Risk of Delays in Delivery of Materials Including Power Conditioners
First written in FY2022-Q1. 2 of 4 entries say "Worsened", first in FY2022-Q2. Latest entry: 2026-10-15.
4entries
5years
1from disclosures
How it moved
Same theme, other companies
Project Progress Risks from Shortages of Materials and Equipment and Delivery DelaysA theme 41 companies write about · 43 as a headwind · 0 as a tailwind
West Holdings moved to the "Worse" side of this theme in 2022, the same year as the typical company in this theme.
The whole theme swung hardest in 2026: 9 of 23 companies on the "Worse" side.
9 other companies' latest entry also says "Restated".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 41 companies compared. The sentences above are computed from all 41.Full recordFilings, disclosures and news, newest first
- 2026-10-15RestatedEarnings
「一部の非FIT太陽光発電所において系統連系の遅延が生じており、電力調達量の拡大時期に影響が生じていることから、早期の系統連系に向け、関係先との協議を継続しております。」
非FIT太陽光発電所の系統連系遅延と、電力調達量の拡大時期への影響を記載した。 - FY2023-Q1WorsenedAnnual report
「いずれも需要が大きく高まっている一方で、地政学リスクの増加、インフレ加速懸念、為替相場動向等、供給面でのリスクを踏まえつつ、施工能力を引き上げていく必要性が高まっており、今後も最優先課題として取り組んでまいります。」
資材納期遅延懸念に加え、地政学リスク、インフレ加速懸念及び為替相場動向など、供給面のリスク要因を広げて記載した。 - FY2022-Q2WorsenedAnnual report
「いずれも需要が大きく高まっている一方で、地政学的リスクが高まる中、物流の混乱により資材納期遅延が発生する懸念は残っており、工事計画の着実な遂行に今後も細心の注意を払ってまいります。」
従来のパワコン中心の納入遅延懸念が、地政学的リスクと物流混乱による資材納期遅延リスクへ広がった。 - FY2022-Q1First statedAnnual report
「いずれも需要が大きく高まっている一方で、パワコンを中心に資材の納入が遅れ気味となりつつあります。工事計画の着実な遂行に今後も細心の注意を払ってまいります。」
自家消費型、ウエストFIT、PPA等の需要が高まる一方、パワコンを中心とする資材納入の遅れが生じつつあると記載した。工期遅延そのものは発生していないが、工事計画への影響に注意するとしている。