Komori
Tokyo Energy & Systems (1945) · InitiativeAdvanced

Transition to contracts for turnkey design, procurement and construction

First written in FY2018. 5 of 8 entries say "Advanced", first in FY2019. Latest entry: FY2024-Q2.

8entries
6years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2018AdvancedFY2019 – FY20212018: 120182019: 120192020: 020202021: 220212022: 120222023: 32023
Same theme, other companies
Integrated EPC and O&M Services for the Environmental BusinessA theme 10 companies write about · 1 as a headwind · 11 as a tailwind

8 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2024-Q2AdvancedAnnual report

    「Rather than remaining limited to conventional contract construction, we have worked diligently to expand orders and sales and generate profits over the medium to long term by energetically pursuing sales activities throughout Japan as an integrated engineering company covering the entire energy business value chain. These activities include proposing one-stop solutions addressing customers' and communities' decarbonization needs, as well as pursuing projects under the Long-Term Decarbonized Power Supply Auction, projects related to decarbonization leading areas and regional resilience projects.」

    As a comprehensive engineering company covering the entire energy-business value chain beyond individual stages such as EPC and O&M, the Company is expanding its proposal activities for decarbonisation-related projects.
  2. FY2023AdvancedAnnual report

    「In addition to hydroelectric power projects, including the Tottori Prefectural Hydroelectric Power Plant Redevelopment Project, and promoting the use of locally produced energy in each region, we will continue working to create new businesses involving PPA (power purchase agreements), CCUS (carbon capture, utilization and storage) and other areas.」

    In addition to integrated support across EPC, O&M and other stages, the Company is expanding its focus to the creation of new solutions including hydropower, distributed energy, PPA and CCUS.
  3. FY2023-Q3RestatedAnnual report

    「We propose integrated, one-stop services from EPC (engineering, procurement and construction) through O&M (operations and maintenance) in the cogeneration and renewable energy sectors, including solar, hydropower and biomass.」

    The Company continues to offer integrated contracts and service proposals from EPC through O&M in the cogeneration, solar, hydropower and biomass sectors.
  4. FY2022AdvancedAnnual report

    「We will advance solution proposals to meet customers’ business needs at every stage of the value chain, including capital participation, owners’ engineering (management services during construction), construction work, O&M (operations and maintenance) and LTSA (long-term service agreements).」

    The Company is moving beyond integrated support centred on EPC and O&M toward value-chain coverage encompassing capital participation, management during construction, construction, O&M and LTSA.
  5. FY2022-Q2RestatedAnnual report

    「We propose integrated, one-stop services ranging from EPC (engineering, procurement and construction) to O&M (operation and maintenance)」

    The Company continues to pursue integrated contracts and service provision from EPC through O&M.
  6. FY2021AdvancedAnnual report

    「To broaden its business scope, we will leverage the technological capabilities developed to date to provide integrated, one-stop services ranging from EPC (engineering, procurement and construction) to O&M (operation and maintenance) for customer-owned facilities such as cogeneration systems and air-conditioning equipment, as well as construction of renewable energy facilities including solar, small-scale hydro, wind, biomass and geothermal power facilities.」

    The Company explicitly stated its policy of applying integrated contracts from EPC through O&M to customer-owned facilities and multiple renewable energy facilities.
  7. FY2019AdvancedAnnual report

    「We will actively pursue sales activities so that we can consistently secure orders from EPC (engineering, procurement and construction) through O&M (operations and maintenance) for cogeneration systems, air-conditioning facilities, and renewable energy facilities including solar, small-scale hydropower, wind, biomass and geothermal power.」

    The Company is moving from the stage of pursuing conventional turnkey contracts to actively developing sales activities aimed at securing integrated contracts from EPC through O&M.
  8. FY2018First statedAnnual report

    「We will pursue contracts under which we undertake the design, procurement and construction of these projects on a turnkey basis.」

    The Company is pursuing an order structure under which it undertakes design, procurement and construction on a turnkey basis for facilities including cogeneration and biomass facilities.
Moved together

"Decommissioning and safety-related work at nuclear power plants" moved the same way as this thread, in the same document, in 4 of its 8 moves.

444444★123456
  1. ★This thread
  2. 1Decommissioning and safety-related work at nuclear power plants4×
  3. 2Expansion of Renewable Energy-Related Construction4×
  4. 3Providing high-value-added services through consultative sales and a one-stop approach4×
  5. 4Power Generation Facility Construction and LTSA/O&M for New Power Providers and Others4×
  6. 5Overseas expansion through a joint venture in Thailand4×
  7. 6Purchase of Machinery and Equipment, Tools and Fixtures to Expand and Improve Production Capacity4×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Tokyo Energy & Systems's next results are scheduled for 2026-11-05. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Transition to contracts for turnkey design, procurement and construction | TOKYO ENERGY & SYSTEMS INC. (1945) | Komori