Expansion of renewable energy, centered on mega-solar projects
First written in FY2016-Q2. 21 of 32 entries say "Restated". Latest entry: FY2026-H1.
The whole theme swung hardest in 2025: 2 of 20 companies on the "Worse" side.
4 other companies' latest entry also says "Restated".
- FY2026-H1RestatedAnnual report
「The operating plants and generation capacity comprised 19 solar power plants generating approximately 81.0 MW and one wood biomass power plant generating approximately 6.2 MW, both of which operated smoothly. The company will continue to use renewable energy to supply safe and reliable energy with consideration for the environment.」
The operating scale remained at 19 solar power plants with approximately 81.0 MW and one wood biomass power plant with approximately 6.2 MW, together with the policy of continuing to supply energy generated from renewable sources. - FY2025-H1RestatedAnnual report
「The operating plants and generation capacity comprised 19 solar power plants generating approximately 81.0 MW and one wood biomass power plant generating approximately 6.2 MW. Although all plants operated smoothly, operations were affected by an increase in output curtailment instructions from electric power companies and reduced solar irradiation caused by unfavorable weather, mainly in the Tohoku region.」
While the operating scale remained at 19 solar power plants with approximately 81.0 MW and one wood biomass power plant with approximately 6.2 MW, the disclosure cited the impact of increased output curtailment instructions and reduced solar irradiation caused by unfavorable weather. - FY2024RestatedAnnual report
「The operating plants and generation capacity comprised 19 solar power plants generating approximately 81.0 MW and one wood biomass power plant generating approximately 6.2 MW, both of which operated smoothly. The company will continue to use renewable energy to supply safe and reliable energy with consideration for the environment.」
The operating scale remained at 19 solar power plants with approximately 81.0 MW and one wood biomass power plant with approximately 6.2 MW, together with the policy of continuing to supply energy generated from renewable sources. - FY2024-Q2RestatedAnnual report
「The operating plants and generation capacity comprised 19 solar power plants generating approximately 81.0 MW and one wood biomass power plant generating approximately 6.2 MW, both of which operated smoothly. The company will continue to use renewable energy to supply safe and reliable energy with consideration for the environment.」
The operating scale remained at 19 solar power plants with approximately 81.0 MW and one wood biomass power plant with approximately 6.2 MW, together with the policy of continuing to supply energy generated from renewable sources. - FY2024-Q1RestatedAnnual report
「The operating plants and generation capacity comprised 19 solar power plants generating approximately 81.0 MW and one wood biomass power plant generating approximately 6.2 MW, both of which operated smoothly. The company will continue to use renewable energy to supply safe and reliable energy with consideration for the environment.」
The operating scale was maintained at 19 solar power plants with approximately 81.0 MW and one wood biomass power plant with approximately 6.2 MW, and the company continued supplying energy generated from renewable sources. - FY2023AdvancedAnnual report
「One new solar power plant began operating in Higashimatsushima, Miyagi Prefecture, in October 2023. As a result, the operating plants and generation capacity comprised 19 solar power plants generating approximately 81.0 MW and one wood biomass power plant generating approximately 6.2 MW.」
The solar power plant in Higashimatsushima, Miyagi Prefecture, began operating in October 2023, expanding solar power generation from 18 plants with approximately 51.0 MW to 19 plants with approximately 81.0 MW. - FY2023-Q3RestatedAnnual report
「Although no new power plants began operating, the power plant in Nishigo Village, Nishirakawa District, Fukushima Prefecture, which has been operating since June 2022, contributed to revenue from the beginning of the period. The operating plants and generation capacity comprised 18 solar power plants generating approximately 51.0 MW and one wood biomass power plant generating approximately 6.2 MW, and the existing plants continued to operate smoothly.」
