Other Disclosures1436GreenEnergy & Company Inc.Construction and Materials

(Update on Previously Disclosed Matter) Notice of Completion and Handover of a Grid-Scale Battery Storage Facility in Itano District, Tokushima Prefecture, as Part of the Tokushima Taisho Bank Group's Grid-Scale Battery Storage Business (とくぎんトモニリンクアップ株式会社)

The Company's wholly owned subsidiary GEP completed and handed over a grid-scale battery storage facility in Itano District, Tokushima Prefecture, on 10 July 2026. The facility was provided to とくぎんトモニリンクアップ株式会社 and uses a battery storage system manufactured by 株式会社パワーエックス.

Worth reading
71In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
1990
Rated output (kW)
Wording
Definitive
How definitive the wording is.

Announced details

Grid-scale battery storage facility / grid-scale battery storage equipment; battery storage system manufactured by 株式会社パワーエックス
Applicable field (uses covered by this announcement)

Adjusting fluctuations in renewable energy generation, balancing electricity supply and demand, and stabilizing the power grid

Launch date10 July 2026 (completed and handed over)
Contract DateThe execution of the agreement was announced on 20 February 2026 (the actual agreement date is Not disclosed).
Relationship between the counterparty and the company
GreenEnergy & Company Inc.1436
Relationship with the Company

The Company has no capital, personnel, business or related-party relationship with とくぎんトモニリンクアップ株式会社. The Company's wholly owned subsidiary GEP provided the battery storage facility.

Counterpartyとくぎんトモニリンクアップ株式会社

Based in Tokushima City, Tokushima Prefecture, the company was established on 4 February 2025 and has capital of ¥100 million. Its Representative Director and President is Amano Yoshihiko (天野嘉彦). It is a wholly owned subsidiary of Tokushima Taisho Bank and operates renewable energy generation and electricity sales, energy storage, and GX consulting businesses, among others.

Location (as indicated in this announcement)

Itano District, Tokushima Prefecture

Rated output: 1,990 kW; rated capacity: 8,226 kWh

In this announcement the company addresses none of Contract Value / Offering price / Impact on Business Performance.

Announced details
ItemDetails
Names of Products / Services CoveredGrid-scale battery storage facility / grid-scale battery storage equipment; battery storage system manufactured by 株式会社パワーエックス
Counterpartyとくぎんトモニリンクアップ株式会社
Counterparty overviewBased in Tokushima City, Tokushima Prefecture, the company was established on 4 February 2025 and has capital of ¥100 million. Its Representative Director and President is Amano Yoshihiko (天野嘉彦). It is a wholly owned subsidiary of Tokushima Taisho Bank and operates renewable energy generation and electricity sales, energy storage, and GX consulting businesses, among others.
Relationship with the CompanyThe Company has no capital, personnel, business or related-party relationship with とくぎんトモニリンクアップ株式会社. The Company's wholly owned subsidiary GEP provided the battery storage facility.
Contract DateThe execution of the agreement was announced on 20 February 2026 (the actual agreement date is Not disclosed).
Launch date10 July 2026 (completed and handed over)
Applicable areaAdjusting fluctuations in renewable energy generation, balancing electricity supply and demand, and stabilizing the power grid
LocationItano District, Tokushima Prefecture
Location scaleRated output: 1,990 kW; rated capacity: 8,226 kWh
Items this document does not state (9)
Contract ValueOffering priceAward/certification nameAwarding / certifying bodyRegistration number and expiry dateQuantitative EffectsUsage historyImpact on Business PerformanceSource

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The facility is intended to help stabilize the power grid as the adoption of renewable energy expands.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
(Update on Previously Disclosed Matter) Notice of Completion and Handover of a Grid-Scale Battery Storage Facility in Itano District, Tokushima Prefecture, as Part of the Tokushima Taisho Bank Group's Grid-Scale Battery Storage Business (とくぎんトモニリンクアップ株式会社) | GreenEnergy & Company Inc. (1436) timely disclosure | Komori