on growth areas and overseas locations
First written in FY2016. 11 of 35 entries say "Advanced", first in FY2017. Latest entry: FY2026.
120 other companies' latest entry also says "Advanced".
- FY2026AdvancedAnnual report
「The Group invested a total of ¥11,031 million in capital expenditures, primarily to expand and enhance its domestic and overseas sites in business fields expected to grow and to support BCP.」
Full-year capital expenditures totaled ¥11,031 million, including ¥5,231 million for industrial products, ¥2,139 million for high-performance products and ¥1,243 million for building materials. - 2026-05-13AdvancedEarnings presentation materials
「600億円体制構築」
高機能製品について、2027年3月期に向けた600億円体制の構築と、各拠点の設備増強・生産性向上を示している。 - FY2026-H1First-half capital expenditure results updatedAnnual report
「Cash used in investing activities totaled ¥3,795 million, compared with ¥3,646 million used in the same interim period of the previous year. This reflected a decrease in cash mainly due to ¥3,578 million in payments for the acquisition of property, plant and equipment.」
First-half payments for investing activities totaled ¥3,795 million, while payments for the acquisition of property, plant and equipment totaled ¥3,578 million. - FY2025Updated full-year capital expenditure resultsAnnual report
「The Group invested a total of ¥6,819 million in capital expenditures, primarily to expand and enhance its domestic and overseas sites in business fields expected to grow and to support BCP.」
Full-year capital expenditures were updated to ¥6,819 million. Investments included ¥2,243 million in industrial products and ¥2,022 million in corporate assets, among others. - FY2025-H1AdvancedAnnual report
「ニチアス㈱ 鶴見工場 鶴見工場 (Yokohama, Kanagawa) Corporate assets Factory building 2,400 11 Internal funds and borrowings June 2024 March 2026 Warehouse consolidation and employee benefits ニチアス㈱ 王寺工場 王寺工場 (Kitakatsuragi District, Nara) High-performance products Manufacturing equipment 1,650 - Internal funds and borrowings September 2024 December 2025 Production capacity expansion」
A plan was confirmed to invest ¥2,400 million in the factory building at 鶴見工場 for warehouse consolidation and employee benefits. At 王寺工場, ¥1,650 million will be invested in new high-performance product manufacturing equipment, scheduled for completion in December 2025, to increase production capacity. - FY2024AdvancedAnnual report
「The Group invested a total of ¥11,117 million in capital expenditures, primarily to expand and enhance its domestic and overseas sites in business fields expected to grow and to support BCP.」
Full-year capital expenditures were updated to ¥11,117 million. Investments included ¥4,990 million in 袋井工場 and 羽島工場 for high-performance products and ¥2,297 million in 蘇州霓佳斯工業製品有限公司 for industrial products. Plans also include BCP support at 王寺工場, operating efficiency improvements through head-office software and increased production capacity at the Malaysian sites. - FY2024-Q3AdvancedAnnual report
「NICHIAS FGS SDN.BHD. Head office plant (Malaysia) Building materials Manufacturing equipment 800 - Internal funds and borrowings December 2023 April 2025 Production capacity expansion」
A new investment plan was confirmed for ¥800 million of building materials manufacturing equipment at the head office plant of NICHIAS FGS SDN.BHD. in Malaysia. The plan is scheduled to start in December 2023 and be completed in April 2025, using internal funds and borrowings to increase production capacity. Cumulative third-quarter payments for the acquisition of property, plant and equipment totaled ¥9,636 million. - FY2024-Q2Updated second-quarter capital expenditure resultsAnnual report
「Cash used in investing activities totaled ¥6,045 million (compared with ¥3,837 million used in the same quarter of the previous year). This reflected a decrease in cash mainly due to ¥5,754 million in payments for the acquisition of property, plant and equipment.」
Cumulative second-quarter payments for investing activities totaled ¥6,045 million, while payments for the acquisition of property, plant and equipment totaled ¥5,754 million. Construction in progress also increased by ¥2,434 million from the end of the previous fiscal year. - FY2024-Q1Updated first-quarter capital expenditure resultsAnnual report
「Cash used in investing activities totaled ¥3,190 million, compared with ¥1,839 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥3,141 million in payments for the acquisition of property, plant and equipment.」
First-quarter payments for investing activities totaled ¥3,190 million, while payments for the acquisition of property, plant and equipment totaled ¥3,141 million. Construction in progress also increased by ¥1,602 million from the end of the previous fiscal year. - FY2023Updated capital expenditure results and facility plansAnnual report
