Komori
Other Disclosures1436GreenEnergy & Company Inc.Construction and Materials

Notice Regarding the Receipt of an Order for Construction of a Grid-Scale Battery Storage System

グリーンエナジー・プラス, a 100%-owned subsidiary, received an order from a company headquartered in Hyogo Prefecture and entered into a contract for construction of a grid-scale battery storage system in Mine, Yamaguchi Prefecture. The facility has a rated output of 1,999 kW and a nominal capacity of 8,128 kWh.

Worth reading
63In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
1999
kW (rated output)
Wording
Conditional
How definitive the wording is.

Announced details

Grid-scale battery storage system / grid-scale battery storage facility construction
Applicable field (uses covered by this announcement)

Balancing fluctuations in renewable power generation, electricity supply-demand balancing, power grid stabilization, and decarbonization

Contract DateBefore 23 October 2026; specific date Not disclosed
Relationship between the counterparty and the company
GreenEnergy & Company Inc.1436
Relationship with the Company

Business relationship under the order contract. The contracting entity is 株式会社グリーンエナジー・プラス, a 100%-owned subsidiary of the Company.

CounterpartyCompany headquartered in Hyogo Prefecture (name not disclosed)

Company headquartered in Hyogo Prefecture. Other details: Not disclosed.

Location (as indicated in this announcement)

Mine, Yamaguchi Prefecture

Rated output: 1,999 kW; nominal capacity: 8,128 kWh
Impact on Business Performance

The impact of this matter alone on results for the current fiscal year is expected to be minor.

The company does not address Contract Value / Offering price.

Announced details
ItemDetails
Names of Products / Services CoveredGrid-scale battery storage system / grid-scale battery storage facility construction
CounterpartyCompany headquartered in Hyogo Prefecture (name not disclosed)
Counterparty overviewCompany headquartered in Hyogo Prefecture. Other details: Not disclosed.
Relationship with the CompanyBusiness relationship under the order contract. The contracting entity is 株式会社グリーンエナジー・プラス, a 100%-owned subsidiary of the Company.
Contract DateBefore 23 October 2026; specific date Not disclosed
Applicable areaBalancing fluctuations in renewable power generation, electricity supply-demand balancing, power grid stabilization, and decarbonization
LocationMine, Yamaguchi Prefecture
Location scaleRated output: 1,999 kW; nominal capacity: 8,128 kWh
Impact on Business PerformanceThe impact of this matter alone on results for the current fiscal year is expected to be minor.
Items this document does not state (9)
Contract ValueOffering priceLaunch dateAward/certification nameAwarding / certifying bodyRegistration number and expiry dateQuantitative EffectsUsage historySource

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The order environment for grid-scale battery storage facilities has remained firm against a backdrop of progress toward decarbonization and the expansion of the balancing market.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Regarding the Receipt of an Order for Construction of a Grid-Scale Battery Storage System | GreenEnergy & Company Inc. (1436) timely disclosure | Komori