West Holdings (1407) · RiskRestatedLatest Earnings (2026-07-15): "Materialised"
Delays in Grid Connection Responses for Non-FIT Power Plants
First written in FY2023-Q1. 1 of 4 entries say "Mitigated", first in FY2023-Q2. Latest entry: 2026-07-15.
4entries
4years
1from disclosures
How it moved
Same theme, other companies
Revisions to Sales Plans Due to Competition for Solar Power Projects and Grid Interconnection DelaysA theme 7 companies write about · 8 as a headwind · 0 as a tailwind
West Holdings moved to the "Worse" side of this theme in 2026.
1 other company's latest entry also says "Materialised".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- 2026-07-15MaterialisedEarnings
「On the other hand, some projects are experiencing delays in grid interconnection. Because revenue cannot be generated until operations commence, we are continuing negotiations so that interconnection can be achieved at an early stage.」
The company disclosed that some projects were experiencing grid interconnection delays, affecting the recognition of revenue. - FY2023RestatedAnnual report
「前年度まで大きなボトルネックとなっていた電力会社との接続連系回答の遅延は概ね改善したものの」
非FIT発電所開発における電力会社の接続連系回答遅延は概ね改善したとの認識を継続しているが、許認可取得や届出義務による工程増加は残っている。 - FY2023-Q2MitigatedAnnual report
「前年度まで大きなボトルネックとなっていた電力会社との接続連系回答の遅延は概ね改善しているものの」
前年度まで大きなボトルネックだった電力会社からの接続連系回答の遅延は、概ね改善したと記載した。 - FY2023-Q1First statedAnnual report
「連系回答の遅延に苦労して参りましたが、ようやく事態が改善しつつあり、徐々に工事が開始されております。」
非FIT発電所開発で電力会社からの連系回答遅延が実際に発生していたが、改善しつつあり工事開始に至っている。