Although no new power plants began operating, the operating scale was maintained at 18 solar power plants with approximately 51.0 MW and one wood biomass power plant with approximately 6.2 MW, with the existing plants operating smoothly. - FY2023-Q2RestatedAnnual report
「During the cumulative second-quarter period under review, no new power plants began operating. However, as one solar power plant began operating in Nishigo Village, Nishishirakawa District, Fukushima Prefecture, in June 2022, the number of solar power plants increased by 1 year on year, contributing to revenue. The operating plants and generation capacity comprised 18 solar power plants generating approximately 51.0 MW and one wood biomass power plant generating approximately 6.2 MW.」
Although no new plants began operating during the quarter, the operating scale remained at 18 solar power plants with approximately 51.0 MW, including the plant that began operating in June 2022, and one wood biomass power plant with approximately 6.2 MW. - FY2023-Q1RestatedAnnual report
「This contributed to higher revenue for the consolidated fiscal period. The operating plants and generation capacity comprised 18 solar power plants generating approximately 51.0 MW and one wood biomass power plant generating approximately 6.2 MW.」
Although no new power plants began operating during the quarter, the operating scale remained at 18 solar power plants with approximately 51.0 MW and one wood biomass power plant with approximately 6.2 MW. - FY2022-Q3AdvancedAnnual report
「During the cumulative third-quarter period under review, one new solar power plant began operating in Nishigo Village, Nishishirakawa District, Fukushima Prefecture. As a result, the operating plants and generation capacity comprised 18 solar power plants generating approximately 51.0 MW and one wood biomass power plant generating approximately 6.2 MW.」
One solar power plant began operating in Nishigo Village, Nishishirakawa District, Fukushima Prefecture, expanding solar power generation from 17 plants with approximately 32.1 MW in the previous quarter to 18 plants with approximately 51.0 MW. - FY2022-Q2RestatedAnnual report
「During the cumulative second-quarter period under review, no new power plants began operating. However, as one solar power plant began operating in Misaki, Sennan District, Osaka Prefecture, in May 2021, the number of solar power plants increased by 1 year on year. The operating plants and generation capacity currently comprise 17 solar power plants generating approximately 32.1 MW and one wood biomass power plant generating approximately 6.2 MW.」
Although no new plants began operating during the quarter, the operating scale remained at 17 solar power plants with approximately 32.1 MW, including the plant that began operating in May 2021, and one wood biomass power plant with approximately 6.2 MW. - FY2022-Q1RestatedAnnual report
「During the cumulative first-quarter period under review, no new power plants began operating. However, as one new solar power plant began operating in Misaki, Sennan District, Osaka Prefecture, in May 2021, the number of solar power plants increased by 1 year on year. The operating plants and generation capacity currently comprise 17 solar power plants generating approximately 32.1 MW and one wood biomass power plant generating approximately 6.2 MW.」
Although no new plants began operating during the quarter, the operating scale remained at 17 solar power plants with approximately 32.1 MW, including the plant that began operating in May 2021, and one wood biomass power plant with approximately 6.2 MW. - FY2021-Q3AdvancedAnnual report
「During the cumulative third-quarter period under review, one new solar power plant began operating in Osaka Prefecture. As a result, the operating plants and generation capacity comprised 17 solar power plants generating approximately 32.1 MW and one wood biomass power plant generating approximately 6.2 MW.」
One new solar power plant began operating in Osaka Prefecture, expanding solar power generation from 16 plants with approximately 22.0 MW in the previous quarter to 17 plants with approximately 32.1 MW. - FY2021-Q1RestatedAnnual report
「No new power plants began operating. The operating plants and generation capacity remained unchanged from the end of the previous fiscal year at 16 solar power plants generating approximately 22.0 MW and one wood biomass power plant generating approximately 6.2 MW.」
No new power plants began operating, and the operating scale was maintained at 16 solar power plants with approximately 22.0 MW and one wood biomass power plant with approximately 6.2 MW. - FY2020RestatedAnnual report
