Decision and Details
The Company filed the notification following approval by the Minister of Land, Infrastructure, Transport and Tourism.Changes to the maximum domestic passenger facility charges at Tokyo International Airport (Haneda)
Preparations for future growth in air travel demand, further improvements to passenger convenience, the opening of new facilities, upgrades to various facilities including passenger boarding bridges, seismic reinforcement measures for material-handling equipment, and rising labor and other costs
Already reflected in the consolidated earnings forecast for the fiscal year ending March 2027, announced on 8 May 2026
| Item | Details |
|---|---|
| Matter Covered | Changes to the maximum domestic passenger facility charges at Tokyo International Airport (Haneda) |
| Decision-Making Body | The Company filed the notification following approval by the Minister of Land, Infrastructure, Transport and Tourism. |
| Decision Date | 23 June 2026 |
| Implementation Date | [First change] From flights departing on or after 1 September 2026 (予定), [Second change] From flights departing on or after 1 May 2027 (予定) |
| Period Covered | From each respective change date onward |
| Amount | Adults: current ¥450, first change ¥580, second change ¥590; children: current ¥220, first change ¥290, second change ¥290. All amounts are per passenger, per use, inclusive of consumption tax. |
| Quantity / scale | Charge per passenger |
| Impact on Business Performance | Already reflected in the consolidated earnings forecast for the fiscal year ending March 2027, announced on 8 May 2026 |
| Reason | Preparations for future growth in air travel demand, further improvements to passenger convenience, the opening of new facilities, upgrades to various facilities including passenger boarding bridges, seismic reinforcement measures for material-handling equipment, and rising labor and other costs |
| Related previous disclosures | The consolidated earnings forecast for the fiscal year ending March 2027 announced on 8 May 2026 |
| Future plans | The North Satellite of Terminal 1 is scheduled to open for service in September 2026, and extension work on the North Satellite of Terminal 2 is scheduled to be completed and open for service in May 2027. The charges will change for flights departing on or after 1 September 2026 and 1 May 2027, respectively. |
Items this document does not state (1)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The changes reflect preparations for future growth in air travel demand, improvements to passenger convenience, construction of new satellite facilities, upgrades to facilities including passenger boarding bridges, seismic reinforcement measures for material-handling equipment, and rising labor and other costs.