Earthquake and Other Natural Disaster Risks at Production Sites in the Tokai Region
First written in FY2016. 6 of 7 entries say "Restated". Latest entry: FY2025.
The whole theme swung hardest in 2018: 32 of 131 companies on the "Worse" side.
90 other companies' latest entry also says "Restated".
- FY2025RestatedAnnual report
「The Company has its principal production facilities in the Tokai region, specifically Fuji, Shizuoka Prefecture. Although it has implemented measures including reinforcement work to mitigate damage from earthquakes and other disasters,」
The discussion continues to describe natural disaster risks affecting the Fuji Plant as a principal production facility, together with measures including reinforcement work. - FY2025-H1RestatedAnnual report
「During the interim consolidated accounting period, Japan's economy remained in a moderate recovery, as improvements in consumer sentiment resulting from wage increases and fixed-amount tax cuts were offset by concerns about high prices, volatile share prices, alertness to the Nankai Trough earthquake, disruptions to the movement of people and goods caused by heavy rain, and the prolonged labor shortage.」
The Nankai Trough earthquake risk and disruptions to the movement of people and goods caused by heavy rain are described as part of the economic environment during the interim consolidated accounting period. It states that there have been no significant changes in the natural disaster risks affecting the principal production facilities. - FY2021RestatedAnnual report
「The Company has its principal production facilities in the Tokai region, specifically Fuji, Shizuoka Prefecture. Although it has implemented measures including reinforcement work to mitigate damage from earthquakes and other disasters, a major earthquake or other disaster in the region could, depending on its severity, seriously disrupt the plant's production facilities and operations, while recovery could incur substantial costs and materially affect the Company's operating results, financial condition and cash flows.」
The discussion continues to address natural disaster risks, including earthquakes, at production facilities in the Tokai region and measures including reinforcement work. - FY2020RestatedAnnual report
「The Company has its principal production facilities in the Tokai region, specifically Fuji, Shizuoka Prefecture. Although it has implemented measures including reinforcement work to mitigate damage from earthquakes and other disasters, a major earthquake or other disaster in the region could, depending on its severity, seriously disrupt the plant's production facilities and operations, while recovery could incur substantial costs and materially affect the Company's operating results, financial condition and cash flows.」
The discussion continues to describe natural disaster risks at production facilities in the Tokai region and measures including reinforcement work. - FY2019RestatedAnnual report
「The Company has its principal production facilities in the Tokai region, specifically Fuji, Shizuoka Prefecture. Although it has implemented measures including reinforcement work to mitigate damage from earthquakes and other disasters, a major earthquake or other disaster in the region could, depending on its severity, seriously disrupt the plant's production facilities and operations, while recovery could incur substantial costs and materially affect the Company's operating results, financial condition and cash flows.」
The discussion continues to describe the risk of natural disasters, including earthquakes, at production facilities in the Tokai region, together with measures including reinforcement work. - FY2018RestatedAnnual report
「The Company has its principal production facilities in the Tokai region, specifically Fuji, Shizuoka Prefecture. Although it has implemented measures including reinforcement work to mitigate damage from earthquakes and other disasters, a major earthquake or other disaster in the region could, depending on its severity, seriously disrupt the plant's production facilities and operations, while recovery could incur substantial costs and materially affect the Company's operating results, financial condition and cash flows.」
The discussion continues to describe the risk of natural disasters, including earthquakes, at production facilities in the Tokai region. - FY2016First statedAnnual report
「The Company has its principal production facilities in the Tokai region, specifically Fuji, Shizuoka Prefecture. Although it has implemented measures including reinforcement work to mitigate damage from earthquakes and other disasters, a major earthquake or other disaster in the region could, depending on its severity, seriously disrupt the plant's production facilities and operations, while recovery could incur substantial costs and materially affect the Company's operating results, financial condition and cash flows.」
While describing measures including reinforcement work, the discussion identifies the risks of operational shutdowns and recovery costs in the event of a major disaster.