Capital Investment, Productivity Improvement and Labor Savings, Centered on Growth Areas
First written in FY2016. 20 of 26 entries say "Advanced", first in FY2017-Q2. Latest entry: FY2027-H1.
41 other companies' latest entry also says "Advanced".
- FY2027-H1AdvancedAnnual report
「Cash used in investing activities was ¥530 million. This was mainly attributable to ¥413 million in “payments for the acquisition of property, plant and equipment.”」
During the current interim consolidated accounting period, ¥530 million was used in investing activities, mainly for the acquisition of property, plant and equipment, and capital investment continued. - FY2026Capital investment declined, but investment in the Odaka plant continued.Annual report
「Total capital investment for the consolidated fiscal year was ¥1,771 million, primarily for the construction of new production facilities at the Company's Odaka Plant in the Industrial Materials segment.」
Capital investment amounted to ¥1,771 million, down from the previous fiscal year, while investment continued, mainly in the construction of new production facilities at the Odaka Plant. - FY2026-H1AdvancedAnnual report
「Funds used in investing activities amounted to ¥946 million. This was mainly attributable to ¥881 million in payments for the acquisition of property, plant and equipment.」
During the interim consolidated accounting period, ¥881.20 million was spent mainly on the acquisition of property, plant and equipment, and capital investment continued. - FY2025AdvancedAnnual report
「The Group made capital investments totaling ¥3,182 million, primarily in areas expected to deliver long-term growth, for research and development, productivity improvements, automation, labor savings, rationalization and enhanced reliability.」
Capital investment amounted to ¥3,182 million, including ¥2,164 million for industrial materials and ¥717 million for sporting goods. - FY2025-H1AdvancedAnnual report
「Funds used in investing activities amounted to ¥840 million. This was mainly attributable to ¥1,153 million in payments for the acquisition of property, plant and equipment.」
During the interim consolidated accounting period, ¥1,153 million was invested mainly in the acquisition of property, plant and equipment, and ¥840 million was used in investing activities. - FY2024AdvancedAnnual report
「The Group made capital investments totaling ¥1,495 million, primarily in areas expected to deliver long-term growth, for research and development, productivity improvements, automation, labor savings, rationalization and enhanced reliability.」
Capital investment totaling ¥1,495 million was made for purposes including automation and labor savings. This was an increase from ¥865 million in the previous year. - FY2024-Q2AdvancedAnnual report
「Funds used in investing activities amounted to ¥576 million. This was mainly attributable to ¥561 million in payments for the acquisition of property, plant and equipment.」
During the cumulative second quarter, ¥576 million was used in investing activities, mainly for the acquisition of property, plant and equipment, while acquisition payments amounted to ¥561 million. - FY2023AdvancedAnnual report
「The Group made capital investments totaling ¥865 million, primarily in areas expected to deliver long-term growth, for research and development, productivity improvements, automation, labor savings, rationalization and enhanced reliability.」
Annual capital investment results in growth areas, including automation and labor savings, were disclosed. - FY2023-Q2AdvancedAnnual report
「Funds used in investing activities amounted to ¥535 million. This was mainly attributable to ¥643 million in payments for the acquisition of property, plant and equipment.」
During the cumulative second quarter, ¥535 million was used in investing activities, mainly for the acquisition of property, plant and equipment, while acquisition payments amounted to ¥643 million. - FY2022-Q2AdvancedAnnual report
「Specific uses ① Capital investment in the renewal, expansion and automation of existing facilities of the Group, including overseas subsidiaries ¥1,678 million April 2022–March 2024 ② Capital investment related to the development of new businesses ¥200 million April 2022–March 2024 ③ Capital investment related to system upgrades for operational reform ¥300 million April 2023–March 2024 Total ¥2,178 million」
The Company presented a specific plan to invest a total of ¥2,178 million of funds raised through stock acquisition rights in the renewal, expansion and automation of existing facilities, new businesses and system upgrades for operational reform from April 2022 to March 2024, with some investments scheduled from April 2023. - FY2021-Q2AdvancedAnnual report
「Funds used in investing activities amounted to ¥812 million. This was mainly attributable to ¥789 million in payments for the acquisition of property, plant and equipment.」
During the cumulative second quarter, ¥812 million was used in investing activities, mainly for the acquisition of property, plant and equipment. - FY2020-Q3AdvancedAnnual report
