Project Progress and Lower Margins on Large Projects in the Heavy Temporary Construction Business
First written in FY2017-Q3. 16 of 36 entries say "Advanced", first in FY2018-Q2. Latest entry: 2026-07-31.
No other company in this theme has enough history to compare yet.
- 2026-07-31Cited as achievedEarnings
「With a contribution from the results of 竹本基礎工事㈱, net sales were ¥1,534 million, up ¥387 million, or 33.7%, and segment profit was ¥258 million, an increase of ¥234 million.」
The Company cited 竹本基礎工事's earnings contribution to the heavy temporary construction and related business, together with the resulting sales and segment profit. - FY2026AdvancedAnnual report
「Results at 竹本基礎工事, which became a consolidated subsidiary mainly at the end of the previous fiscal year, contributed to revenue of ¥5.372 billion (up ¥1.341 billion year on year, or 33.3%) and segment profit of ¥289 million (up ¥173 million, or 150.6%).」
In the heavy temporary construction and related business, revenue increased 33.3% and segment profit increased 150.6%, driven by the contribution from 竹本基礎工事. - FY2026-H1AdvancedAnnual report
「As the profitability of construction projects already won improved and the results of 竹本基礎工事㈱, acquired in February 2025, were reflected, revenue was ¥2.477 billion (up ¥366 million year on year, or 17.3%), and segment profit was ¥91 million (up ¥16 million, or 22.1%).」
In the heavy temporary construction and related business, revenue and segment profit both increased year on year due to improved profitability on projects already won and the inclusion of post-acquisition results from 竹本基礎工事. - FY2025AdvancedAnnual report
「Although Group-wide order-intake activities drove revenue up to ¥4.030 billion (up ¥360 million year on year, or 9.8%), segment profit was limited to ¥115 million (down ¥75 million, or 39.5%) as construction profitability deteriorated.」
Revenue increased as order-intake activities were strengthened, while profit declined due to deteriorating construction profitability. - FY2025-H1AdvancedAnnual report
「② Heavy temporary construction business: As the profitability of construction projects already won improved, revenue was ¥2.111 billion (up ¥580 million year on year, or 37.9%), and segment profit was ¥75 million (up ¥39 million, or 110.6%).」
The heavy temporary construction business generated higher revenue as the profitability of construction projects already won improved, while segment profit increased 110.6% year on year. - FY2024AdvancedAnnual report
「After establishing an internal structure to strengthen order intake and pursuing sales activities across the Group, revenue increased year on year to ¥3.669 billion (up ¥851 million, or 30.2%). Segment profit was ¥191 million (up ¥101 million, or 114.3%), reflecting a significant improvement in the profitability of construction work at subsidiaries.」
The heavy temporary construction business generated higher revenue through the development of an internal structure to strengthen order intake and Group-wide sales activities, while improved profitability at subsidiaries led to a substantial increase in profit. - FY2024-Q3AdvancedAnnual report
「② Heavy temporary construction business: As construction progressed, revenue was ¥2.618 billion (up ¥574 million year on year, or 28.1%), and segment profit was ¥150 million (up ¥71 million, or 90.4%), mainly due to improved earnings at subsidiaries.」
The heavy temporary construction business generated higher revenue as construction progressed, while segment profit increased 90.4% against the backdrop of improved earnings at subsidiaries. - FY2024-Q2Higher revenue, but lower profit due to rising costsAnnual report
「As work on projects already won progressed, revenue was ¥1.530 billion (up ¥208 million year on year, or 15.8%), but segment profit was ¥35 million (down ¥4 million, or 11.4%) as some projects were affected by rising costs.」
The heavy temporary construction business generated higher revenue as projects already won progressed, while segment profit declined year on year due to rising costs on some projects. - FY2024-Q1Higher profit from delayed construction progress and cost reductionsAnnual report
「Although revenue was ¥685 million, down ¥26 million, or 3.7%, due to delays in the progress of some construction projects, segment profit was ¥29 million, up ¥3 million, or 14.9%, as a result of lower construction costs.」
In the heavy temporary construction business, revenue declined due to delays in the progress of some projects, while segment profit increased as a result of reductions in construction costs. - FY2023Higher revenue, but lower profit due to higher costs at construction companiesAnnual report
「As work on projects already won progressed, revenue increased year on year to ¥2.818 billion (up ¥68 million, or 2.5%), but segment profit was ¥89 million (down ¥43 million, or 32.8%), partly due to higher costs at a construction company whose full-scale operations were delayed.」
Revenue increased as projects already won progressed, while segment profit declined due to higher costs at a construction company whose full-scale operations were delayed. - FY2023-Q3AdvancedAnnual report
「As work on projects already won progressed, revenue was ¥2.043 billion (up ¥3 million year on year, or 0.2%), and segment profit was ¥79 million (up ¥6 million, or 8.6%).」
