Costs and Continued Supply Risks Associated with the Expropriation of Part of the Shonan Plant Site and Relocation to a New Plant
First written in FY2026-H1. 2 of 4 entries say "Materialised", first in 2026-04-24. Latest entry: FY2026.
4entries
2years
2from disclosures
How it moved
Same theme, other companies
New plant relocation costs and supply continuity risks arising from the compulsory acquisition of the Shonan Plant siteA theme 1 companies write about · 1 as a headwind · 0 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2026AdvancedAnnual report
「Shonan Plant relocation site (Fujisawa, Kanagawa) Corrugated-product plant relocation 40,837 10,913 Internal funds and borrowings February 2027 January 2029」
For the relocation to a new plant associated with the acquisition of part of the Shonan Plant site, we specified the investment amount, start date and scheduled completion date, and recognized a provision of ¥2,377 million for plant relocation costs. - FY2026-H1First statedAnnual report
「Part of the site of our Shonan Plant is located within the area covered by the urban planning road project for the Shonandai-Okami-Isehara Line. Following discussions with Kanagawa Prefecture, the project operator, we agreed to the land acquisition and will receive approximately ¥14.8 billion in compensation.」
The acquisition of part of the Shonan Plant site was finalized, and the approximately ¥14.8 billion compensation, handover scheduled for 31 March 2031, relocation to a new plant and relocation-related costs were disclosed. The impact on operating performance is still being examined, and maintaining supply obligations remains an issue.