Taihei Dengyo (1968) · InitiativeAchieved

Initiating a plan to own in-house power plants

First written in FY2017. 5 of 10 entries say "Advanced", first in FY2018-Q2. Latest entry: FY2020-Q3.

10entries
4years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2017 – FY2018-Q1RestatedFY2018-Q3AdvancedFY2018 – FY2019-Q2RestatedFY2019-Q3AdvancedFY2019 – FY2020-Q32017: 320172018: 320182019: 320192020: 12020
Same theme, other companies
Expansion of Company-Owned Megasolar Investment PropertiesA theme 11 companies write about · 0 as a headwind · 11 as a tailwind

1 other company's latest entry also says "Achieved".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2020-Q3AchievedAnnual report

    「The Nishikaze Shinto Biomass Power Plant, which was under planning at the end of the previous consolidated fiscal year, was completed in October 2019 and commenced commercial operations.」

    The company stated that the target facility had reached completion of construction and the start of commercial operations.
  2. FY2020-Q2AdvancedAnnual report

    「At the Nishikaze Shinto Biomass Power Plant, which was completed in October this year, we will contribute to the local community by helping realize a low-carbon society through renewable energy, an energy source for the next generation, while deepening our knowledge of next-generation power generation technologies and the electricity sales business and working to enhance corporate value.」

    The company stated that the Nishikaze Shinto Biomass Power Plant is scheduled for completion in October this year, marking progress toward acquiring expertise in power generation technology and the electricity sales business.
  3. FY2019AdvancedAnnual report

    「The Nishikaze Shinto Biomass Power Plant (Hiroshima, Hiroshima Prefecture), whose construction began in earnest in April last year, is scheduled for completion in the current fiscal year,」

    The plan to own a company-operated power plant progressed from the full-scale start of construction of the Nishikaze Shinto Biomass Power Plant to the stage where completion is scheduled for the current fiscal year.
  4. FY2019-Q3RestatedAnnual report

    「In addition, construction of the Nishikaze Shinto Biomass Power Plant (Hiroshima, Hiroshima Prefecture), which will be the company's first company-owned power plant, is progressing in earnest, and the entire company is working toward the start of operations in November 2019.」

    The company continues to state that construction of the Nishikaze Shinto Biomass Power Plant is progressing in earnest and that operations are targeted to begin in November 2019.
  5. FY2019-Q2AdvancedAnnual report

    「In addition, full-scale construction work began on the Nishikaze Shinto Biomass Power Plant (Hiroshima, Hiroshima Prefecture), which will be the first power plant owned by the Company, and the entire Company is working toward commencing operations in November next year.」

    The plan to own a company-operated power plant progressed to the full-scale construction phase for the target facility, with a target start of operations in November of the following year.
  6. FY2018AdvancedAnnual report

    「In addition, construction of the Nishikaze Shinto Biomass Power Plant (Hiroshima, Hiroshima Prefecture), which will be the first power plant owned by the Company, began in April this year. We will aim to commence operations in November next year while contributing to regional development and giving consideration to safety and the environment.」

    The plan to own a company-operated power plant progressed to the start of construction of the Nishikaze Shinto Biomass Power Plant, with a target start of operations in November of the following year.
  7. FY2018-Q3RestatedAnnual report

    「Preparations for plans to own the Nishikaze Shinto Biomass Power Plant (Hiroshima, Hiroshima Prefecture)」

    The company continues preparations to own the Nishikaze Shinto Biomass Power Plant.
  8. FY2018-Q2AdvancedAnnual report

    「Preparations for plans to own the Nishikaze Shinto Biomass Power Plant (Hiroshima, Hiroshima Prefecture)」

    The company specified the Nishikaze Shinto Biomass Power Plant as the subject of its plan to own a company-operated power plant and stated that preparations had begun.
  9. FY2018-Q1RestatedAnnual report

    「Initiation of plans to own company-operated power plants,」

    The company reiterated the initiation of a plan to own company-operated power plants as a measure under its medium-term management plan.
  10. FY2017First statedAnnual report

    「Initiation of plans to own company-operated power plants,」

    The company disclosed for the first time its policy of initiating a plan to own company-operated power plants.
Moved together

"Addressing high-efficiency thermal power, biomass and nuclear safety improvement projects" moved the same way as this thread, in the same document, in 6 of its 10 moves.

654332★123456
  1. ★This thread
  2. 1Addressing high-efficiency thermal power, biomass and nuclear safety improvement projects6×
  3. 2Strengthening production capacity, alliances and specialist organizations to support an integrated operating structure5×
  4. 3Expanding Renewable Energy Adoption and Achieving an Optimal Energy Mix4×
  5. 4Expanding maintenance coverage, stationing personnel at repair sites, and promoting long-term maintenance contracts3×
  6. 5Risk of guarantee obligations if the share price falls in relation to the E-Ship Trust3×
  7. 6Promotion of Overseas Business Centered on Myanmar and Indonesia2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Taihei Dengyo yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Initiating a plan to own in-house power plants | TAIHEI DENGYO KAISHA,LTD. (1968) | Komori