- 2026-10-13AdvancedEarnings
「In the construction division, the completion of projects secured substantially above the same period of the previous year, mainly large private-sector construction projects, resulted in sales exceeding the same period of the previous year.」
The trend of expanding orders, mainly for large private-sector construction projects across Hokkaido, was reflected in the completion of projects exceeding the same period of the previous year and higher sales. - FY2026AdvancedAnnual report
「There was a significant fluctuation in the value of orders received during the current consolidated fiscal year. This was due to an increase in new orders in the construction business.」
Construction orders totaled ¥5,974 million, or 530.6% of the year-earlier period, while the order backlog was ¥3,658 million, or 577.6% of the year-earlier period, reflecting a substantial increase in new orders. - FY2026-H1AdvancedAnnual report
「In the building division, the company secured orders above the previous year, mainly for private-sector construction across a broad area of Hokkaido. However, revenue and operating profit for the current interim consolidated accounting period both fell below the year-earlier period due to the timing of project completions.」
Although the company made progress in securing orders above the previous year, mainly for private-sector construction across a broad area of Hokkaido, revenue and operating profit in the current interim period fell below the year-earlier period due to the timing of project completions. - FY2025AdvancedAnnual report
「In the building division, new orders progressed across a broad area of Hokkaido, and the company secured a stable volume of orders, primarily for private-sector construction.」
Regarding efforts to expand the sales area across Hokkaido, the company describes progress in securing new orders and a stable volume of private-sector construction orders. - FY2024First statedAnnual report
「Although private-sector construction projects continued to be put on hold as companies waited to see how the surge in material prices would affect capital investment, orders remained firm despite the challenging environment, partly due to the expansion of the sales area.」
In the construction business amid surging material prices, the company has for the first time explicitly identified expansion of the sales area as a specific means of securing orders. Construction orders in the current fiscal year totaled ¥3,426 million, or 166.1% of the year-earlier period, while the order backlog was ¥1,877 million, or 177.0% of the year-earlier period.