Firm orders for power-generation equipment for AI data centers are increasing, driving broader investment in component supply and long-term maintenance. Japanese companies' order backlogs and investment plans are expanding, making the strengthening of supply chains a key focus.
The most notable development over the past 14 days was Baker Hughes' disclosure of firm orders for 43 gas turbines, with a combined capacity of approximately 1.1 GW, for AI computing infrastructure. The company will supply power-generation equipment combining Frame 5 and NovaLT16 turbines, along with cooling equipment, indicating an integrated supply model.
GE Vernova's firm gas turbine order backlog and manufacturing capacity reservations grew to a combined 122 GW. Of the new contracts, 3 GW represents firm orders and 8 GW manufacturing capacity reservations, while 13 GW of existing reservations were converted to firm orders. The company also announced equipment that has already been shipped.
Among Japanese companies, Mitsubishi Heavy Industries reported a contract backlog of 83 large gas turbines totaling approximately 37 GW, and outlined growth plans including approximately ¥500 billion of investment in GTCC hot-section components and approximately ¥100 billion in power-generation engine production capacity. NTT DATA signed a 900 MW fuel cell equipment contract with Bloom Energy, with shipments scheduled to begin in 2027.
For domestic projects, including Nippon Paper Industries' Kushiro Mill, contracts have been reported for data center businesses using existing infrastructure, broadening the range of transaction models serving data center demand. Alongside developments in North America and Europe, demand for Japanese companies' component supply and maintenance services is expected to increase.