Efficiently Converting More Than ¥40 Billion of Backlog into Revenue and Profit
First written in FY2022. 3 of 7 entries say "Advanced", first in FY2025-H1. Latest entry: FY2026.
The whole theme swung hardest in 2020: 16 of 94 companies on the "Worse" side.
45 other companies' latest entry also says "Other".
- FY2026Carryover work into the next period of ¥43.5 billionAnnual report
「合計 44,986 29,289 74,275 30,730 43,545」
当事業年度末の次期繰越工事高は43,545百万円となり、前事業年度の44,986百万円から減少した。 - 2026-05-15AdvancedEarnings presentation
「Sales increased as large-scale construction progressed generally smoothly both at construction sites and in product manufacturing, and as the value of projects nearing completion increased through final design-change contracts.」
For the order backlog exceeding ¥40.0 billion, large-scale construction and product manufacturing progressed smoothly and conversion into revenue advanced. - FY2026-H1AdvancedAnnual report
「売上高につきましては、潤沢な手持ち工事が順調に進捗したことにより16,291百万円(前年同期比5.4%増)となりました。」
潤沢な手持ち工事が順調に進捗し、売上高は16,291百万円、前年同期比5.4%増となった。 - FY2025次期繰越工事高が449億円Annual report
「合計 52,075 25,217 77,293 32,306 44,986」
当事業年度末の次期繰越工事高は44,986百万円となり、前事業年度の52,075百万円から減少した。 - FY2025-H1AdvancedAnnual report
「売上高につきましては、潤沢な手持ち工事が順調に進捗したことにより15,456百万円(前年同期比30.1%増)となりました。」
潤沢な手持ち工事が順調に進捗し、売上高は15,456百万円、前年同期比30.1%増となった。 - FY2023次期繰越工事高が509億円Annual report
「合計 41,704 34,858 76,563 25,644 50,919」
当事業年度末の次期繰越工事高は50,919百万円となり、前事業年度の41,704百万円から増加した。 - FY2022First statedAnnual report
「2022年度は、過去最高レベルとなる400億円を超える潤沢な手持ち工事を抱えており、今後はこれらを効率的に消化して収益につなげていくことに努めます。」
2022年度の手持ち工事が過去最高レベルの400億円超に達しているとの事業状況を示し、これを効率的に消化して収益につなげる方針を記載した。