「No new power plants began operating. Accordingly, the operating plants and generation capacity remained at 16 solar power plants generating approximately 22.0 MW and one wood biomass power plant generating approximately 6.2 MW.」
No new power plants began operating, and the operating scale was maintained at 16 solar power plants with approximately 22.0 MW and one wood biomass power plant with approximately 6.2 MW. - FY2020-Q3RestatedAnnual report
「During the cumulative third-quarter period under review, no new power plants began operating. Accordingly, the operating plants and generation capacity remained at 16 solar power plants generating approximately 22.0 MW and one wood biomass power plant generating approximately 6.2 MW.」
No new power plants began operating, and the operating scale remained at 16 solar power plants with approximately 22.0 MW and one wood biomass power plant with approximately 6.2 MW. - FY2020-Q2RestatedAnnual report
「During the cumulative second-quarter period under review, no new power plants began operating. The operating plants and generation capacity comprised 16 solar power plants generating approximately 22.0 MW and one wood biomass power plant generating approximately 6.25 MW.」
No new power plants began operating, and the operating scale remained at 16 solar power plants with approximately 22.0 MW and one wood biomass power plant with approximately 6.25 MW. - FY2020-Q1RestatedAnnual report
「During the cumulative first-quarter period under review, no new power plants began operating. The operating plants and generation capacity remained unchanged from the end of the previous fiscal year at 16 solar power plants with approximately 22.0 MW and one wood biomass power plant with approximately 6.2 MW.」
The operating scale remained unchanged from the end of the previous fiscal year at 16 solar power plants with approximately 22.0 MW and one wood biomass power plant with approximately 6.2 MW. - FY2019RestatedAnnual report
「As of 31 October 2019, the number of operating solar power plants had reached 16, generating approximately 22.0 MW.」
The scale of solar power operations remained at 16 plants with approximately 22.0 MW. The renewable energy business also operated a wood biomass power plant. - FY2019-Q3RestatedAnnual report
「During the cumulative third-quarter period under review, one new solar power plant each began operating in Hokkaido and Wakayama Prefecture. As a result, the number of operating solar power plants nationwide reached 16, generating approximately 22.0 MW. The company also operated a wood biomass power plant in Hokkaido, generating approximately 6.25 MW.」
The reported scale of operations remained unchanged from the previous quarter at 16 solar power plants with approximately 22.0 MW and a wood biomass power plant with approximately 6.25 MW. - FY2019-Q2AdvancedAnnual report
「During the cumulative second-quarter period under review, one new solar power plant each began operating in Hokkaido and Wakayama Prefecture. As a result, the number of operating solar power plants nationwide reached 16, generating approximately 22.0 MW. The company also operated a wood biomass power plant in Hokkaido, generating approximately 6.25 MW.」
One solar power plant each began operating in Hokkaido and Wakayama Prefecture, expanding solar power generation from 14 plants with approximately 18.0 MW to 16 plants with approximately 22.0 MW. - FY2019-Q1AdvancedAnnual report
「During the cumulative first-quarter period under review, the Eco Renewable Energy business operated 14 solar power plants nationwide, generating approximately 18.0 MW. It also operated a wood biomass power plant in Hokkaido, generating approximately 6.25 MW.」
The company continued to operate 14 solar power plants with approximately 18.0 MW of capacity, and also reported the operation of a wood biomass power plant with approximately 6.25 MW in Hokkaido, broadening the scope of its renewable energy operations. - FY2018-Q3RestatedAnnual report
「During the cumulative third quarter, a solar power plant began operating in Osaka Prefecture in February. As a result, the company operated solar power facilities at 14 locations, comprising 4 in Hokkaido, 4 in Hyogo Prefecture, 1 in Fukuoka Prefecture, 1 in Shiga Prefecture, 2 in Osaka Prefecture, 1 in Tokushima Prefecture, and 1 in Ibaraki Prefecture, with capacity of approximately 18.0 MW.」
