- FY2026Significant decrease in capital investmentAnnual report
「Total capital investment during the current consolidated fiscal year was ¥583 million. The main investment was the renovation of facilities at the company's head office and branch office buildings.」
Capital investment fell sharply from ¥8,316 million in the previous fiscal year to ¥583 million, with the main investment during the fiscal year being the renovation of facilities at the head office and branch office buildings. - FY2024AdvancedAnnual report
「Total capital investment during the current consolidated fiscal year was ¥8,316 million. The main investment was the acquisition of land and buildings for the company's rental business. Following the ZEB renovation, both buildings achieved energy savings of at least 50% in primary energy consumption versus the reference consumption level. Under the Building Energy-efficiency Labeling System (BELS), the research center building received ZEB certification and the research administration building received ZEB Ready certification. The renovation work was completed in May 2024.」
Capital investment increased from ¥7,323 million in the previous fiscal year to ¥8,316 million. The company completed the ZEB renovations at the Construction Technology Research Center, with both buildings achieving energy savings of at least 50% and receiving ZEB or ZEB Ready certification. - FY2023AdvancedAnnual report
「Total capital investment during the current consolidated fiscal year was ¥7,323 million. The main investment was the acquisition of land and buildings for the company's rental business.」
Capital investment increased from ¥2,794 million in the previous fiscal year to ¥7,323 million. In addition to acquiring rental business assets, the company began renovations to convert the research administration building and general testing building at the Construction Technology Research Center into net-zero energy buildings (ZEBs). - FY2020AdvancedAnnual report
「Total capital investment during the current consolidated fiscal year was ¥2,794 million. The main investments were the acquisition of land and buildings for the company's rental business and the rebuilding of the construction testing building at the Construction Technology Research Center.」
The company made ¥2,794 million in capital investments, acquiring land and buildings for the rental business and rebuilding the construction testing building at the Construction Technology Research Center. - FY2019AdvancedAnnual report
「Total capital investment during the current consolidated fiscal year was ¥3,624 million. The main investments were the acquisition of land and buildings for the company's rental business and the acquisition of the land and building for the head office of subsidiary Tekken Kōsan Co., Ltd.」
Capital investment increased from ¥1,992 million in the previous fiscal year to ¥3,624 million, with the acquisition of land and buildings for rental business assets and the subsidiary's head office building. In addition, the company announced a ¥671 million plan to construct a new construction testing building at the Construction Technology Research Center. - FY2018First statedAnnual report
「Total capital investment during the current consolidated fiscal year was ¥1,992 million. The main investments were the acquisition of land and buildings for the rental business and the extension of the training facilities at the Construction Technology Research Center.」
The company made ¥1,992 million in capital investments during the fiscal year, acquiring land and buildings for the rental business and extending the training facilities at the Construction Technology Research Center.