Installation of solar power generation-based renewable energy equipment at the Tohoku Business Division
First written in FY2022. 1 of 4 entries say "Achieved", first in FY2023. Latest entry: FY2025.
0 other companies' latest entry also says "Cited as achieved".
- FY2025Cited as achievedAnnual report
「In fiscal 2023, we installed solar panels and a battery storage system and introduced an energy management system at the Tohoku Business Division. In addition, by using non-fossil power generated through methods that emit no CO₂, we achieved 100% renewable energy at the Tohoku Business Division.」
The installation of solar panels, a battery storage system and an energy management system at the Tohoku Business Division, and the achievement of 100% renewable energy, are being restated as past accomplishments. - FY2024AdvancedAnnual report
「In March 2023, the company installed solar panels and a battery storage system and introduced an energy management system at its Tohoku Division. It also achieved 100% renewable energy use at the Tohoku Division, its main site.」
The report states that the Tohoku Division introduced solar panels, a battery storage system and an energy management system, and achieved 100% renewable energy use. - FY2023AchievedAnnual report
「The company has installed renewable energy facilities based on solar power at its Tohoku Division.」
The solar-based renewable energy facilities at the Tohoku Division, which were scheduled for installation in the previous fiscal year, are stated to have been installed. - FY2022First statedAnnual report
「As part of efforts to strengthen initiatives to prevent global warming, protect resources and prevent environmental pollution, the company will install renewable energy facilities based on solar power at its Tohoku Division.」
As a specific measure for environmental conservation, resource protection and the prevention of global warming, the company has newly announced the installation of renewable energy facilities based on solar power at its Tohoku Division.