「The Group invested a total of ¥10,069 million in capital expenditures, primarily to expand and enhance its domestic and overseas sites in business fields expected to grow and to support BCP.」
Full-year capital expenditure results were updated to ¥10,069 million. The planned investment for high-performance product manufacturing equipment at 袋井工場 was updated to ¥2,820 million, with completion scheduled for March 2024, and production capacity expansion plans at 蘇州工場 and other sites were also presented. - FY2023-Q3AdvancedAnnual report
「Planned investment amount Total (¥ million) 1,890 Amount paid to date (¥ million) 1,413 Start June 2021 Completion March 2023 Production capacity Expansion ニチアス㈱ 羽島工場 High-performance products Manufacturing equipment 670 23 Internal funds and borrowings September 2022 October 2023 Production capacity expansion ㈱福島ニチアス 本社工場 High-performance products Factory buildings and manufacturing equipment 1,130 322 Internal funds and borrowings November 2022 December 2023 Production capacity expansion ニチアス㈱ 王寺工場 High-performance products Manufacturing equipment 760 - Internal funds and borrowings December 2022 March 2024 Production capacity expansion」
The amount paid to date for the production capacity expansion plan at 袋井工場 was updated to ¥1,413 million. New production capacity expansion plans for high-performance products were also confirmed at 羽島工場, the 本社工場 of 福島ニチアス and 王寺工場. - FY2023-Q2Updated the investment amount and scheduled completion date for the facility planAnnual report
「Planned investment amount Total (¥ million) 1,890 Amount paid to date (¥ million) 1,154 Start June 2021 Completion March 2023 Production capacity Expansion (Note) 1. The planned investment amount in the facility installation plan for the previous consolidated fiscal year was ¥1,700 million, but has been changed to ¥1,890 million. 2. The scheduled completion date in the facility installation plan for the previous consolidated fiscal year was October 2022, but has been changed to March 2023. The principal newly confirmed plans for the installation of major facilities during the cumulative second quarter were as follows. ニチアス㈱ 羽島工場 High-performance products Manufacturing equipment 670 - Internal funds and borrowings September 2022 October 2023 Production capacity expansion」
The planned investment amount for high-performance product manufacturing equipment at 袋井工場 was increased from ¥1,700 million to ¥1,890 million, and the scheduled completion date was changed from October 2022 to March 2023. A new production capacity expansion plan was also confirmed for 羽島工場, with a planned investment of ¥670 million and completion scheduled for October 2023. - FY2023-Q1Updated first-quarter capital expenditure resultsAnnual report
「Cash used in investing activities totaled ¥1,839 million, compared with ¥394 million provided in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥1,674 million in payments for the acquisition of property, plant and equipment.」
First-quarter payments for investing activities totaled ¥1,839 million, while payments for the acquisition of property, plant and equipment totaled ¥1,674 million. - FY2022-Q3Updated third-quarter capital expenditure plans and paymentsAnnual report
「ニチアス㈱ 羽島工場 High-performance products Manufacturing equipment 1,400 - Internal funds and borrowings October 2021 October 2023 BCP support」
The facility plan to increase production capacity for high-performance products and support BCP was updated to reflect amounts paid and the scheduled completion date as of the third quarter. Cumulative payments for the acquisition of property, plant and equipment under capital expenditures totaled ¥7,250 million. - FY2022-Q2AdvancedAnnual report
「The principal newly confirmed plans for the installation of major facilities during the cumulative second quarter were as follows.」
Plans were confirmed to install manufacturing equipment costing ¥1,700 million at 袋井工場, ¥300 million at 鶴見工場, ¥300 million at 熊本ニチアス and ¥200 million at 福島ニチアス to increase production capacity for high-performance products. In addition, ¥1,400 million will be invested at 羽島工場 to support BCP, with completion scheduled for October 2023. - FY2022-Q1Updated first-quarter capital expenditure resultsAnnual report
「Cash provided by investing activities totaled ¥394 million, compared with ¥1,806 million used in the same quarter of the previous year. Although cash decreased mainly due to ¥963 million in payments for the acquisition of property, plant and equipment, it increased due to ¥1,542 million in proceeds from the liquidation of an affiliated company, among other factors.」
