Quality and Delivery Risks Associated with Outsourcing to Partner Companies
First written in FY2020. 4 of 6 entries say "Mitigated", first in FY2022. Latest entry: FY2026-H1.
The whole theme swung hardest in 2024: 10 of 32 companies on the "Worse" side.
15 other companies' latest entry also says "Mitigated".
- FY2026-H1MitigatedAnnual report
「In system development, the production structure recovered to normal operations from the same period of the previous year, when it was affected by delivery delays at outsourced contractors, and expanded beyond the level before the problem occurred. This, together with the acceleration into the first half of major customers' annual development plans, led to higher revenue and profit.」
The company stated that, regarding the impact of delivery delays at outsourced contractors that occurred in the same period of the previous year, the production structure had recovered to normal operations and expanded beyond the level before the problem occurred. - FY2025-H1MitigatedAnnual report
「In system development, the production structure recovered to normal operations from the same period of the previous year, when it was affected by delivery delays at outsourced contractors, and expanded beyond the level before the problem occurred. This, together with the acceleration into the first half of major customers' annual development plans, led to higher revenue and profit.」
The company stated that, regarding the delivery delays at outsourced contractors that occurred in the same period of the previous year, the production structure had recovered to normal operations and expanded beyond the level before the problem occurred. - FY2024-Q3MitigatedAnnual report
「In addition, hardware development back orders that arose during the first half owing to production capacity constraints at the manufacturing contractor are being steadily cleared toward the end of the fiscal year.」
The company stated that hardware development back orders caused by production capacity constraints at the manufacturing contractor were being steadily cleared toward the end of the fiscal year. - FY2024-Q2MaterialisedAnnual report
「In hardware contract development, revenue was slightly below the initial forecast because of delivery delays caused by production capacity constraints at the manufacturing contractor, among other factors. However, there is already a clear prospect of resolving the delivery-delay issue, and we do not believe it will affect achievement of the full-year revenue plan.」
The previously identified quality and delivery risk involving business partners and manufacturing contractors materialized as delivery delays caused by production capacity constraints. However, the company stated that, as of the filing date, there was a clear prospect of resolving the issue. - FY2022MitigatedAnnual report
「We have established a dedicated organization responsible for strengthening cooperation with existing partner companies and developing new partners, and are working to develop our principal business partners (outsourced contractors).」
To address quality and delivery risks involving business partners, the company has established a dedicated organization, strengthened cooperation with existing partners and developed new partners. - FY2020First statedAnnual report
「If problems at a business partner (outsourced contractor) result in lower project quality, development delays, defects or other issues, the group's financial position and operating results could be affected.」
The company uses outsourcing to accommodate increases in order volume and reduce costs.