Taiwanese AI infrastructure company Nocera will provide funding to Canadian company BitRock and acquire a 44% stake, securing financing for a planned 10 MW self-powered AI data center in Alberta and board representation. Following the signing of an LOI, the companies plan to secure funding for the first phase of construction.
Nocera will acquire $22 million worth of shares in BitRock, taking a 44% stake. This will give Nocera the right to nominate directors, receive regular financial reports and participate in decision-making on material matters.
The funds will be used to build BitRock's first 10 MW data center, planned for Alberta, Canada, on a site of approximately 37 acres. Construction will use a modular approach with four 2.5 MW prefabricated modules, with the site ultimately expected to expand by 10 MW at a time in response to demand, reaching a maximum scale of 200 MW.
BitRock aims to operate a self-powered data center using natural-gas generation facilities on the site. The campus is planned for colocation operations with an N+1 redundant configuration and a target PUE of 1.225. The parties intend to execute a definitive investment agreement under the LOI as soon as possible, and the required permits for power generation and electricity supply have already been obtained, according to the company.
Nocera's director for Asia, Andrew Teng, identified power as the scarcest asset in AI infrastructure and said the company plans to enter the North American market through phased expansion of a business built around self-generation.
The transaction is one of several partnerships Nocera has pursued since the start of 2026. Additional investments in digital innovation companies and energy-related businesses have also been reported.