「As stated in the “Notice Regarding Receipt of the Investigation Report from the Special Investigation Committee” dated 29 August 2022, it was discovered that an employee of the company, who was subject to disciplinary dismissal on 28 September 2022, had made improper expenditures and had received kickbacks from the company's business partners.」
It was disclosed that the employee involved in the case involving improper expenditures and kickbacks related to new store construction was subject to disciplinary dismissal dated 28 September 2022. - FY2023-Q2MaterialisedAnnual report
「As disclosed in the timely disclosure dated 29 August 2022, “Notice Regarding Receipt of the Investigation Report from the Special Investigation Committee,” concerning the case involving improper expenditures and other matters related to construction work for our new stores, we take the situation seriously and are formulating specific measures to prevent recurrence in line with the findings and recommendations of the special investigation committee, while working thoroughly to prevent recurrence. During the cumulative second quarter of the current fiscal year, ¥170 million in investigation costs related to the case incurred by the special investigation committee was recognized as an extraordinary loss.」
In connection with the case involving improper expenditures related to new store construction, ¥170 million in investigation costs incurred by the special investigation committee was recognized as an extraordinary loss. - FY2023-Q1MaterialisedAnnual report
「It was discovered that improper expenditures had been made in connection with construction work for our new stores. To conduct a fair and appropriate investigation, we established a special investigation committee comprising external experts and recognized the committee's investigation costs as special investigation expenses.」
In connection with improper expenditures related to new store construction, ¥75.308 million in special investigation expenses incurred by the special investigation committee was recognized. - FY2022MaterialisedAnnual report
「As a result, it was found that, in construction work for several of our stores, our employees had instructed contractors to place fictitious orders and reallocate construction costs, resulting in improper expenditures, and had received kickbacks from our business partners through payments of fictitious brokerage and planning fees.」
Fictitious orders, cost reallocations and receipt of kickbacks were identified in construction work for several stores, and a ¥29.860 million loss related to improper conduct was recognized.