Revenue and segment profit in the heavy temporary construction business both increased year on year as projects already won progressed. Profit growth has replaced the decline caused by deteriorating profitability on some projects in the previous quarter. - FY2023-Q2Higher revenue from project progress, but lower profit due to deteriorating profitability on some projectsAnnual report
「As work on projects already won progressed, revenue was ¥1.321 billion (up ¥112 million year on year, or 9.3%), but segment profit was ¥40 million (down ¥15 million, or 28.3%) due in part to deteriorating profitability on some projects.」
The heavy temporary construction business generated higher revenue as projects already won progressed, while segment profit fell 28.3% year on year due to deteriorating profitability on some projects. - FY2023-Q1AdvancedAnnual report
「As construction progressed, revenue was ¥711 million (up ¥208 million year on year, or 41.3%), and segment profit was ¥25 million (up ¥0 million, or 2.7%).」
In the heavy temporary construction business, construction progressed, driving a 41.3% year-on-year increase in revenue and a 2.7% increase in segment profit. - FY2022AdvancedAnnual report
「As work on projects already won progressed, revenue was ¥2.75 billion (up ¥359 million year on year, or 15.0%), and segment profit was ¥132 million (up ¥7 million, or 5.6%).」
In the heavy temporary construction business, revenue and segment profit both increased year on year as projects already won progressed. - FY2022-Q3RestatedAnnual report
「Progress on awarded construction projects resulted in revenue of ¥2.039 billion, up ¥193 million, or 10.5%. However, fewer highly profitable projects brought segment profit to ¥73 million, down ¥69 million, or 48.9%.」
In the heavy temporary works business, progress on awarded projects continued to generate higher revenue, while the decline in highly profitable projects continued to result in a substantial decrease in profit. - FY2022-Q2Lower revenue and profit due to fewer highly profitable projectsAnnual report
「Fewer highly profitable projects resulted in revenue of ¥1.209 billion, down ¥15 million, or 1.3%, and segment profit of ¥56 million, down ¥45 million, or 44.9%.」
The heavy temporary works business posted lower revenue and profit due to fewer highly profitable projects, following the gap between awarded construction projects in the preceding quarter. Revenue declined 1.3% and segment profit fell 44.9%. - FY2022-Q1Lower revenue and profit due to a gap between awarded construction projectsAnnual report
「Due to a gap between awarded construction projects, revenue was ¥503 million, down ¥116 million, or 18.8%, and segment profit was ¥24 million, down ¥21 million, or 46.0%.」
In the heavy temporary works business, revenue and segment profit declined year on year due to a gap between awarded construction projects. - FY2021Lower revenue and profit as redevelopment construction projects took a pauseAnnual report
「The pause in redevelopment construction projects resulted in revenue of ¥2.39 billion, down ¥185 million, or 7.2%, and segment profit of ¥125 million, down ¥22 million, or 15.0%.」
In the heavy temporary works business, the pause in redevelopment construction projects led to a shift from higher profit driven by improved profitability management in the previous fiscal year to lower revenue and profit. - FY2021-Q3Continued higher profit from improved subsidiary profitability despite lower revenueAnnual report
「Revenue edged down 1.2% year on year to ¥1.845 billion, down ¥22 million, while improved profitability at subsidiary 丸建基礎工事㈱ also contributed to segment profit of ¥142 million, up ¥56 million, or 66.3%.」
The heavy temporary works business continued to see marginally lower revenue but higher profit due to improved profitability at subsidiary 丸建基礎工事. - FY2021-Q2Higher profit from improved subsidiary profitability despite continued delays in construction progressAnnual report
「The impact of delays in awarded construction projects and other factors reduced revenue to ¥1.225 billion, down ¥46 million, or 3.7%. However, improved profitability at subsidiary 丸建基礎工事㈱ also contributed to segment profit of ¥101 million, up ¥35 million, or 54.6%.」
Delays in the progress of awarded construction projects continued, while improved subsidiary profitability resulted in higher segment profit despite lower revenue. - FY2021-Q1AdvancedAnnual report
「Progress on highly profitable construction projects resulted in revenue of ¥620 million, up ¥43 million, or 7.5%, and segment profit of ¥45 million, up ¥29 million, or 180.5%.」
In the heavy temporary works business, progress on highly profitable construction projects resulted in a 7.5% increase in revenue and a 180.5% increase in segment profit. - FY2020Full-year revenue decline and profit growthAnnual report
「Heavy temporary works business Revenue edged down 0.6% year on year to ¥2.576 billion, down ¥15 million, while segment profit increased 13.0% to ¥147 million, up ¥17 million, due to improved profitability management.」
The heavy temporary works business posted a slight full-year decline in revenue, while segment profit increased due to improved profitability management. - FY2020-Q3Lower Revenue, Slightly Higher ProfitAnnual report
「Delays in the progress of awarded construction projects and other factors reduced revenue to ¥1.868 billion, down ¥133 million, or 6.6%. However, improved margins on some projects resulted in segment profit of ¥85 million, up ¥0 million, or 0.6%.」
Delays in the progress of awarded construction projects continued, but improved margins resulted in a marginal year-on-year increase in segment profit despite lower revenue. - FY2020-Q2Higher profit from improved margins on some projects despite continued construction delaysAnnual report
