Rasa (3023) · RiskMaterialisedLatest Earnings (2026-08-07): "Worsened"

Extension of the construction period due to additional construction work and other factors

First written in FY2019-Q1. 7 of 13 entries say "Mitigated", first in FY2019-Q2. Latest entry: 2026-08-07.

13entries
9years
1from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseMitigatedFY2019-Q2MitigatedFY2021-Q2 – FY2022-Q2MaterialisedFY2025 – 2026-08-072018: 220182019: 020192020: 420202021: 420212022: 020222023: 020232024: 020242025: 220252026: 12026
Same theme, other companies

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. 2026-08-07WorsenedEarnings

    「Provision for loss on construction contracts 16 19」

    The provision for loss on construction contracts increased from ¥16 million at the end of the previous consolidated fiscal year to ¥19 million at the end of the first quarter.
  2. FY2026-H1MaterialisedAnnual report

    「However, delays in the schedules of shield tunnelling machine projects for overseas markets affected sales. Sales in the related segment amounted to ¥4,070 million, a decrease of ¥201 million, or 4.7%, from the previous year.」

    Project-delay risk actually affected sales of shield tunneling machines for overseas markets, and sales in the industrial and construction machinery business decreased 4.7% year on year.
  3. FY2025MaterialisedAnnual report

    「In the industrial and construction machinery business, sales of shield tunneling machines for overseas markets were affected by project delays, but domestic demand for sewage-sludge pumps, parts and servicing remained firm.」

    The report specifically stated that project-delay risk affected sales of shield tunneling machines for overseas markets. Meanwhile, domestic demand for pumps and servicing provided support.
  4. FY2022-Q2MitigatedAnnual report

    「In the plant and equipment construction business, partly due to the early completion of scheduled projects, including large-scale projects, sales in the related segment amounted to ¥3,949 million, an increase of ¥1,649 million, or 71.7%, from the same quarter of the previous year.」

    The early completion of scheduled projects improved conditions from the period when project delays had weighed on performance, and sales in the plant and equipment construction business increased.
  5. FY2022-Q1MitigatedAnnual report

    「In the plant and equipment construction business, scheduled energy-related projects were completed as planned, resulting in sales of ¥2,059 million in the related segment, an increase of ¥915 million, or 80.1%, from the same quarter of the previous year. Higher sales also lifted segment profit to ¥215 million, an increase of ¥66 million, or 44.9%, from the same quarter of the previous year.」

    Scheduled energy-related projects were completed as planned, and sales in the plant and equipment construction business increased 80.1% year on year, while segment profit increased 44.9%. Conditions improved from the period when project delays had affected performance.
  6. FY2021MitigatedAnnual report

    「In the plant and equipment construction business, scheduled and additional projects, including large-scale projects, were completed, resulting in sales of ¥6,175 million in the related segment, an increase of ¥881 million, or 16.6%, from the previous consolidated fiscal year.」

    Scheduled and additional projects were completed, improving conditions from the period when project delays had weighed on performance.
  7. FY2021-Q3MitigatedAnnual report

    「In the plant and equipment construction business, scheduled projects, including large-scale projects, were completed as planned, resulting in sales of ¥4,088 million in the related segment, an increase of ¥1,169 million, or 40.1%, from the same quarter of the previous year.」

    Scheduled projects were completed as planned, improving conditions from the previous fiscal year, when project delays had affected performance. Sales in the plant and equipment construction business increased 40.1%.
  8. FY2021-Q2MitigatedAnnual report

    「In the plant and equipment construction business, partly due to the early completion of scheduled projects, sales in the related segment amounted to ¥2,261 million, an increase of ¥25 million, or 1.1%, from the same quarter of the previous year.」

    The early completion of scheduled projects improved conditions from the situation in which project delays had weighed on performance, and sales in the plant and equipment construction business increased.
  9. FY2021-Q1MaterialisedAnnual report

    「In the plant and equipment construction business, although projects were completed largely as planned, the impact of some delays resulted in sales of ¥1,145 million in the related segment, a decrease of ¥34 million, or 2.9%, from the same quarter of the previous year.」

    Project delays also occurred in the first quarter of the current fiscal year, and sales in the plant and equipment construction business decreased 2.9% year on year.
  10. FY2020MitigatedAnnual report

    「In the plant and equipment construction business, progress was made in completing scheduled projects, including large-scale projects, resulting in sales of ¥5,307 million in the related segment, an increase of ¥269 million, or 5.4%, from the previous consolidated fiscal year.」

    Against the project-delay risk that had arisen in the previous fiscal year, progress was made in completing scheduled projects, and sales in the plant and equipment construction business increased.
  11. FY2020-Q3MaterialisedAnnual report

    「In the plant and equipment construction business, due partly to delays in scheduled projects, sales in the related segment amounted to ¥2,918 million, a decrease of ¥154 million, or 5.0%, from the same quarter of the previous year.」

    Scheduled projects were delayed, and sales in the plant and equipment construction business decreased 5.0% year on year.
  12. FY2019-Q2MitigatedAnnual report

    「In the plant and equipment construction business, projects that had been delayed by additional construction and other factors were completed during the period, resulting in sales of ¥2,110 million in the related segment, an increase of ¥389 million, or 22.6%, from the same quarter of the previous year.」

    Projects delayed by additional construction and other factors, as reported in the previous quarter, were completed during the period, and sales in the plant and equipment construction business increased 22.6% year on year.
  13. FY2019-Q1First statedAnnual report

    「In the plant and equipment construction business, although some projects were delayed due to additional construction and other factors, sales in the related segment amounted to ¥592 million, an increase of ¥8 million, or 1.5%, from the same quarter of the previous year.」

    The report stated that some projects had been delayed due to additional construction and other factors.
Moved together

"Strengthening Equity Capital and the Financial Base and Enhancing Investment Capacity" moved the same way as this thread, in the same document, in 7 of its 13 moves.

765555★123456
  1. ★This thread
  2. 1Strengthening Equity Capital and the Financial Base and Enhancing Investment Capacity7×
  3. 2Commodity Price Volatility Risk for Resources and Chemical Products6×
  4. 3Establishing New Revenue Streams and Expanding Revenue Through 6 Businesses5×
  5. 4Changes in Economic Trends and Capital Investment Trends5×
  6. 5Expansion of orders for expansion, renovation, repairs and new construction at domestic manufacturing facilities5×
  7. 6Weak Demand for Synthetic Resins for the Wire Industry5×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Rasa yet. It last moved in the Earnings of 2026-08-07: "Worsened".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Extension of the construction period due to additional construction work and other factors | Rasa Corporation (3023) | Komori