How it moved
ProgressHeldSoftenedWorseRestatedFY2016 – FY20262016: 120162017: 020172018: 020182019: 020192020: 020202021: 120212022: 120222023: 120232024: 020242025: 020252026: 12026
Same theme, other companies
Cost burden risk arising from serious construction accidents and contractual non-conformityA theme 33 companies write about · 34 as a headwind · 0 as a tailwind

The whole theme swung hardest in 2026: 4 of 14 companies on the "Worse" side.

19 other companies' latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 33 companies compared. The sentences above are computed from all 33.
Full recordFilings, disclosures and news, newest first
  1. FY2026RestatedAnnual report

    「If an unexpected serious accident occurs during construction or defects are found in a completed property, resulting in substantial repair costs or damages arising from litigation and other claims, this could affect future business performance.」

    It reiterates the risks of serious accidents, defects in completed properties, repair costs and damages.
  2. FY2023RestatedAnnual report

    「If an unexpected serious accident occurs during construction or defects are found in a completed property, resulting in substantial repair costs or damages arising from litigation and other claims, this could affect future business performance.」

    It reiterates the risks of serious accidents, defects in completed properties, repair costs and damages.
  3. FY2022RestatedAnnual report

    「If an unexpected serious accident occurs during construction or defects are found in a completed property, resulting in substantial repair costs or damages arising from litigation and other claims, this could affect future business performance.」

    It reiterates the risks of serious accidents, defects in completed properties, repair costs and damages.
  4. FY2021RestatedAnnual report

    「If an unexpected serious accident occurs during construction or defects are found in a completed property, resulting in substantial repair costs or damages arising from litigation and other claims, this could affect future business performance.」

    It reiterates the risks of serious accidents, defects in completed properties, and damages arising from repair costs and litigation.
  5. FY2016First statedAnnual report

    「If an unexpected serious accident occurs during construction or defects are found in a completed property, resulting in substantial repair costs or damages arising from litigation and other claims, this could affect future business performance.」

    It identifies accidents during construction, defects in completed properties, and associated repair costs, litigation and damages as risks.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
Nakano's next results are scheduled for 2026-11-13. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.