Senshu Electric (9824) · InitiativeAchieved
Establishment of the Nagoya FA Center
First written in FY2023-Q3. 1 of 3 entries say "Advanced", first in FY2024. Latest entry: FY2025-H1.
3entries
3years
0from disclosures
How it moved
Same theme, other companies
Establishment of the Nagoya FA CenterA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2025-H1AchievedAnnual report
「The company also opened its Nagoya FA Center in Inazawa, Aichi Prefecture, in April 2025 to strengthen its control panel manufacturing and agribusiness operations.」
The company reported that the Nagoya FA Center, which had been planned since Q3 2023, opened in April 2025 as scheduled. - FY2024AdvancedAnnual report
「The company changed the total planned investment for the construction of the Nagoya FA Center from ¥2,356 million to ¥2,351 million.」
For the Nagoya FA Center, the total planned investment is ¥2,351 million and the amount already paid is ¥1,615 million, indicating progress in the capital investment. The scheduled completion date of April 2025 remains unchanged. - FY2023-Q3First statedAnnual report
「Company Nagoya FA Center Inazawa, Aichi Prefecture Wires and cables Wire processing and control panel manufacturing 2,207 46 Internal funds January 2024 April 2025 Land 6,835.00㎡ Building 7,749.87㎡」
The company reported for the first time a plan to construct the Nagoya FA Center, a facility for wire processing and control panel manufacturing, for a total planned investment of ¥2,207 million. Construction began in January 2024 and was scheduled for completion in April 2025; ¥46 million had already been paid.