Construction of Development and Production Facilities for the Shallow Layers of the Hokkaido Yufutsu Oil and Gas Field
First written in FY2018-Q1. 3 of 7 entries say "Restated". Latest entry: FY2021-Q1.
No other company in this theme has enough history to compare yet.
- FY2021-Q1AchievedAnnual report
「The shallow development production facility, listed among the Company's plans for new construction and other work involving major facilities at the end of the previous consolidated fiscal year (location: Yufutsu County, Hokkaido; construction start: July 2017), was completed in June 2020.」
The shallow development production facility at the Yufutsu oil and gas field in Hokkaido was completed in June 2020, following the start of construction in July 2017, completing the facility construction plan. - FY2020RestatedAnnual report
「Hokkaido Office Yufutsu County, Hokkaido Shallow development production facility 2,800 1,026 Internal funds From July 2017 To June 2020 Crude oil production capacity Approximately 200 kilolitres per day」
The Yufutsu shallow development project continues under a plan for total investment of ¥2.8 billion, completion in June 2020, and production capacity of approximately 200 kilolitres per day. - FY2019SoftenedAnnual report
「Japan Petroleum Exploration Co.,Ltd. Hokkaido Office Yufutsu County, Hokkaido Shallow development production facility 2,700 993 Internal funds From July 2017 To June 2020 Crude oil production capacity Approximately 200 kilolitres per day」
The Yufutsu shallow development project is continuing, but the planned investment was changed from approximately ¥2.9 billion to ¥2.7 billion, and the planned completion date was changed from May 2020 to June 2020. Production capacity remains approximately 200 kilolitres per day. - FY2018SoftenedAnnual report
「Yufutsu shallow development production facility, Hokkaido 2,900 238 Internal funds From July 2017 To May 2020 Crude oil production capacity Approximately 200 kilolitres per day」
The Yufutsu shallow development project is continuing, but the planned investment was changed from approximately ¥3 billion to ¥2.9 billion, and the planned completion date was changed from October 2019 to May 2020. Production capacity remains approximately 200 kilolitres per day. - FY2018-Q3RestatedAnnual report
「During the nine-month period ended the third quarter, the Company confirmed that it would carry out work to refurbish and complete existing wells and construct shallow development and production facilities at the Yufutsu oil and gas field in Hokkaido (planned investment: approximately ¥3 billion; construction period: July 2017 to October 2019; production capacity: approximately 200 kilolitres of crude oil per day).」
The plan for refurbishing existing wells and constructing shallow development facilities at the Yufutsu oil and gas field in Hokkaido continues to be disclosed: approximately ¥3 billion, completion by October 2019, and production capacity of approximately 200 kilolitres per day. - FY2018-Q2RestatedAnnual report
「During the six-month period ended the second quarter, the Company confirmed that it would carry out work to refurbish and complete existing wells and construct shallow development and production facilities at the Yufutsu oil and gas field in Hokkaido (planned investment: approximately ¥3 billion; construction period: July 2017 to October 2019; production capacity: approximately 200 kilolitres of crude oil per day).」
The plan for refurbishing existing wells and constructing shallow development facilities at the Yufutsu oil and gas field in Hokkaido continues to be disclosed: approximately ¥3 billion, completion by October 2019, and production capacity of approximately 200 kilolitres per day. - FY2018-Q1First statedAnnual report
「The Company has confirmed that it will carry out work to refurbish and complete existing wells and construct shallow development and production facilities at the Yufutsu oil and gas field in Hokkaido (planned investment: approximately ¥3 billion; construction period: July 2017 to October 2019; production capacity: approximately 200 kilolitres of crude oil per day).」
The Company has disclosed for the first time a plan to refurbish existing wells and construct shallow development facilities, investing approximately ¥3 billion to establish crude oil production capacity of approximately 200 kilolitres per day by October 2019.