Expansion of the Circular Reinvestment Business
First written in FY2018. 22 of 24 entries say "Advanced", first in FY2019. Latest entry: FY2026.
21 other companies' latest entry also says "Advanced".
- FY2026AdvancedAnnual report
「The renewable energy business is increasing its operating facilities as planned. Total rated capacity once all facilities are operational, before adjustment for equity ownership, is expected to reach 2,693MW, up 166MW from the end of the fiscal year ending March 2025.」
Expected total rated capacity once all facilities are operational increased from 2,527MW to 2,693MW. The number of operating facilities reached 223, with operational rated capacity of 2,077MW. - FY2026-H1AdvancedAnnual report
「The renewable energy business is increasing its operating facilities as planned. Total rated capacity once all facilities are operational, before adjustment for equity ownership, is expected to reach 2,674MW, up 147MW from the end of the fiscal year ending March 2025.」
Operating renewable energy facilities increased from 196 to 216, and operational rated capacity rose from 1,955MW to 2,067MW. Expected capacity once all facilities are operational also increased from 2,527MW to 2,674MW. - FY2025AdvancedAnnual report
「The renewable energy business is increasing its operating facilities as planned. Total rated capacity once all facilities are operational, before adjustment for equity ownership, is expected to reach 2,527MW, up 699MW from the end of the previous fiscal year.」
Including the consolidation of リニューアブル・ジャパン, expected capacity once all facilities are operational increased to 2,527MW. The number of operating facilities also rose to 196, with operational rated capacity reaching 1,955MW. - FY2025-H1AdvancedAnnual report
「The renewable energy business is increasing its operating facilities as planned. New facilities are also being secured, and total rated capacity once all facilities are operational, before adjustment for equity ownership, is expected to reach 1,807MW, up 56MW from the end of the fiscal year ending March 2024.」
Operating renewable energy facilities totaled 90, with operational rated capacity of 1,413MW, while expected total rated capacity once all facilities are operational increased to 1,807MW. - FY2024SoftenedAnnual report
「As of 31 March 2024, rated capacity before adjustment for equity ownership was approximately 1.8GW, covering domestic projects only and including projects under development. We plan to increase this to 2.1GW in the fiscal year ending March 2026, equivalent to the output of 2 nuclear power plants.」
Renewable energy rated capacity had reached approximately 1.8GW, while the timing for achieving the previously stated fiscal 2025 target of 2.1GW was shown as the fiscal year ending March 2026. - FY2024-Q3AdvancedAnnual report
「The renewable energy business is expanding steadily, with the number of operating facilities increasing as planned. Once all facilities in Japan are operational, total rated capacity, before adjustment for equity ownership, is expected to reach 1,760MW.」
At the end of the third quarter, operating renewable energy facilities totaled 72, with operational rated capacity of 1,291MW, while expected total rated capacity once all facilities are operational increased from 1,625MW in the previous quarter to 1,760MW. - FY2024-Q2AdvancedAnnual report
「The renewable energy business is expanding steadily, with the number of operating facilities increasing as planned. Once all facilities are operational, total rated capacity, before adjustment for equity ownership, is expected to reach 1,625MW.」
Operating renewable energy facilities totaled 70, with operational rated capacity of 1,183MW, while expected total rated capacity once all facilities are operational increased from 1,612MW in the previous quarter to 1,625MW. - FY2024-Q1AdvancedAnnual report
「The renewable energy business is expanding steadily, with the number of operating facilities increasing as planned. Once all facilities are operational, total rated capacity, before adjustment for equity ownership, is expected to reach 1,612MW.」
Operating renewable energy facilities totaled 69, with operational rated capacity of 1,174MW, while expected total rated capacity once all facilities are operational increased from the previous 1,389MW to 1,612MW. - FY2023-Q3AdvancedAnnual report
「The renewable energy business is expanding steadily, with the number of operating facilities increasing as planned. Once all facilities are operational, total rated capacity, before adjustment for equity ownership, is expected to reach 1,389MW.」
Expected total rated capacity once all facilities are operational increased from 1,338MW in the previous quarter to 1,389MW. The company disclosed 63 operating facilities and rated capacity of 913MW at the end of the third quarter. - FY2023-Q2AdvancedAnnual report
「The renewable energy business is expanding steadily, with the number of operating facilities increasing as planned. Once all facilities are operational, total rated capacity, before adjustment for equity ownership, is expected to reach 1,338MW.」
Expected total rated capacity once all facilities are operational increased from 1,329MW in the first quarter to 1,338MW. The number of operating facilities is 67, with rated capacity of 937MW. - FY2023-Q1AdvancedAnnual report