First-quarter payments for the acquisition of property, plant and equipment totaled ¥963 million. Proceeds of ¥1,542 million from the liquidation of an affiliated company were also included in investing cash flows. - FY2021AdvancedAnnual report
「The Group invested a total of ¥7,703 million in capital expenditures, primarily to expand and enhance its domestic and overseas sites in business fields expected to grow and to support BCP.」
Full-year capital expenditures were updated to ¥7,703 million, with investments identified in manufacturing equipment at 王寺工場 and factory buildings and manufacturing equipment at ニチアスセラテック㈱, among others. Plans to support BCP and increase production capacity at 大阪支社, 王寺工場 and 中野工場 were also presented, with completion scheduled between 2021 and 2022. - FY2021-Q3Third-quarter capital expenditure results updatedAnnual report
「Cash used in investing activities totaled ¥4,425 million, compared with ¥7,825 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥5,591 million in payments for the acquisition of property, plant and equipment.」
Cumulative third-quarter payments for investing activities totaled ¥4,425 million, while payments for the acquisition of property, plant and equipment totaled ¥5,591 million. - FY2021-Q2First-half capital expenditure results updatedAnnual report
「Cash used in investing activities totaled ¥3,188 million, compared with ¥5,623 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥3,935 million in payments for the acquisition of property, plant and equipment.」
Cumulative second-quarter payments for investing activities totaled ¥3,188 million, while payments for the acquisition of property, plant and equipment totaled ¥3,935 million. - FY2021-Q1Updated first-quarter capital expenditure resultsAnnual report
「Cash used in investing activities totaled ¥1,806 million, compared with ¥3,379 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥2,021 million in payments for the acquisition of property, plant and equipment.」
First-quarter payments for investing activities totaled ¥1,806 million, while payments for the acquisition of property, plant and equipment totaled ¥2,021 million. - FY2020AdvancedAnnual report
「The Group invested a total of ¥8,978 million in capital expenditures, primarily to expand and enhance its domestic and overseas sites in business fields expected to grow and to support BCP.」
Full-year capital expenditures were updated to ¥8,978 million, with investments identified in manufacturing equipment and factory buildings at 結城工場, NICHIAS HAIPHONG and NT RUBBER-SEALS, among others. Equipment plans to increase production capacity and support BCP were also presented for 王寺工場 and other sites. - FY2020-Q3Updated third-quarter capital expenditure resultsAnnual report
「Cash used in investing activities totaled ¥7,825 million, compared with ¥8,173 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥7,927 million in payments for the acquisition of property, plant and equipment.」
Cumulative third-quarter payments for investing activities totaled ¥7,825 million, while payments for the acquisition of property, plant and equipment totaled ¥7,927 million. - FY2020-Q2First-half capital expenditure results updatedAnnual report
「Cash used in investing activities totaled ¥5,623 million, compared with ¥5,796 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥6,159 million in payments for the acquisition of property, plant and equipment.」
Cumulative second-quarter payments for investing activities totaled ¥5,623 million, while payments for the acquisition of property, plant and equipment totaled ¥6,159 million. - FY2020-Q1Update to first-quarter capital investment resultsAnnual report
「Cash used in investing activities totaled ¥3,379 million, compared with ¥3,520 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥3,262 million in payments for the acquisition of property, plant and equipment.」
First-quarter payments for investing activities totaled ¥3,379 million, while payments for the acquisition of property, plant and equipment totaled ¥3,262 million. - FY2019AdvancedAnnual report
「The Group invested a total of ¥12,816 million in capital expenditures, primarily to expand and enhance its domestic and overseas sites in business fields expected to grow and to support BCP.」
Full-year capital expenditures totaled ¥12,816 million, with specific investments identified in factory buildings and manufacturing equipment at NICHIAS HAIPHONG, 福島ニチアス, ニチアスセラテック and 蘇州双友汽車零部件有限公司, among others. - FY2019-Q3Updated third-quarter capital expenditures and investment resultsAnnual report
