Restructuring the production system and securing frozen noodle production capacity
First written in FY2025. 1 of 3 entries say "Advanced", first in 2026-05-12. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026RestatedAnnual report
「Shimadaya Kanto Co., Ltd., Maebashi Plant (Maebashi, Gunma Prefecture), Foodservice Business, construction of a new frozen noodle plant, ¥2,455.159 million, construction start: September 2024, scheduled completion: May 2026, 10% increase in frozen noodle production capacity」
The plan to build a new frozen noodle plant at the Maebashi Plant remains in place, with completion scheduled for May 2026 and a planned 10% increase in production capacity reiterated. - 2026-05-12AdvancedEarnings presentation
「June 2026: New frozen noodle production line scheduled to begin operation Frozen noodle production capacity to increase by approximately 10%」
The new frozen noodle production line at the Maebashi Plant site is scheduled to begin operation in June 2026, increasing production capacity by approximately 10%. - FY2025First statedAnnual report
「Shimadaya Kanto Co., Ltd., Maebashi Plant (Maebashi, Gunma Prefecture), Foodservice Business, construction of a new frozen noodle plant, planned investment of ¥2,636 million, construction start: September 2024, scheduled completion: May 2026, 10% increase in frozen noodle production capacity」
Against a backdrop of tight frozen noodle production capacity and expanding overseas sales, the Company plans to build a new facility at the Maebashi Plant, with completion scheduled for May 2026 and a 10% increase in production capacity.