Penta-Ocean Construction (1893) · InitiativeRestated
Development of a rationalized RC foundation construction method
First written in FY2018. 1 of 2 entries say "Restated". Latest entry: FY2019.
2entries
2years
0from disclosures
How it moved
Same theme, other companies
Improving Construction Productivity Through Structural Construction Methods, BIM, and PrefabricationA theme 14 companies write about · 0 as a headwind · 19 as a tailwind
The whole theme swung hardest in 2018: 1 of 8 companies on the "Worse" side.
7 other companies' latest entry also says "Restated".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2019RestatedAnnual report
「During the consolidated fiscal year, the method was applied to part of the foundation beams at a building construction site. As a result, labor savings and a shorter construction period were achieved compared with conventional methods.」
The application of the rationalized RC foundation construction method at a building construction site and the resulting labor savings and shorter construction period have been reconfirmed. - FY2018First statedAnnual report
「Structural testing confirmed that the foundation beams produced using the new method satisfied the target performance requirements for short-term allowable stress, including structural capacity and degree of damage.」
The structural performance and construction accuracy of a labor-saving foundation-beam method using half-precast concrete panels as formwork were verified.