Items stated in the management plan
Annual updateEach line is the climb from the baseline the document states to the target it sets. The slope is scaled against the largest climb in this document. For metrics expressed as percentages, differences are shown in percentage points (pt).The increase shown by the dotted line is calculated from the two reported figures because the company did not provide the amount of growth.
| Item | Details |
|---|---|
| Plan name | Medium-Term Management Plan Green300 & Long-Term Vision Sustainable Growth 2035 |
| Plan period | Fiscal years ending April 2025–April 2029 (Green300); 2030–2035 (Sustainable Growth 2035) |
| Progress against the plan | Annual update |
| Sales Target | Actual for the fiscal year ending April 2026: ¥18,358 million → Fiscal year ending April 2029: ¥30,000 million |
| Operating profit target | Actual for the fiscal year ending April 2026: ¥1,191 million → Fiscal year ending April 2029: ¥2,000 million |
| ROE target | Actual for the fiscal year ending April 2026: 9.1% (9.4% on another page) → Approximately 12% (Green300). The Company aims to achieve at least 20% ahead of schedule in the fiscal year ending April 2027. |
| Payout ratio / DOE policy | Under Green300, the Company targets a payout ratio of approximately 15%. The applicable period is the fiscal years ending April 2025 through April 2029. DOE: not disclosed. |
| Non-financial targets | Indicator name Number of green energy facilities developed / Target value 1,500 cases / Timing Fiscal year ending April 2029, Indicator name Development and construction of grid-scale battery storage facilities / Target value Cumulative total of 1 GWh (1,000 MWh) / Timing By April 2029 |
| Plan assumptions | The grid-scale battery storage market is expected to expand to ¥424 billion in fiscal 2030., The government target assumes the introduction of up to 23.8 GWh of grid-scale battery storage by 2030., The market-size forecast was prepared based on information available as of 20 January 2026. |
| Key initiatives | Medium-Term Management Plan Green300, Long-Term Vision Sustainable Growth 2035, Pursuing capital efficiency and development scale simultaneously, Further focus on the grid-scale battery storage business, Concentration on the grid-scale battery storage business, Improving profit and capital efficiency, Steadily expanding development scale, Ongoing strategy: maximizing the number of developments, Ongoing strategy: strategic progress in solar power generation facilities, Priority strategy 1: expanding the number of store units, Priority strategy 2: expanding the business area, Stock business strategy (O&M) |
| Results under the previous plan | Initial plan for the fiscal year ending April 2026: ¥19.5 billion → Actual for the fiscal year ending April 2026: ¥18.4 billion |
| Size of the Target Market | The grid-scale battery storage market is estimated at ¥120 billion in fiscal 2026, ¥200 billion in fiscal 2027, ¥270 billion in fiscal 2028, ¥350 billion in fiscal 2029, and ¥424 billion in fiscal 2030. These figures were estimated and interpreted comprehensively and independently by the Company based on publicly available materials from the government and private-sector sources. |
| Risks identified | Natural disasters and other events, Changes in laws and regulations, Leakage of personal information and other data, Delays in connection to the power grid, Risk of outstanding customer deposits and advance payments, Customers' funding risk, Accountability arising from customers' insufficient understanding of the power generation business, Risk of delays in aggregation and O&M, Risk associated with forming SPC funds, Rising interest rates, Dilution through equity financing, including CBs |
| Publication date | 31 July 2026 |
Items this document does not state (11)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The medium-term management plan, Green300, is progressing at a pace exceeding the initial plan, and performance is expected to exceed the plan in the fiscal year ending April 2027 as well. In addition, the Company aims to capture the expansion of the grid-scale battery storage market while simultaneously increasing its development scale and capital efficiency.