Damage to Classroom Buildings and Equipment Caused by the 2016 Kumamoto Earthquake

First written in FY2017-Q1. 2 of 6 entries say "Restated". Latest entry: FY2018.

6entries
3years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseMaterialisedFY2017-Q1OtherFY2017-Q2 – FY20182016: 220162017: 220172018: 22018
Same theme, other companies
Direct Disaster Losses from the Kumamoto EarthquakeA theme 31 companies write about · 31 as a headwind · 0 as a tailwind

The whole theme swung hardest in 2026: 4 of 6 companies on the "Worse" side.

5 other companies' latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 31 companies compared. The sentences above are computed from all 31.
Full recordFilings, disclosures and news, newest first
  1. FY2018RestatedAnnual report

    「Fiscal year ended 28 February 2018 (from 1 March 2017 to 28 February 2018) There are no applicable matters.」

    It states that there were no applicable disaster losses related to the Kumamoto Earthquake for the fiscal year, distinguishing them from the ¥69.680 million loss in the previous fiscal year.
  2. FY2018-Q3No loss in the current periodAnnual report

    「Nine months ended 30 November 2017 (from 1 March 2017 to 30 November 2017) There are no applicable matters.」

    While disaster losses related to the Kumamoto Earthquake were stated as ¥70.080 million for the comparable nine-month period of the previous fiscal year, no applicable loss was recorded for the nine months ended 30 November 2017.
  3. FY2017Update to the amount of loss recordedAnnual report

    「This represents ¥69.680 million in costs of restoring classroom buildings and equipment in Kumamoto Prefecture damaged by the 2016 Kumamoto Earthquake, which occurred on 14 and 16 April 2016.」

    The damage to classroom buildings and equipment caused by the Kumamoto Earthquake is reiterated. Restoration costs and other expenses are stated as ¥69.680 million in the annual results, compared with ¥70.080 million in the quarterly report.
  4. FY2017-Q3RestatedAnnual report

    「This represents ¥70.080 million in costs of restoring classroom buildings and equipment in Kumamoto Prefecture damaged by the 2016 Kumamoto Earthquake, which occurred on 14 and 16 April 2016.」

    The damage to classroom buildings and equipment caused by the Kumamoto Earthquake and the recording of ¥70.080 million in restoration costs and other expenses are reiterated.
  5. FY2017-Q2Update to the loss amountAnnual report

    「This represents ¥70.080 million in costs of restoring classroom buildings and equipment in Kumamoto Prefecture damaged by the 2016 Kumamoto Earthquake, which occurred on 14 and 16 April 2016.」

    The damage caused by the Kumamoto Earthquake continues to be described as a risk that actually occurred, and the recorded amount for restoration costs and other expenses was updated from ¥69 million previously to ¥70.080 million.
  6. FY2017-Q1MaterialisedAnnual report

    「We estimated and recorded ¥69 million as a special loss for costs of restoring classroom buildings and equipment in Kumamoto Prefecture damaged by the 2016 Kumamoto Earthquake that occurred in April.」

    Damage to classroom buildings and equipment caused by the Kumamoto Earthquake occurred, and ¥69 million was recorded as an expense for provision for disaster-related losses.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
No upcoming earnings preview for Subaru yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Damage to Classroom Buildings and Equipment Caused by the 2016 Kumamoto Earthquake | SUBARU CO.,LTD. (9778) | Komori