The scale of 14 operating locations and approximately 18.0 MW following the start-up of the Osaka Prefecture plant remains unchanged from the previous quarter. - FY2018-Q2AdvancedAnnual report
「During the cumulative second quarter, a new solar power plant began operating in Osaka Prefecture. As a result, the company operated solar power facilities at 14 locations, comprising 4 in Hokkaido, 4 in Hyogo Prefecture, 1 in Fukuoka Prefecture, 1 in Shiga Prefecture, 2 in Osaka Prefecture, 1 in Tokushima Prefecture, and 1 in Ibaraki Prefecture, with capacity of approximately 18.0 MW.」
A new solar power plant began operating in Osaka Prefecture, increasing operating facilities from 13 locations and approximately 15.9 MW in the previous quarter to 14 locations and approximately 18.0 MW. - FY2018-Q1AdvancedAnnual report
「The eco-renewable energy business operates solar power facilities at 13 locations, comprising 4 in Hokkaido, 4 in Hyogo Prefecture, 1 in Fukuoka Prefecture, 1 in Shiga Prefecture, 1 in Osaka Prefecture, 1 in Tokushima Prefecture, and 1 in Ibaraki Prefecture, with capacity of approximately 15.9 MW.」
Operating solar-generation capacity increased from 12 locations and 13.5 MW in the previous quarter to 13 locations and approximately 15.9 MW. The company also recorded a gain on the transfer of rights to one solar power project. - FY2017-Q3AdvancedAnnual report
「The eco-renewable energy business operates solar power facilities at 12 locations, comprising 4 in Hokkaido, 4 in Hyogo Prefecture, 1 in Fukuoka Prefecture, 1 in Shiga Prefecture, 1 in Osaka Prefecture, and 1 in Tokushima Prefecture, with total capacity of 13.5 MW. The scale of power generation decreased from the same period of the previous year because some power plants were sold in October 2016.」
Operating capacity increased from 10 locations and approximately 9.3 MW in the previous quarter to 12 locations and 13.5 MW. At the same time, the year-on-year reduction in scale resulting from the sale of some power plants in October 2016 continues to be reported. - FY2017-Q2RestatedAnnual report
「The eco-renewable energy business operates utility-scale solar facilities at 10 locations, comprising 4 in Hokkaido, 4 in Hyogo Prefecture, 1 in Fukuoka Prefecture, and 1 in Shiga Prefecture, with capacity of approximately 9.3 MW. The scale of power generation decreased from the same period of the previous year because some power plants were sold in October 2016.」
The company continues to report utility-scale solar generation at 10 locations with capacity of approximately 9.3 MW, and the reduction in scale resulting from the sale of some power plants in October 2016, as in the previous quarter. - FY2017-Q1SoftenedAnnual report
「The eco-renewable energy business operates utility-scale solar facilities at 10 locations, comprising 4 in Hokkaido, 4 in Hyogo Prefecture, 1 in Fukuoka Prefecture, and 1 in Shiga Prefecture, with capacity of approximately 9.3 MW. The scale of power generation decreased from the same period of the previous year because some power plants were sold in October 2016.」
Operating capacity decreased from 14 locations and 16.3 MW in the previous quarter to 10 locations and approximately 9.3 MW. The sale of some power plants is specifically identified as the reason, making this a contraction from the previously reported expansion in scale and direction. - FY2016-Q3AdvancedAnnual report
「As of the end of July 2016, utility-scale solar facilities had begun generating power at 14 locations, comprising 4 in Hokkaido, 4 in Hyogo Prefecture, 5 in Fukuoka Prefecture, and 1 in Shiga Prefecture, with total capacity of 16.3 MW. The company will continue to promote new energy generation projects in various regions, centered on utility-scale solar power, to expand the use of safer, cleaner renewable energy.」
Operating capacity increased from 13 locations and 15.6 MW as of the second quarter to 14 locations and 16.3 MW. The policy of expanding the use of renewable energy also continues. - FY2016-Q2First statedAnnual report
「As of the end of April 2016, utility-scale solar facilities had begun generating power at 13 locations, comprising 4 in Hokkaido, 4 in Hyogo Prefecture, and 5 in Fukuoka Prefecture, with total capacity of 15.6 MW. The company will continue to promote new energy generation projects in various regions, centered on utility-scale solar power, to expand the use of safer, cleaner renewable energy.」
The company reports 13 operating locations with capacity of 15.6 MW and continues to pursue expansion of renewable energy centered on utility-scale solar power.