Long-Term Co-Creation Development Model: From PoC to MVP and Continuous Development
First written in FY2023. 3 of 6 entries say "Advanced", first in FY2024. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026RestatedAnnual report
「In consulting, the Company conducts interviews and analyzes information from the perspective of how to translate the findings into engineering, develops a deep understanding of industry conditions and customer issues, and creates a proof of concept or prototype in approximately 3 months. It then incorporates feedback from partner companies and develops the MVP through full-scale development over approximately 24 months while engaging in dialogue with them.」
The company reaffirmed its long-term co-created development model, which progresses from a PoC or prototype to approximately 24 months of MVP development and then to ongoing development after the initial release. - FY2025RestatedAnnual report
「In consulting, the company conducts interviews and analyzes information from the perspective of how to translate concepts into engineering, gains a deep understanding of industry conditions and customer challenges, and creates a PoC (Note 4) or prototype in approximately 3 months. It then incorporates feedback from partner companies and conducts full-scale development to develop an MVP (Note 5) over approximately 24 months through ongoing dialogue.」
The company reaffirmed its long-term co-created development model, which progresses from a PoC or prototype to approximately 24 months of MVP development and then to ongoing development after the initial release. - FY2024AdvancedAnnual report
「The duration of full-scale development in this segment was 24 months, based on the results of the PlantStream project, which has already entered the ongoing development phase. After full-scale development ends, the company conducts ongoing development projects ranging from ¥50 million annually to several hundred million yen. The average total project duration, from full-scale development through ongoing development, was 36.7 months based on results as of the end of June 2024.」
The average project duration under the long-term co-created development model was updated from 36.4 months to 36.7 months. The structure of 24 months of full-scale development followed by ongoing development remains unchanged. - FY2023First statedAnnual report
「The migration rate from PoC to full-scale development in this segment was 68% based on results from the fiscal years ended June 2019 through June 2023, and the duration of full-scale development was 24 months, based on the results of the PlantStream project, which has already entered the ongoing development phase. After full-scale development ends, the company conducts ongoing development projects ranging from ¥50 million annually to several hundred million yen. The average total project duration, from full-scale development through ongoing development, was 36.4 months based on results as of the end of June 2023.」
The company discloses actual results for a process comprising approximately 3 months of PoC, approximately 2 years of MVP development and ongoing development, including the migration rate, duration of ongoing development, ongoing development fees and average project duration.