Establishment of a semiconductor-related research and manufacturing site in Kumamoto Prefecture
First written in FY2023-Q2. 4 of 7 entries say "Advanced", first in FY2023-Q3. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026AdvancedAnnual report
「November 2025 New Kumamoto Facility established in Kamimashiki District, Kumamoto Prefecture」
The Kumamoto Facility was newly established in November 2025, and the company invested ¥6,526 million in the acquisition of buildings and equipment during the fiscal year. The semiconductor-related research and manufacturing site has progressed from the planning stage to the development of an operating facility. - 2026-06-03AchievedGeneral Meeting of Shareholders
「(注)2025年11月4日付で熊本事業所(熊本県上益城郡)を新設いたしました。」
熊本事業所について、従来の建設・投資計画から、2025年11月4日付の新設及び当期6,526百万円の建物・設備取得が記載され、拠点整備が稼働段階に進んだ。 - FY2025AdvancedAnnual report
「Reporting company Mashiki Town, Kamimashiki District, Kumamoto Prefecture Kumamoto Facility Building construction 11,400,000 5,022,119 Internal funds February 2023 December 2025」
Construction of the Kumamoto Facility has progressed to ¥5,022,119 thousand already paid against total planned investment of ¥11,400,000 thousand. Although planned investment has increased from the previous approximately ¥8.0 billion plan, completion remains scheduled for December 2025. - FY2024-Q3SoftenedAnnual report
「Reporting company Kamimashiki District, Kumamoto Prefecture Mashiki Town Kumamoto Facility (provisional name) Building construction 8,000,000 192,440 Internal funds February 2023 December 2025」
For the semiconductor-related research and manufacturing site in Mashiki Town, Kumamoto Prefecture, the planned investment of ¥8.0 billion and the internally funded plan remain unchanged, with ¥192,440 thousand already paid, but the scheduled completion has changed from April 2025 to December 2025. - FY2023AdvancedAnnual report
「Reporting company Mashiki Town, Kamimashiki District, Kumamoto Prefecture Kumamoto Facility (provisional name) Building construction 8,000,000 18,579 Internal funds February 2023 April 2025」
The semiconductor-related research and manufacturing site in Mashiki Town, Kumamoto Prefecture, has progressed to a building construction plan scheduled to begin in February 2023, with ¥18,579 thousand already paid, total investment of ¥8.0 billion, and completion scheduled for April 2025. - FY2023-Q3AdvancedAnnual report
「During the second quarter cumulative period, the company decided to purchase land in Mashiki Town, Kamimashiki District, Kumamoto Prefecture, for a total of ¥392,676 thousand to establish a new research and development and manufacturing site. Although the total investment including construction costs and other expenses had not been determined, the company decided on the following plan for establishing major facilities. Reporting company Kamimashiki District, Kumamoto Prefecture Mashiki Town Research building, factory building, and warehouse building 8,000,000 - Internal funds To be determined April 2025」
Procedures related to the acquisition of land in Mashiki Town, Kumamoto Prefecture, have been completed, and the plan to establish a research building, factory building, and warehouse building has been finalized at a total cost of ¥8.0 billion, funded with internal funds and scheduled for completion in April 2025. The semiconductor-related research and manufacturing site has progressed from land acquisition to the facility planning stage. - FY2023-Q2First statedAnnual report
「During the second quarter cumulative period, the company decided to purchase land in Mashiki Town, Kamimashiki District, Kumamoto Prefecture, for a total of ¥392,676 thousand to establish a new research and development and manufacturing site. The total investment, including construction costs and other expenses, has not yet been determined. At a meeting of the Board of Directors held on 7 November 2022, the company resolved to establish a new production and research and development site as follows. In the electronics field, one of the company's key target areas, semiconductor demand is expected to continue increasing in response to new technologies such as 6G and DX. To achieve further growth, the company decided to establish a site in Kumamoto Prefecture, where the semiconductor industry is growing rapidly, for research and development of semiconductor-related chemicals and manufacturing of those chemicals and other products. Total investment: approximately ¥8.0 billion, excluding the cost of acquiring the factory site Scheduled completion: April 2025」
The company disclosed for the first time its plan to establish a research and development and manufacturing site in Mashiki Town, Kamimashiki District, Kumamoto Prefecture. The land acquisition price is ¥392,676 thousand, the site area is 26,178.40 m², total investment excluding the cost of acquiring the factory site is approximately ¥8.0 billion, and completion is scheduled for April 2025. The site is planned to conduct research and development and manufacturing of semiconductor-related chemicals.