Komori
Japan Petroleum Exploration (1662) · InitiativeAdvanced

Utilization and Expansion of Domestic Gas Supply Infrastructure

First written in FY2016. 6 of 16 entries say "Advanced", first in FY2017. Latest entry: 2026-08-06.

16entries
11years
5from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseAdvancedFY2017 – FY2019-Q2RestatedFY2020 – FY2022AchievedFY2024 – FY20252016: 120162017: 120172018: 220182019: 220192020: 220202021: 020212022: 120222023: 020232024: 120242025: 120252026: 52026
Same theme, other companies
ガス供給インフラの安全・安定供給維持投資A theme 6 companies write about · 0 as a headwind · 7 as a tailwind

The whole theme swung hardest in 2017: 1 of 6 companies on the "Worse" side.

3 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2025AdvancedAnnual report

    「Soma Operations; Shinchi, Fukushima Prefecture; gas supply facilities; 1,200; 243; internal funds; from December 2024; to December 2026; LNG tanker loading facilities; 7 lanes」

    For domestic gas supply infrastructure, plans have taken shape for a 7-lane LNG tanker loading facility at the Soma Operations, with an investment of ¥1.2 billion and completion scheduled for December 2026.
  2. FY2024AchievedAnnual report

    「The calorific value adjustment facility at the Nagaoka Office of Japan Petroleum Exploration Co.,Ltd., which has been described since the Annual Securities Report for the fiscal year ended March 2021, was completed in June 2024 after acceptance of some of the construction work was completed.」

    The heat-volume adjustment facilities in Niigata City reached completion in June 2024, with only part of the construction remaining at the outset. Gas transmission volumes and post-completion capacity remain unchanged.
  3. FY2022Partial operation of the calorific value adjustment facility; completion date undeterminedAnnual report

    「Completion had been scheduled for March 2022 as of the end of the previous consolidated fiscal year, but some construction remains and the completion date was undetermined as of the end of the current consolidated fiscal year. Most of the facility had been accepted, however, and began operating in November 2021.」

    Most of the calorific value adjustment facility in Niigata City began operating in November 2021, while some construction remained and the completion date became undetermined.
  4. FY2020RestatedAnnual report

    「Our group secures the funds required in line with funding needs by effectively utilizing internal funds and bank borrowings. Working capital is financed mainly with internal funds, and the introduction of a CMS (cash management system) is intended to improve funding efficiency and secure liquidity.」

    The policy of continuing capital investment, including in domestic gas supply infrastructure, while using internal funds and the CMS to secure funding efficiency and liquidity has been reaffirmed.
  5. FY2020-Q3AdvancedAnnual report

    「During the first 3 quarters, it was decided to construct a natural gas transportation pipeline approximately 4 km long in Shibata, Miyagi Prefecture, with planned investment of approximately ¥1 billion and a construction period from June 2019 to January 2021. As the project extends an existing line, no increase in capacity is expected after completion. It was also decided to construct a calorific value adjustment facility within an existing gas transmission facility in Niigata City, Niigata Prefecture, with planned investment of approximately ¥3 billion and a construction period from October 2019 to March 2022. As gas transmission volumes will not change, no increase in capacity is expected after completion.」

    In addition to construction of the approximately 4 km natural gas transportation pipeline in Shibata, construction of a calorific value adjustment facility within an existing gas transmission facility in Niigata City was confirmed. The latter involves planned investment of approximately ¥3 billion, with construction scheduled from October 2019 to March 2022. No increase in supply capacity is expected after completion of either project.
  6. FY2020-Q2AdvancedAnnual report

    「During the first 2 quarters, it was decided to construct a natural gas transportation pipeline approximately 4 km long in Shibata, Miyagi Prefecture, with planned investment of approximately ¥1 billion and a construction period from June 2019 to January 2021. As the project extends an existing line, no increase in capacity is expected after completion.」

    For domestic gas supply infrastructure, construction of an approximately 4 km natural gas transportation pipeline in Shibata, Miyagi Prefecture, was confirmed. Planned investment is approximately ¥1 billion, with construction scheduled from June 2019 to January 2021. No increase in capacity is expected after completion because the project extends an existing line.
  7. FY2019-Q3RestatedAnnual report

    「At the end of the previous consolidated fiscal year, the plan for the construction of major facilities included gas supply facilities and a natural gas pipeline in Niigata City, Niigata Prefecture, with construction starting in July 2015. The project was completed in September 2018.」

    The filing reiterates that the gas supply facilities and natural gas pipeline in Niigata City were completed in September 2018. It shows no new progress.
  8. FY2019-Q2AchievedAnnual report

    「At the end of the previous consolidated fiscal year, the plan for the construction of major facilities included gas supply facilities and a natural gas pipeline in Niigata City, Niigata Prefecture, with construction starting in July 2015. The project was completed in September 2018.」

    The construction plan for the gas supply facilities and natural gas pipeline in Niigata City reached completion in September 2018.
  9. FY2018-Q3AdvancedAnnual report

    「At the end of the previous consolidated fiscal year, the plan for the construction of major facilities included the Soma LNG terminal and natural gas pipeline, located from Shinchi, Fukushima Prefecture, to Iwanuma, Miyagi Prefecture, with construction starting in November 2013. The project was completed in November 2017.」

    The construction plan for the Soma LNG terminal and natural gas pipeline advanced from the planning and construction stage to completion in November 2017.
  10. FY2017AdvancedAnnual report

    「Major items include production facility construction, expansion and development costs for the Hangingstone field in Canada, and construction of the Soma LNG terminal and pipelines.」

    Construction of the Soma LNG terminal and pipelines is disclosed as ongoing capital investment.
  11. FY2016First statedAnnual report

    「We will further utilize and expand domestic gas supply infrastructure.」

    Gas supply infrastructure is identified as a specific business foundation supporting stable supply to domestic customers.
Moved together

"Financial Risks from Large-Scale Investments in Overseas Projects and Debt Guarantees" moved the same way as this thread, in the same document, in 6 of its 16 moves.

633333★123456
  1. ★This thread
  2. 1Financial Risks from Large-Scale Investments in Overseas Projects and Debt Guarantees6×
  3. 2Expanding Production and Reserves Through an Overseas Shift3×
  4. 3Promotion of Methane Hydrates, CCS and Geothermal Power Generation3×
  5. 4Creation and Expansion of CO2 Emissions Reduction and Offset Technologies and Renewable Energy Businesses3×
  6. 5Transition to an integrated energy company centered on oil and natural gas E&P3×
  7. 6Development and production of the Gharaf oil field in Iraq and investment recovery3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Japan Petroleum Exploration yet. It last moved in the Investor presentation of 2026-08-06: "Advanced".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Utilization and Expansion of Domestic Gas Supply Infrastructure | Japan Petroleum Exploration Co.,Ltd. (1662) | Komori