Capital investment for rebuilding the new head office building
First written in FY2024-Q2. 3 of 6 entries say "Advanced", first in FY2024. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026AdvancedAnnual report
「Filing company Head office (new head office building) (Naka Ward, Nagoya) Buildings and other assets (rebuilding) 23,923 3,558 Borrowings and internal funds Scheduled for completion in fiscal 2028」
For the rebuilding of the new head office building, the Company disclosed planned investment of ¥23,923 million, ¥3,558 million already paid, funding through borrowings and internal funds, and scheduled completion in fiscal 2028. - FY2026-H1RestatedAnnual report
「Major funding needs for investment purposes included reconstruction of the Company’s new head office building and construction of a new company facility in the facilities-construction business.」
The Company continues to identify rebuilding the new head office building as a major funding need for investment purposes. - FY2025-H1AdvancedAnnual report
「Filing company Head office (new head office building) (Naka Ward, Nagoya) Buildings and other assets (rebuilding) 23,923 599 Borrowings and internal funds Scheduled for completion in fiscal 2028」
For the rebuilding of the new head office building, the Company finalised and disclosed a total planned investment of ¥23,923 million, ¥599 million already paid, funding through borrowings and internal funds, and scheduled completion in fiscal 2028. - FY2024AdvancedAnnual report
「Filing company Head office (new head office building) (Naka Ward, Nagoya) Buildings and other assets (rebuilding) Undetermined 595 Borrowings and internal funds Scheduled for completion in fiscal 2028」
For the rebuilding of the new head office building, the Company disclosed ¥595 million already paid, funding through borrowings and internal funds, and scheduled completion in fiscal 2028, providing greater detail on the plan. - FY2024-Q3RestatedAnnual report
「Major funding needs for investment purposes included reconstruction of the Company’s new head office building and construction of a new company facility in the facilities-construction business.」
The Company continues to identify rebuilding the new head office building as a major funding need for investment purposes. - FY2024-Q2First statedAnnual report
「Major funding needs for investment purposes included reconstruction of the Company’s new head office building and construction of a new company facility in the facilities-construction business.」
The Company identified for the first time as an independent theme the rebuilding of its new head office building as a major funding need for investment purposes.