- 2026-08-13AchievedFinancial results briefing materialsSuggests it is closing out
「Recognition of one-time costs was completed in the first quarter, and operating profit came in as expected.」
The company stated that recognition of one-time costs related to the head office relocation was completed in the first quarter, indicating that the temporary relocation-related expenses had ended. - FY2026AchievedAnnual report
「The company relocated its head office effective 1 April 2026.」
The head-office relocation previously resolved and contracted for was completed effective 1 April 2026. Total capital investment was ¥453.829 million, including ¥391.763 million in construction in progress. - FY2026-H1AdvancedAnnual report
「During the interim accounting period, the company decided when it would vacate the leased head-office premises. It shortened the useful lives of buildings, building improvements, tools, fixtures and equipment so that depreciation would be completed over the expected remaining period of use through the scheduled vacation date.」
The vacation date for the leased head office was determined, and useful lives of fixed assets and the expected-use period of the asset retirement obligation were changed to align with the planned move. Completion of the relocation itself was not stated. - FY2025First statedAnnual report
「At a Board of Directors meeting held on 15 April 2025, the company resolved to relocate its head office and entered into a fixed-term building lease on 30 April 2025. New equipment is expected to be installed in connection with the relocation, but the specific investment amount has not been determined.」
The company resolved to relocate its head office and entered into a fixed-term lease. New equipment is planned, but the specific investment amount remains undecided.