「Cash used in investing activities totaled ¥8,173 million, compared with ¥10,940 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥7,910 million in payments for the acquisition of property, plant and equipment and ¥447 million in payments for the acquisition of intangible assets.」
Updated cumulative third-quarter payments for investing activities and the acquisition of property, plant and equipment and intangible assets. - FY2019-Q2Updated second-quarter capital expenditures and investment resultsAnnual report
「Cash used in investing activities totaled ¥5,796 million, compared with ¥7,081 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥5,610 million in payments for the acquisition of property, plant and equipment and ¥393 million in payments for the acquisition of intangible assets.」
Updated cumulative second-quarter payments for investing activities and the acquisition of property, plant and equipment and intangible assets. - FY2019-Q1Updated first-quarter capital expenditures and investment resultsAnnual report
「Cash used in investing activities totaled ¥3,520 million, compared with ¥3,089 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥3,122 million in payments for the acquisition of property, plant and equipment and ¥364 million in payments for the acquisition of intangible assets.」
Updated first-quarter payments for investing activities and the acquisition of property, plant and equipment and intangible assets. - FY2018-Q3Updated third-quarter capital expenditures and investment resultsAnnual report
「Cash used in investing activities totaled ¥10,940 million, compared with ¥7,930 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥9,069 million in payments for the acquisition of property, plant and equipment and ¥1,693 million in payments for the acquisition of shares in subsidiaries.」
Updated investment results for the cumulative third quarter, including the acquisition of property, plant and equipment and shares in subsidiaries. - FY2018-Q2Updated first-half capital expenditures and investment resultsAnnual report
「Cash used in investing activities totaled ¥7,081 million, compared with ¥3,951 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥5,295 million in payments for the acquisition of property, plant and equipment and ¥1,686 million in payments for the acquisition of shares in subsidiaries.」
Updated investment results for the cumulative second quarter, including the acquisition of property, plant and equipment and shares in subsidiaries. - FY2018-Q1Updated first-quarter capital expenditures and investment resultsAnnual report
「Cash used in investing activities totaled ¥3,089 million, compared with ¥1,368 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥2,216 million in payments for the acquisition of property, plant and equipment and ¥1,059 million in payments for the acquisition of shares in subsidiaries.」
Updated first-quarter investment results, including payments for the acquisition of property, plant and equipment and shares in subsidiaries. - FY2017AdvancedAnnual report
「The Group invested a total of ¥9,775 million in capital expenditures, primarily to expand and enhance its domestic and overseas sites in business fields expected to grow and to support business continuity planning (BCP).」
Full-year capital expenditures totaled ¥9,775 million, with specific investments identified for expanding and enhancing domestic and overseas sites and supporting BCP. - FY2017-Q3Third-quarter capital expenditure results updatedAnnual report
「Cash used in investing activities was ¥7,930 million, compared with ¥3,438 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥5,900 million used for the acquisition of property, plant and equipment and ¥1,783 million used for the acquisition of shares in subsidiaries resulting in changes to the scope of consolidation.」
Capital expenditures for the acquisition of property, plant and equipment during the cumulative third quarter were stated at ¥5,900 million. - FY2017-Q2First-half capital expenditure results updatedAnnual report
「Cash used in investing activities was ¥3,951 million, compared with ¥2,282 million used in the same quarter of the previous year. This reflected a decrease in cash mainly due to ¥3,841 million used for the acquisition of property, plant and equipment.」
Cash used for the acquisition of property, plant and equipment during the second quarter of the current consolidated cumulative period was ¥3,841 million. - FY2016First statedAnnual report
「We invested ¥4,287 million in capital expenditures across the Group, primarily in business fields expected to grow in the future, including the expansion and enhancement of overseas sites.」
Plans to expand factory buildings and manufacturing equipment in Indonesia, Malaysia, Vietnam, the Czech Republic and elsewhere are disclosed.