「Delays in awarded construction projects and delays in commencement reduced revenue to ¥1.272 billion, down ¥59 million, or 4.5%. However, improved margins on some projects resulted in segment profit of ¥65 million, up ¥11 million, or 21.8%.」
Delays in awarded construction projects and delays in commencement continued, but improved margins on some projects resulted in higher profit despite lower revenue in the heavy temporary works business. - FY2020-Q1RestatedAnnual report
「Delays in the progress and commencement of already-awarded construction projects resulted in revenue of ¥576 million, down ¥70 million, or 10.8%, and segment profit of ¥16 million, down ¥6 million, or 29.1%.」
The company stated that delays in the progress and commencement of already-awarded construction projects continued, reaffirming the existing theme of project delays. - FY2019-Q3Continued lower revenue and profit due to delays in large-scale project progressAnnual report
「Affected by delays in large-scale construction projects in the Tokyo metropolitan area, revenue was ¥2.001 billion, down ¥406 million, or 16.9%, and segment profit was ¥85 million, down ¥29 million, or 25.6%.」
Continued delays in large-scale construction projects in the Tokyo metropolitan area resulted in lower revenue and profit in the heavy temporary works business year on year. - FY2019-Q2Lower revenue and profit due to delays in large-scale project progressAnnual report
「Heavy temporary works business Affected by delays in large-scale construction projects in the Tokyo metropolitan area, revenue was ¥1.331 billion, down ¥204 million, or 13.3%, and segment profit was ¥54 million, down ¥15 million, or 22.3%.」
Delays arose in large-scale construction projects in the Tokyo metropolitan area, resulting in lower revenue and profit in the heavy temporary works business year on year. - FY2019-Q1AdvancedAnnual report
「Revenue from the Company's standalone construction operations was roughly unchanged from the previous year, but strong performance by subsidiary 丸建基礎工事㈱ resulted in revenue of ¥647 million, up ¥21 million, or 3.5%, and segment profit of ¥23 million, up ¥19 million, or 490.6%.」
In the heavy temporary works business, strong performance by subsidiary 丸建基礎工事 resulted in higher revenue and a 490.6% year-on-year increase in segment profit. - FY2018AdvancedAnnual report
「Progress on large-scale construction projects, mainly in the Tokyo metropolitan area, resulted in revenue of ¥3.024 billion, up ¥266 million, or 9.7%, and segment profit of ¥126 million, up ¥84 million, or 198.8%.」
Large-scale construction projects in the Tokyo metropolitan area progressed, resulting in higher full-year revenue and a 198.8% increase in segment profit. - FY2018-Q3AdvancedAnnual report
「Progress on large-scale construction projects, mainly in the Tokyo metropolitan area, resulted in higher revenue and profit, with revenue of ¥2.408 billion, up ¥381 million, or 18.8%, and segment profit of ¥114 million, up ¥99 million, or 646.3%.」
Large-scale construction projects in the Tokyo metropolitan area progressed, resulting in substantial year-on-year increases in revenue and profit in the heavy temporary works business. The business continued to move further into the black from the loss recorded in the same period of the previous year in the preceding quarter. - FY2018-Q2AdvancedAnnual report
「As large-scale projects in the Tokyo metropolitan area received orders in the previous fiscal year progressed steadily, revenue was ¥1.536 billion, up ¥411 million year on year, or 36.6%, and segment profit was ¥69 million, up ¥84 million, turning profitable from a ¥14 million loss in the same period of the previous year.」
Large-scale projects in the Tokyo metropolitan area progressed steadily, and the heavy temporary works business returned to profitability from a loss in the same period of the previous year. - FY2018-Q1RestatedAnnual report
「Progress on large-scale construction projects in the Tokyo metropolitan area remained solid, resulting in revenue of ¥625 million, up ¥43 million, or 7.4%. However, lower margins brought segment profit to ¥3 million, down ¥0 million, or 7.7%, essentially unchanged from the previous year.」
Large-scale construction projects progressed steadily, while lower margins caused segment profit to decline year on year, with project progress and deteriorating profitability occurring simultaneously. - FY2017RestatedAnnual report
「Progress on construction projects, mainly in the Tokyo metropolitan area, resulted in revenue of ¥2.757 billion, up ¥282 million, or 11.4%. However, lower margins, particularly on large-scale projects, brought segment profit to ¥42 million, down ¥51 million, or 54.9%.」
Construction project progress generated higher revenue, while lower margins, particularly on large-scale projects, resulted in a substantial decline in full-year profit. - FY2017-Q3First statedAnnual report
「As construction projects that had been delayed in the first half progressed, revenue increased 1.7% year on year to ¥2.026 billion, up ¥33 million. However, lower margins, particularly on large-scale projects, resulted in segment profit of ¥15 million, down ¥62 million, or 80.3%.」
Construction projects that had been delayed in the first half progressed, but the decline in margins, particularly on large-scale projects, resulted in a significant decrease in profit in the heavy temporary works business.