「The renewable energy business is expanding steadily, with the number of operating facilities increasing as planned. Once all facilities are operational, total rated capacity, before adjustment for equity ownership, is expected to reach 1,329MW.」
Renewable energy power generation facilities increased from 66 facilities and 882MW at the end of the previous fiscal year to 67 facilities and 937MW at the end of the first quarter. Expected total rated capacity once all facilities are operational is 1,329MW. - FY2022AdvancedAnnual report
「To achieve further scale expansion, we plan to increase rated capacity from 1.3GW as of 31 March 2022, before adjustment for equity ownership and including projects under development, to 2.1GW in fiscal 2025, equivalent to the output of 2 nuclear power plants.」
A specific target was presented to increase renewable energy rated capacity from 1.3GW at the end of March 2022 to 2.1GW in fiscal 2025. - FY2022-Q3AdvancedAnnual report
「The renewable energy business is expanding steadily, with the number of operating facilities increasing as planned. Once all facilities are operational, total rated capacity, before adjustment for equity ownership, is expected to reach 1,314MW.」
Renewable energy power generation facilities increased from 48 facilities and 773MW at the end of the second quarter to 61 facilities and 817MW at the end of the third quarter. Expected total rated capacity once all facilities are operational also increased from 1,201MW to 1,314MW. - FY2022-Q2AdvancedAnnual report
「The renewable energy business is expanding steadily, with the number of operating facilities increasing as planned. Once all facilities are operational, total rated capacity, before adjustment for equity ownership, is expected to reach 1,201MW.」
Renewable energy power generation facilities increased to 48 facilities and 773MW at the end of the second quarter, while total rated capacity once all facilities are operational was indicated at approximately 1,201MW. - FY2022-Q1AdvancedAnnual report
「The renewable energy business is expanding steadily, with the number of operating facilities increasing as planned.」
Renewable energy power generation facilities increased from 38 facilities and 730MW at the end of the previous fiscal year to 47 facilities and 772MW at the end of the first quarter. - FY2021AdvancedAnnual report
「In addition, with respect to expanding the scope of Growth Strategy ②, the completion of multiple infrastructure-related properties, including renewable energy facilities and logistics facilities, has advanced the initiatives under this plan's growth strategy.」
In addition to the completion of multiple renewable energy and logistics facilities, operating renewable energy facilities totaled 38 with a capacity of 730MW, demonstrating concrete progress in the cyclical reinvestment business. - FY2021-Q3AdvancedAnnual report
「The renewable energy business is progressing steadily, with the number of operating facilities increasing as planned. At the end of the third quarter Number of operating facilities (facilities) 38 Rated capacity (MW) 677」
Renewable energy power generation facilities increased from 35 facilities and 596MW at the end of the second quarter to 38 facilities and 677MW, demonstrating concrete progress in the cyclical reinvestment business. - FY2021-Q2AdvancedAnnual report
「The renewable energy business is progressing smoothly, with the number of operating facilities increasing as planned.」
Renewable energy power generation facilities totaled 35 facilities with a rated capacity of 596MW at the end of the second quarter, up from 30 facilities and 487MW at the end of the previous fiscal year. - FY2021-Q1AdvancedAnnual report
「Renewable energy power generation facilities At the end of the first quarter Number of operating facilities (facilities) 33 Rated capacity (MW) 546」
Renewable energy power generation facilities increased from 30 facilities and 487MW at the end of the fiscal year ending March 2020 to 33 facilities and 546MW at the end of the first quarter. - FY2020AdvancedAnnual report
「In addition, with respect to expanding the scope of Growth Strategy ②, the completion of multiple infrastructure-related properties, including solar power facilities and logistics facilities under the renewable energy business, has advanced the initiatives under this plan's growth strategy.」
The completion of multiple infrastructure-related properties, including solar power facilities and logistics facilities, marked concrete progress in expanding the scope of the cyclical reinvestment business. - FY2019AdvancedAnnual report
「Under Growth Strategy 2, the Company also invested in renewable energy, including solar power generation, and infrastructure-related assets such as logistics facilities, advancing its initiatives under the growth strategy in this plan.」
Investments were made in renewable energy and infrastructure-related assets such as logistics facilities, advancing the expansion of the cyclical reinvestment business. - FY2018First statedAnnual report
「Under Growth Strategy 2, the Company also expanded the scope of its circular reinvestment business by advancing investment in renewable energy, including solar power generation, and infrastructure-related assets such as logistics facilities.」
The Company newly specified measures to expand renewable energy and infrastructure-related assets, including logistics facilities, as investment areas.