Capital Investment Plan for the New Research Building, Reconstruction of the Hamamatsu Plant, and Technology Development Center
First written in FY2022. 6 of 9 entries say "Advanced", first in FY2024-Q3. Latest entry: FY2026.
The whole theme swung hardest in 2024: 1 of 7 companies on the "Worse" side.
4 other companies' latest entry also says "Advanced".
- FY2026AdvancedAnnual report
「The group, comprising the company and its consolidated subsidiaries, continues to renew existing facilities to meet market needs, improve chemical quality and expand production capacity, expand processing capacity, and enhance assets used for research and development. During the consolidated fiscal year, the group made capital investments totaling ¥12,629 million.」
Disclosed capital investments of ¥12,629 million. The group continues investments including the opening of the new Integrated Technology Research Institute, renewal of existing facilities, and expansion of chemicals and processing capacity. - FY2026-H1AdvancedAnnual report
「日本パーカライジングインディア㈱ India Chemicals business New Chennai plant 5,814 September 2025 December 2026」
For its capital investment plans, the company newly finalized a plan to build a chemicals manufacturing plant in Chennai, India, with planned investment of ¥581.4 million, construction scheduled to begin in September 2025 and completion scheduled for December 2026. - FY2025SoftenedAnnual report
「As announced in “Postponement of Construction of the New Kyushu Plant,” published on 25 December 2024, the construction plan has been frozen.」
The chemicals manufacturing plant plan in Kitakyushu disclosed in the previous filing was frozen following a postponement. - FY2025AdvancedAnnual report
「The company built a new Integrated Technology Research Institute (Parker Innovation Center), which opened in April 2025 to strengthen its technological development capabilities, and reorganized its research and development structure by establishing the Advanced Technology Research Department and the Core Technology Research Department.」
The company opened the new Integrated Technology Research Institute in April 2025 and moved to the stage of establishing the Advanced Technology Research Department and the Core Technology Research Department. - FY2025-H1AdvancedAnnual report
「パーカー加工㈱ | Kasai, Hyogo | Processing business | Construction of a new anti-corrosion treatment plant | 2,489 | February 2025 | June 2026」
In the processing business, the company newly finalized plans to build an anti-corrosion treatment plant in Kasai, Hyogo. The planned investment is ¥2,489 million, with construction scheduled to begin in February 2025 and be completed in June 2026, funded with internal funds. - FY2024AdvancedAnnual report
「In the equipment business, the company opened a new “Technology Development Center” in Funabashi, Chiba, last November.」
The technology development center in Funabashi, Chiba, planned in the previous fiscal year, opened in November 2023. It operates as a base equipped with new coating technologies, experimental facilities and links to IoT systems. - FY2024-Q3AdvancedAnnual report
「NIHON PARKERIZING CO.,LTD. | Wakamatsu Ward, Kitakyushu, Fukuoka | Chemicals business | Chemicals manufacturing plant | 10,000 | April 2025 | September 2026」
In the chemicals business, the company newly finalized plans to build a chemicals manufacturing plant in Wakamatsu Ward, Kitakyushu, Fukuoka. The planned investment is ¥10.0 billion, with construction scheduled to begin in April 2025 and be completed in September 2026, funded with internal funds. - FY2023RestatedAnnual report
「In the equipment business, the company will complete construction of a new technology development center in Funabashi, Chiba, in November 2023.」
The company continues its plan for the technology development center, scheduled for completion in November 2023, together with a demonstration plant and IoT-based equipment management. - FY2022First statedAnnual report
「NIHON PARKERIZING CO.,LTD. | Hiratsuka, Kanagawa | Group-wide | Construction of a new research building and renovation of the existing research building | 6,500 | Scheduled for 2022 | Scheduled for 2024 / パーカー加工㈱ | Hamamatsu, Shizuoka | Processing business | Reconstruction of the anti-corrosion treatment plant (Hamamatsu) | 3,318 | May 2021 | February 2023 / パーカーエンジニアリング㈱ | Funabashi, Chiba | Equipment business | Construction of an experimental and office building at the technology development center | 1,120 | July 2022 | September 2023」
Newly disclosed major capital investment plans totaling ¥10,938 million to strengthen the foundations for research and development, production and equipment technology development.