「Construction of new plant building 985,000 688,450 Internal funds September 2018 March 2020」
Payments made for construction of the new building at the Haramachi Plant increased from ¥358.450 million in the previous disclosure to ¥688.450 million, while the scheduled completion date remained March 2020. - FY2020-Q2SoftenedAnnual report
「Our Haramachi Plant Minamisoma, Fukushima Industrial materials Construction of new plant building 985,000 358,450 Internal funds September 2018 March 2020」
Construction of the new building at the Haramachi Plant had progressed to ¥358.450 million in payments made, while the scheduled completion date changed from November 2019 to March 2020, extending the planned completion deadline. - FY2019AdvancedAnnual report
「The Group made capital investments totaling ¥1,049 million, primarily in areas expected to deliver long-term growth, for research and development, productivity improvement, labor saving, rationalization and enhanced reliability.」
Capital investment of ¥1,049 million was made during the fiscal year for research and development in growth areas, productivity improvements and labor savings. - FY2019-Q3RestatedAnnual report
「Construction of new factory building: 985,000; 5,450; internally funded; September 2018; November 2019.」
The Company continues to disclose the plan to construct a new factory building at the Haramachi Plant, with planned investment of ¥985 million, construction beginning in September 2018 and completion scheduled for November 2019. - FY2019-Q2AdvancedAnnual report
「Construction of new factory building: total planned investment (¥ thousands) 985,000; amount already paid 5,450; start date September 2018; scheduled completion November 2019.」
The Company disclosed a plan to begin construction of a new factory building at the Haramachi Plant in September 2018, with planned investment of ¥985 million and completion scheduled for November 2019. The project is intended to expand production of medical rubber products and other items and improve operating efficiency by consolidating administrative functions. - FY2019-Q1AdvancedAnnual report
「At a Board of Directors meeting held on 26 July 2018, the Company resolved to construct a new factory building on the premises of its Haramachi Plant in Minamisoma, Fukushima Prefecture, to expand the production area and for other purposes. The planned capital investment is ¥985 million, and completion is scheduled for November 2019.」
The Board of Directors resolved to construct a new factory building to expand the production area at the Haramachi Plant. The planned investment is ¥985 million, with completion scheduled for November 2019. - FY2018AdvancedAnnual report
「The Group made capital investments totaling ¥1,802 million, primarily in areas expected to deliver long-term growth, for research and development, productivity improvement, labor saving, rationalization and enhanced reliability.」
The Group disclosed capital investment of ¥1,802 million for the fiscal year under review, including ¥1,414 million invested mainly in the acquisition of production facilities in China and Vietnam for industrial materials. - FY2018-Q3RestatedAnnual report
「The Group formulated a new three-year medium-term plan beginning in the current fiscal year and is focusing on proactive capital investment, sales activities and new product development.」
The Group continues to make active capital investments under its new three-year medium-term plan. Specific investment plans for expanding the third plant are also continuing to be disclosed. - FY2018-Q2AdvancedAnnual report
「Cash used in investing activities totaled ¥1,310 million. This was primarily attributable to ¥1,160 million in payments for the acquisition of property, plant and equipment.」
The Group used ¥1,310 million in investing activities during the six-month period of the second quarter, mainly for the acquisition of property, plant and equipment, and continued capital investment. - FY2017AdvancedAnnual report
「The Group made capital investments totaling ¥2,559 million, primarily in areas expected to deliver long-term growth, for research and development, productivity improvement, labor saving, rationalization and enhanced reliability.」
Capital investment totaled ¥2,559 million, focused primarily on overseas production facilities for industrial materials. - FY2017-Q2AdvancedAnnual report
「Cash used in investing activities during the six-month period of the second quarter under review was ¥782 million. This was primarily attributable to payments for the acquisition of property, plant and equipment.」
The Group recorded ¥782 million in investing activity expenditures during the six-month period of the second quarter, mainly for the acquisition of property, plant and equipment. - FY2016First statedAnnual report
「The Group made capital investments totaling ¥1,699 million, primarily in areas expected to deliver long-term growth, for research and development, productivity improvement, labor saving, rationalization and enhanced reliability.」
The Group states that it made capital investments of ¥1,699 million during the fiscal year under review.