Ichinen Holdings (9619) · InitiativeInvestment amount and scheduled completion updated
Relocation of the Chemical Plant
First written in FY2024. . Latest entry: FY2026.
2entries
3years
0from disclosures
How it moved
Same theme, other companies
Relocation of the Chemical Plant to KogaA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2026Investment amount and scheduled completion updatedAnnual report
「Chemicals business, production facilities, ¥7,374 million, amount paid to date ¥2,792 million, June 2024, October 2027」
For the chemicals plant relocation plan, the total planned investment was updated from ¥3,315 million to ¥7,374 million and the scheduled completion date from April 2026 to October 2027. The amount paid to date of ¥2,792 million was also disclosed. - FY2024First statedAnnual report
「Chemicals business, production facilities, ¥3,315 million, March 2024, April 2026」
Newly disclosed the plan to relocate the chemicals business production facilities to Koga, Ibaraki Prefecture. The total planned investment is ¥3,315 million, with work starting in March 2024 and scheduled for completion in April 2026.